Last visit was: 24 Apr 2024, 07:59 It is currently 24 Apr 2024, 07:59

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
Math Expert
Joined: 02 Sep 2009
Posts: 92902
Own Kudos [?]: 618748 [18]
Given Kudos: 81587
Send PM
Most Helpful Reply
Verbal Forum Moderator
Joined: 08 Dec 2013
Status:Greatness begins beyond your comfort zone
Posts: 2101
Own Kudos [?]: 8808 [8]
Given Kudos: 171
Location: India
Concentration: General Management, Strategy
GPA: 3.2
WE:Information Technology (Consulting)
Send PM
General Discussion
User avatar
Current Student
Joined: 18 Oct 2014
Posts: 680
Own Kudos [?]: 1763 [3]
Given Kudos: 69
Location: United States
GMAT 1: 660 Q49 V31
GPA: 3.98
Send PM
User avatar
Manager
Manager
Joined: 19 Dec 2015
Posts: 89
Own Kudos [?]: 395 [1]
Given Kudos: 13
Location: United States
GMAT 1: 720 Q50 V38
GPA: 3.8
WE:Information Technology (Computer Software)
Send PM
Re: 15 Java programmers, working in a constant pace, finish a web page in [#permalink]
1
Kudos
15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the
remainder of the job
15 programmers finish a work in 3 days. So 1 programmer finished the same work in 3*15 = 45 days.
So 1 programmer contributed to 1/45 of the total work per day.

Now, we are told that 9 leave after day1. So total programmers left =6 => Total work contribution per day = 6*1/45 = 2/15
Work finished by now = 1/3. Left = 2/3.

Days required to complete work = (2/3) / (2/15) = 5. Hence the answer is A.
Director
Director
Joined: 20 Feb 2015
Posts: 631
Own Kudos [?]: 711 [2]
Given Kudos: 74
Concentration: Strategy, General Management
Send PM
Re: 15 Java programmers, working in a constant pace, finish a web page in [#permalink]
2
Kudos
15 Java programmers can finish the job in 3 days = 15*3 = 45 programmer days
15 programmers in one day finish 1/3rd of the job , job left = 45-45/3=30 programmer days
programmers left after a day = 6
days required to complete the remaining job = 30/6 = 5 days
Manager
Manager
Joined: 07 May 2015
Posts: 159
Own Kudos [?]: 72 [0]
Given Kudos: 21
Location: India
GMAT 1: 660 Q48 V31
GPA: 3
Send PM
Re: 15 Java programmers, working in a constant pace, finish a web page in [#permalink]
Assume total work is 45units
since 15 people complete work in 3 days so each worker works 1 unit each day

number of units completed on day 1 = 15*1 = 15
amount of work left = 45 - 15 = 30
Number of members that left = 9
Number of members remaining in the team = 15- 9= 6
Thus number of days needed to complete remaining work by remaining team = 30 /6 = 5

Ans :A
User avatar
Manager
Manager
Joined: 18 Jan 2010
Posts: 210
Own Kudos [?]: 997 [2]
Given Kudos: 9
Send PM
Re: 15 Java programmers, working in a constant pace, finish a web page in [#permalink]
2
Kudos
Bunuel wrote:
15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the
remainder of the job?

A. 5.
B. 2.
C. 8.
D. 4.
E. 6.



15 workers complete the work in 3 days.

That means 15 workers do (1/3)rd work in one day.

If after one day some 9 workers left, that means (1/3) work is done.

So (2/3)rd work has to be done.


Now 15 workers do (1/3)rd work in one day.

That means 1 worker does (1/45) work in 1 day
6 workers do (6/45) work in 1 day = (2/15) work in one day.

Days taken to compete 2/3 work:

(2/3) / (2/15) = 5 days.

