Find all School-related info fast with the new School-Specific MBA Forum

It is currently 29 Jul 2015, 22:17
GMAT Club Tests

Close

GMAT Club Daily Prep

Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Events & Promotions

Events & Promotions in June
Open Detailed Calendar

4 workers can produce x units in 6 days. How many workers

  Question banks Downloads My Bookmarks Reviews Important topics  
Author Message
CEO
CEO
avatar
Joined: 15 Aug 2003
Posts: 3467
Followers: 61

Kudos [?]: 728 [0], given: 781

4 workers can produce x units in 6 days. How many workers [#permalink] New post 09 Oct 2003, 15:36
00:00
A
B
C
D
E

Difficulty:

(N/A)

Question Stats:

0% (00:00) correct 0% (00:00) wrong based on 0 sessions
This topic is locked. If you want to discuss this question please re-post it in the respective forum.

4 workers can produce x units in 6 days. How many workers are needed to produce 3x units in 4 days?
Intern
Intern
avatar
Joined: 29 Aug 2003
Posts: 49
Location: Detroit, MI
Followers: 0

Kudos [?]: 2 [0], given: 0

Re: PS : Work [#permalink] New post 09 Oct 2003, 16:10
4 workers - x units - 6 days

24 workers - x units - 1 day
72 workers - 3x units - 1 day

13 workers - 3x units - 4 days

Ans. 13 workers.
Intern
Intern
avatar
Joined: 29 Aug 2003
Posts: 49
Location: Detroit, MI
Followers: 0

Kudos [?]: 2 [0], given: 0

Re: PS : Work [#permalink] New post 09 Oct 2003, 17:11
wonder_gmat wrote:
amarsesh wrote:
4 workers - x units - 6 days

24 workers - x units - 1 day
72 workers - 3x units - 1 day

13 workers - 3x units - 4 days

Ans. 13 workers.


I think you meant 18?!? 72/4 = 18


Yes, This tells me that I should eat properly before I take the exam. Hunger seems to be having adverse effects on my thinking.

Sorry guys. I will be careful from now on.

Answer should be 18.

Amar.
Re: PS : Work   [#permalink] 09 Oct 2003, 17:11
Display posts from previous: Sort by

4 workers can produce x units in 6 days. How many workers

  Question banks Downloads My Bookmarks Reviews Important topics  


GMAT Club MBA Forum Home| About| Privacy Policy| Terms and Conditions| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group and phpBB SEO

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.