Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Events & Promotions

Events & Promotions in June
Open Detailed Calendar

6 workers should finish a job in 8 days. After 3 days came 4

  Question banks Downloads My Bookmarks Reviews Important topics  
Author Message
TAGS:
Manager
Manager
avatar
Status: Working hard to score better on GMAT
Joined: 02 Oct 2012
Posts: 92
Location: Nepal
Concentration: Finance, Entrepreneurship
GPA: 3.83
WE: Accounting (Consulting)
Followers: 0

Kudos [?]: 42 [0], given: 23

6 workers should finish a job in 8 days. After 3 days came 4 [#permalink] New post 26 May 2013, 08:20
00:00
A
B
C
D
E

Difficulty:

  45% (medium)

Question Stats:

54% (02:14) correct 46% (01:39) wrong based on 94 sessions
6 workers should finish a job in 8 days. After 3 days came 4 workers join them. How many days do they need to finish the same job?

A. 3
B. 4
C. 5
D. 6
E. 7

I do not have the OA. sorry for the inconvenience....
[Reveal] Spoiler: OA

_________________

Do not forget to hit the Kudos button on your left if you find my post helpful.

Expert Post
Math Expert
User avatar
Joined: 02 Sep 2009
Posts: 19093
Followers: 3404

Kudos [?]: 24875 [0], given: 2697

Re: 6 workers should finish a job in 8 days. After 3 days came 4 [#permalink] New post 26 May 2013, 08:36
Expert's post
atalpanditgmat wrote:
6 workers should finish a job in 8 days. After 3 days came 4 workers join them. How many days do they need to finish the same job?

A. 3
B. 4
C. 5
D. 6
E. 7

I do not have the OA. sorry for the inconvenience....


There are 6*8=48 units of work to be done (1 unit done by 1 worker in 1 day).

After 3 days 3*6=18 units are done and 30 units left to be done.

Now, 6+4=10 workers can do 30 units of the work in 30/10=3 days.

Answer: A.

Hope it's clear.
_________________

NEW TO MATH FORUM? PLEASE READ THIS: ALL YOU NEED FOR QUANT!!!

PLEASE READ AND FOLLOW: 11 Rules for Posting!!!

RESOURCES: [GMAT MATH BOOK]; 1. Triangles; 2. Polygons; 3. Coordinate Geometry; 4. Factorials; 5. Circles; 6. Number Theory; 7. Remainders; 8. Overlapping Sets; 9. PDF of Math Book; 10. Remainders; 11. GMAT Prep Software Analysis NEW!!!; 12. SEVEN SAMURAI OF 2012 (BEST DISCUSSIONS) NEW!!!; 12. Tricky questions from previous years. NEW!!!;

COLLECTION OF QUESTIONS:
PS: 1. Tough and Tricky questions; 2. Hard questions; 3. Hard questions part 2; 4. Standard deviation; 5. Tough Problem Solving Questions With Solutions; 6. Probability and Combinations Questions With Solutions; 7 Tough and tricky exponents and roots questions; 8 12 Easy Pieces (or not?); 9 Bakers' Dozen; 10 Algebra set. ,11 Mixed Questions, 12 Fresh Meat

DS: 1. DS tough questions; 2. DS tough questions part 2; 3. DS tough questions part 3; 4. DS Standard deviation; 5. Inequalities; 6. 700+ GMAT Data Sufficiency Questions With Explanations; 7 Tough and tricky exponents and roots questions; 8 The Discreet Charm of the DS ; 9 Devil's Dozen!!!; 10 Number Properties set., 11 New DS set.


What are GMAT Club Tests?
25 extra-hard Quant Tests

Get the best GMAT Prep Resources with GMAT Club Premium Membership

Manager
Manager
User avatar
Joined: 18 May 2012
Posts: 51
Concentration: Finance, Marketing
GMAT 1: 600 Q47 V25
GMAT 2: 670 Q49 V32
GMAT 3: 750 Q50 V41
Followers: 4

Kudos [?]: 48 [0], given: 15

Re: 6 workers should finish a job in 8 days. After 3 days came 4 [#permalink] New post 26 May 2013, 09:06
Let Rate of one worker be R
=> (6*R)*8 = 1 (Rate * Time = work)
=> R = 1/48
=> Work remaining after 3 days
1 - (3*6)/48 = 30/48

After 4 ppl joined in
((6+4)*Time)/48 = 30/48
Time = 3 days to finish the task
IMO A
_________________

while(1) { "I Love GMAT" . "I Hate GMAT" } .. BREAK .. Thank god this is over, but now I miss it!!
My Debrief - Broken Shackles 600-750 http://gmatclub.com/forum/broken-shackles-600-to-170870.html

1 KUDOS received
Intern
Intern
avatar
Joined: 17 Jun 2013
Posts: 1
Followers: 0

Kudos [?]: 1 [1] , given: 0

Re: 6 workers should finish a job in 8 days. After 3 days came 4 [#permalink] New post 19 Jun 2013, 11:17
1
This post received
KUDOS
I agree with the math of both of the previous answers, just a question regarding wording: the question asks for "How many days do they need to finish the same job?," which in my mind is the 3 days that the 6 workers use, PLUS the 3 days that the 10 workers use, making the answer D. Thoughts?
Intern
Intern
avatar
Joined: 29 Apr 2013
Posts: 1
Followers: 0

Kudos [?]: 0 [0], given: 0

Re: 6 workers should finish a job in 8 days. After 3 days came 4 [#permalink] New post 19 Jun 2013, 11:33
Completely agree with Jeffcarl... I got 3+3 =6 days...