A is the answer.
Manager
Manager
Joined: 27 May 2014
Status:Never Say Never
Posts: 51
Own Kudos [?]: 24 [1]
Given Kudos: 63
Location: India
Concentration: International Business, Technology
GMAT 1: 640 Q46 V32
GMAT 2: 670 Q49 V33
GPA: 3.89
WE:Information Technology (Computer Software)
Send PM
Re: 15 Java programmers, working in a constant pace, finish a web page in [#permalink]
1
Bookmarks
15 programmers -> 3 days
1 programmer ->45 days
Rate = 1/45

Day 1 : all 15 worked
therefore work done : RT = D
15* (1/45) * 1 = D

D = 1/3
1/3 of the work was done on day 1

Remaining days : 9 programmers quit , 6 remaining
work remaining = 1-1/3 = 2/3
Again, Rt = D
6* (1/45) t = 2/3
t = 5

hence (A)
Intern
Intern
Joined: 25 Jan 2014
Posts: 26
Own Kudos [?]: 30 [0]
Given Kudos: 58
Location: India
Concentration: Marketing, Operations
GMAT 1: 590 Q45 V26
GPA: 3.5
WE:Design (Manufacturing)
Send PM
Re: 15 Java programmers, working in a constant pace, finish a web page in [#permalink]
Given:

3 day's work : x
1 day's work : x/3

Given:
15 people complete the work in 3 days .
After 1 day's work (x/3), 9 people left.
Remaining work = x - x/3 =2x/3

Now ,
1 day's work of 15 persons= x/3
1 day's work of 1 person = x/45.

1 day's work of 6 persons(15-9)= 2x/15.

2x/15 work completed in 1 day.
2x/3 work completed in = 5 days

Question asks how many more days needed to complete the remaining work,therefore 5 more days needed to complete the remaining work.

Answer is A.
Intern
Intern
Joined: 12 Aug 2017
Posts: 3
Own Kudos [?]: 0 [0]
Given Kudos: 47
GMAT 1: 730 Q45 V45
GMAT 2: 710 Q48 V40
GMAT 3: 720 Q44 V45
Send PM
Re: 15 Java programmers, working in a constant pace, finish a web page in [#permalink]
One quick way to solve this:

15 build 1 site in 3 days = 1/3 of the site per day
After 9 leave, 6/15 or 2/5 of original number remain
rate of work per programmer remains constant so time required to do same amount of work per day increases by 5/2 (reciprocal of 2/5)
This means you need 5/2 days to build 1/3 of the site
2/3 of the site remains so you need (5/2)*2 days to build the rest

5 days needed
Manager
Manager
Joined: 07 Jun 2017
Posts: 81
Own Kudos [?]: 19 [0]
Given Kudos: 454
Send PM
Re: 15 Java programmers, working in a constant pace, finish a web page in [#permalink]
FacelessMan wrote:
15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the
remainder of the job
15 programmers finish a work in 3 days. So 1 programmer finished the same work in 3*15 = 45 days.
So 1 programmer contributed to 1/45 of the total work per day.

Now, we are told that 9 leave after day1. So total programmers left =6 => Total work contribution per day = 6*1/45 = 2/15
Work finished by now = 1/3. Left = 2/3.

Days required to complete work = (2/3) / (2/15) = 5. Hence the answer is A.

(2/3) / (2/15) is 10, right?
trying to follow, is it a typo?
thank you
avatar
Intern
Intern
Joined: 14 Sep 2017
Posts: 4
Own Kudos [?]: 0 [0]
Given Kudos: 295
Send PM
Re: 15 Java programmers, working in a constant pace, finish a web page in [#permalink]
Bunuel wrote:
15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the remainder of the job?

A. 5.
B. 2.
C. 8.
D. 4.
E. 6.



As the question asked "how many more days?", shouldn't be answer 5-1=4 days?
Math Expert
Joined: 02 Sep 2009
Posts: 92902
Own Kudos [?]: 618748 [2]
Given Kudos: 81587
Send PM
Re: 15 Java programmers, working in a constant pace, finish a web page in [#permalink]
1
Kudos
1
Bookmarks
Expert Reply
Rupanjel wrote:
Bunuel wrote:
15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the remainder of the job?

A. 5.
B. 2.
C. 8.
D. 4.
E. 6.



As the question asked "how many more days?", shouldn't be answer 5-1=4 days?


Total job to be done = 15*3 = 45 units (1 unit of work is done by 1 worker in 1 day).

After one day, 1/3 of the job (15 units) is done and 30 units is left to be completed by 6 workers. 30 units will be done in 30/6 = 5 days.

Answer: A.
Intern
Intern
Joined: 20 Jun 2017
Posts: 25
Own Kudos [?]: 4 [0]
Given Kudos: 26
GMAT 1: 580 Q36 V32
GMAT 2: 660 Q39 V41
GRE 1: Q159 V160
Send PM
15 Java programmers, working in a constant pace, finish a web page in [#permalink]
Skywalker18 wrote:
Since 15 programmers take 3 days to finish the job , number of programmer days = 15*3 = 45
Work done in 1 day = 15 programmer days
After one day , 6 programmers are left , work remaining = 30 programmer days
Number of days needed to finish the remainder of job = 30 / 6 = 5 days
Answer A


JeffTargetTestPrep The question asks how many more days, is this not 5 days - 3 days required = 2 days?
Senior PS Moderator
Joined: 26 Feb 2016
Posts: 2873
Own Kudos [?]: 5205 [0]
Given Kudos: 47
Location: India
GPA: 3.12
Send PM
15 Java programmers, working in a constant pace, finish a web page in [#permalink]
Hi Mco100,

I think the question asks how much more time the remaining programmers(after 9 leaving)
take in order to finish the work in hand(remaining 30 units).

If the question was asking how many more days, it would be 3, not 2 as the 15 programmers
would have already done one day's work.

Total job to be done = 15*3 = 45 units (assuming each worker does 1 unit of work in 1 day).

After one day, 15 units of the work is done. That same day 9 programmers leave.
There are a total of 6 programmers working to finish the 30 units, thereby completing
the remainder of the work in 5 days. So extra time taken will be \(1+5-3 = 3\)

Hope that helps you!
Senior SC Moderator
Joined: 22 May 2016
Posts: 5330
Own Kudos [?]: 35485 [0]
Given Kudos: 9464
Send PM
15 Java programmers, working in a constant pace, finish a web page in [#permalink]
Expert Reply
Bunuel wrote:
15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the remainder of the job?

A. 5.
B. 2.
C. 8.
D. 4.
E. 6.

For one day there are 15 workers. They finish a fraction of the work. Some people leave. How many [more] days are needed for the new number of workers to finish the remaining work? You could take out the word "more."

That word, though, signals you to find the amount of work already done. It takes 5 days for 6 people to finish what is left. "Five days to finish" is five days more than one day.

Maybe trying individual rate will help. I think the work units and/or group efficiency methods might confuse. The group's numbers change, but the rate at which each person works does not. Fewer people to work equals more time to finish.

Find the rate of an individual programmer.

Just add (# of workers) to LHS in the standard (\(rt=W\)) formula. To find individual rate, you have to use t = 3 days

(# of workers * r * t) = W
# of workers = 15, \(r\) = ??, \(t = 3\), \(W = 1\)

\((15 * r * 3) = 1\)
\(45r = 1\)
\(r = \frac{1}{45}\)

At that individual programmer's rate, in ONE day, the amount of work that 15 workers will finish, (# * r * t) = W:

\((15 *\frac{1}{45} * 1) =(\frac{15}{45}) =(\frac{1}{3})\)
of work is finished.

\(\frac{2}{3}\) of work remains

But nine workers have gone. Use individual rate for the new number of workers.

How many [] days are needed for 6 workers to finish the remaining \(\frac{2}{3}\) of W?