Posted from my mobile device Image
1 KUDOS received
Manager
Manager
avatar
Joined: 09 Apr 2013
Posts: 214
Location: United States
Concentration: Finance, Economics
GMAT 1: 710 Q44 V44
GMAT 2: 740 Q48 V44
GPA: 3.1
WE: Sales (Mutual Funds and Brokerage)
Followers: 4

Kudos [?]: 56 [1] , given: 40

Re: 6 workers should finish a job in 8 days. After 3 days came 4 [#permalink] New post 19 Jun 2013, 14:36
1
This post received
KUDOS
jeffcarl wrote:
I agree with the math of both of the previous answers, just a question regarding wording: the question asks for "How many days do they need to finish the same job?," which in my mind is the 3 days that the 6 workers use, PLUS the 3 days that the 10 workers use, making the answer D. Thoughts?


I originally picked D as well, for the same reason.. but after reviewing it again.


"how many days do they need to finish the same project?"

well the project as a whole takes 6 days, but only 3 days left to finish it.
Expert Post
Math Expert
User avatar
Joined: 02 Sep 2009
Posts: 19093
Followers: 3404

Kudos [?]: 24875 [0], given: 2697

Re: 6 workers should finish a job in 8 days. After 3 days came 4 [#permalink] New post 20 Jun 2013, 03:06
Expert's post
dave785 wrote:
jeffcarl wrote:
I agree with the math of both of the previous answers, just a question regarding wording: the question asks for "How many days do they need to finish the same job?," which in my mind is the 3 days that the 6 workers use, PLUS the 3 days that the 10 workers use, making the answer D. Thoughts?


I originally picked D as well, for the same reason.. but after reviewing it again.


"how many days do they need to finish the same project?"

well the project as a whole takes 6 days, but only 3 days left to finish it.


Yes, that's correct. The question asks: "how many days do they need to finish the same job?"
_________________

NEW TO MATH FORUM? PLEASE READ THIS: ALL YOU NEED FOR QUANT!!!

PLEASE READ AND FOLLOW: 11 Rules for Posting!!!

RESOURCES: [GMAT MATH BOOK]; 1. Triangles; 2. Polygons; 3. Coordinate Geometry; 4. Factorials; 5. Circles; 6. Number Theory; 7. Remainders; 8. Overlapping Sets; 9. PDF of Math Book; 10. Remainders; 11. GMAT Prep Software Analysis NEW!!!; 12. SEVEN SAMURAI OF 2012 (BEST DISCUSSIONS) NEW!!!; 12. Tricky questions from previous years. NEW!!!;

COLLECTION OF QUESTIONS:
PS: 1. Tough and Tricky questions; 2. Hard questions; 3. Hard questions part 2; 4. Standard deviation; 5. Tough Problem Solving Questions With Solutions; 6. Probability and Combinations Questions With Solutions; 7 Tough and tricky exponents and roots questions; 8 12 Easy Pieces (or not?); 9 Bakers' Dozen; 10 Algebra set. ,11 Mixed Questions, 12 Fresh Meat

DS: 1. DS tough questions; 2. DS tough questions part 2; 3. DS tough questions part 3; 4. DS Standard deviation; 5. Inequalities; 6. 700+ GMAT Data Sufficiency Questions With Explanations; 7 Tough and tricky exponents and roots questions; 8 The Discreet Charm of the DS ; 9 Devil's Dozen!!!; 10 Number Properties set., 11 New DS set.


What are GMAT Club Tests?
25 extra-hard Quant Tests

Get the best GMAT Prep Resources with GMAT Club Premium Membership

Re: 6 workers should finish a job in 8 days. After 3 days came 4   [#permalink] 20 Jun 2013, 03:06
    Similar topics Author Replies Last post
Similar
Topics:
5 Probability of deaths after 4 days score780 2 01 Apr 2013, 00:18
4 Experts publish their posts in the topic If a group of 5 skilled workers take 3 hours to finish a job ikokurin 4 17 Apr 2012, 00:15
13 men and 7 boys can finish a job in 7 days, while 6 boys nfa1rhp 4 22 Jul 2007, 12:08
6 Experts publish their posts in the topic A and B working together can finish a job in d days. If A Himalayan 12 14 Jul 2007, 17:58
13 men and 7 boys can finish a job in 7 days, while 6 boys krisrini 5 05 Jan 2006, 03:23
Display posts from previous: Sort by

6 workers should finish a job in 8 days. After 3 days came 4

  Question banks Downloads My Bookmarks Reviews Important topics  


GMAT Club MBA Forum Home| About| Privacy Policy| Terms and Conditions| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group and phpBB SEO

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.