(# of workers * r * t) = W
# of workers = 6, \(r =\frac{1}{45}\),\(t\) = ??, \(W =\frac{2}{3}\)

Time needed: \((6 *\frac{1}{45} * t)\) = \(\frac{2}{3}\)

\((\frac{6}{45}t) = \frac{2}{3}\)

\(t = (\frac{2}{3}) * (\frac{45}{6})\)

\(t\) = 5 days

Total days:
ONE DAY for 15 people to finish 1/3, and
FIVE DAYS for 6 people to finish 2/3

1 + 5 = 6 days' total.

After the first day (subtract it from the total days) it takes: (6 - 1) = 5 MORE days

Hope it helps!
Intern
Intern
Joined: 28 Sep 2017
Posts: 18
Own Kudos [?]: 4 [0]
Given Kudos: 5
Location: India
Concentration: Technology, General Management
GPA: 3.5
WE:Information Technology (Computer Software)
Send PM
Re: 15 Java programmers, working in a constant pace, finish a web page in [#permalink]
one day work for one programmer = 1/45
one day work for 15 programmer = 15/45
remaining work = 30/45
remaining java programmer = 6
one day work of 6 java programmer = 6/45
so total days needed = 30/6 = 5 days
Director
Director
Joined: 13 Mar 2017
Affiliations: IIT Dhanbad
Posts: 628
Own Kudos [?]: 589 [0]
Given Kudos: 88
Location: India
Concentration: General Management, Entrepreneurship
GPA: 3.8
WE:Engineering (Energy and Utilities)
Send PM
Re: 15 Java programmers, working in a constant pace, finish a web page in [#permalink]
Bunuel wrote:
15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the remainder of the job?

A. 5.
B. 2.
C. 8.
D. 4.
E. 6.


15 Java programmer complete a work in 3 days ..
1 Java programmer complete the work in 45 days..

Amount of work completed by 1 Java programmer in 1 day = 1/45

So, on 1st day amount of work completed = 1/45 * 15 = 1/3
Amount of work left at the end of the 1st day = 2/3
No. of programmers left after 1st day = 6

No. of extra days = (2/3)/(1/45* 6 ) = 5 days.

Answer A
Target Test Prep Representative
Joined: 14 Oct 2015
Status:Founder & CEO
Affiliations: Target Test Prep
Posts: 18754
Own Kudos [?]: 22044 [0]
Given Kudos: 283
Location: United States (CA)
Send PM
Re: 15 Java programmers, working in a constant pace, finish a web page in [#permalink]
Expert Reply
Bunuel wrote:
15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the remainder of the job?

A. 5.
B. 2.
C. 8.
D. 4.
E. 6.



We know that the daily rate of 15 workers is ⅓ of the job. To find the daily rate of 6 workers, then, we can set up the following proportion:

15/(1/3) = 6/x

45 = 6/x

45x = 6

x = 6/45 = 2/15 (This is the daily rate of 6 workers.)

Since after 1 day of work 1/3 of the job is completed, the 6 workers now have to complete the remaining 2/3 of the job at the rate of 2/15 of the job per day.

We use the formula work = rate x time. We let x = the time it will take the 6 workers to finish ⅔ of the job.

2/3 = (2/15)(x)

30/6 = x

x = 5

Answer: A
User avatar
Intern
Intern
Joined: 06 Mar 2019
Posts: 6
Own Kudos [?]: 0 [0]
Given Kudos: 2
Send PM
Re: 15 Java programmers, working in a constant pace, finish a web page in [#permalink]
Bunuel wrote:
15 Java programmers, working in a constant pace, finish a web page in 3 days. If after one day, 9 programmers quit, how many more days are needed to finish the remainder of the job?

A. 5.
B. 2.
C. 8.
D. 4.
E. 6.

So - 15 programmers need 3 days
1 programmer needs 15 multiplied by 3 = 45 days
after 15 programmers worked for 1 day - they worked 15 days that are connected to 1 programmer
then 45-15 = 30 days left for one programmer
if 6 programmers are left
then 30/6 = 5 days
Answer A
GMAT Club Bot
Re: 15 Java programmers, working in a constant pace, finish a web page in [#permalink]
 1   2   
Moderators:
Math Expert
92902 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne