A and B together can do a peace of work in 12 days,which B [#permalink]
05 Feb 2007, 11:30
A and B together can do a peace of work in 12 days,which B and C together can do in 16 days.After A has been working at it for 5 Days and B for 7 Days,C finishes in 13 days.In how many days C alone will do the work?
|
|
|
|
|
|
|
VP
Joined: 09 Jan 2007
Posts: 1046
Location: New York, NY
Schools: Chicago Booth Class of 2010
Followers: 9
Kudos [?]:
156
[0], given: 3
|
I Think this PS would be easily solved by changing the answers in the equations. Don't you have them?
|
|
|
|
|
|
Senior Manager
Joined: 04 Jan 2006
Posts: 282
Followers: 1
Kudos [?]:
14
[0], given: 0
|
sravan_m444 wrote: A and B together can do a peace of work in 12 days,which B and C together can do in 16 days.After A has been working at it for 5 Days and B for 7 Days,C finishes in 13 days.In how many days C alone will do the work?
Assuming everybody works at constant rate and independent from each other.
When A works for 5 days and B works for 7 days, we can conclude that A and B work together for 5 days and B works alone for 2 days. And
Work Rate(A+B) = 1/12 (work/day)
Thus, Work is done by A and B for 5 days together = 5 days x 1/12 (work/day) = 5/12 work
When B works for 7-5 = 2 days and C works for 13 day, we can conclude that B and C work together for 2 days and C work alone for 13 - 2 = 11 days.
Work Rate(B+C) = 1/16 (work/day)
Thus, Work is done by B and C for 2 days = 2 days x 1/16 (work/day) = 1/8 work
The remaining job = 1 - 5/12 - 1/8 = (24 - 10 - 3)/24 = 11/24 work
C can finish this part of work within 11 days. Therefore, the work rate for C = 11/24 (work) x 1/11(1/day) = 1/24 (work/day)
Or C can finish one work in = 24 days
Hope this is right.
|
|
|
|
|
|
Intern
Joined: 20 Jan 2007
Posts: 18
Followers: 0
Kudos [?]:
0
[0], given: 0
|
nice answer devilmirror, but i'm not sure if it accurately represents the stem:
"After A has been working at it for 5 Days and B for 7 Days", then C has 13 days left...
It seems to me that A,B and C work as in a sequence: first A, second B and then C.
ARe you sure that A and B can work together?
|
|
|
|
|
|
Manager
Joined: 10 Dec 2005
Posts: 114
Followers: 1
Kudos [?]:
2
[0], given: 0
|
I solved it like this
Let's say rate of A is R1 work/day,
rate of B is R2 work/day, and
rate of C is R3 work/day
Based on the information we have we know that
R1 + R2 = 1/12 ---------------------- 1
R2 + R3 = 1/16----------------------- 2
5R1 + 7R2 + 13R3 = 1 -------------- 3
Let's solve equation 3 for R2
5(1/12 - R2) + 7R2 + 13(1/16 - R2) = 1
5/12 - 5R2 + 7R2 + 13/16 - 13R2 = 1
5/12 + 13/16 -11R2 = 1
Therefore, 11R2 = 5/12 + 13/16
R2 = 1/11(5/12 + 13/16)
R2 = 0.11
We need to find R3 though, we know from 2 that
R3 = 1/16 - R2
R3 = 1/16 - 0.11
R3 = -0.0475
But rate cannot be negative hence
R3 = 0.0475 w/day
Hence in order to finish 1 work R3 will take 1/0.0475 = 21 days
_________________
"Live as if you were to die tomorrow. Learn as if you were to live forever." - Mahatma Gandhi
|
|
|
|
|
|
Manager
Joined: 10 Dec 2005
Posts: 114
Followers: 1
Kudos [?]:
2
[0], given: 0
|
sravan_m444, can you validate the answer please
_________________
"Live as if you were to die tomorrow. Learn as if you were to live forever." - Mahatma Gandhi
|
|
|
|
|
|
Director
Joined: 12 Jun 2006
Posts: 544
Followers: 1
Kudos [?]:
6
[0], given: 1
|
This is kind of vague (at least for me). Are A,B and C working in succession or in unison?
|
|
|
|
|
|
Manager
Joined: 10 Dec 2005
Posts: 114
Followers: 1
Kudos [?]:
2
[0], given: 0
|
I solved it considering succession
_________________
"Live as if you were to die tomorrow. Learn as if you were to live forever." - Mahatma Gandhi
|
|
|
|
|
|
Senior Manager
Joined: 04 Jan 2006
Posts: 282
Followers: 1
Kudos [?]:
14
[0], given: 0
|
pau.sabria wrote: nice answer devilmirror, but i'm not sure if it accurately represents the stem:
"After A has been working at it for 5 Days and B for 7 Days", then C has 13 days left...
It seems to me that A,B and C work as in a sequence: first A, second B and then C.
ARe you sure that A and B can work together?
Hi pau.sabria,
Altough, A, B, and C work as sequence but you can consider them working to gether on the same days and use the rate provide from the question. Just keep in mind that the time that they work will be 2 time faster.
Here the prove.
Assuming A's work rate = 1/a (work/day)
Assuming B's work rate = 1/b (work/day)
If A works for T day the work that A does = T/a work
If B also works for T day the work that B does = T/b work
Total work done = T/a + T/b
However, if A and B working together they will use T day to finish this job.
Work rate = (T/a + T/b)/T = (1/a + 1/b)
The equation above is the work rate of A + B combined!
Therefore, we can safely conclude that.
If A work on T day and B work on T day seperately, this will equal to A and B working together for T day.
Using the prove above to solve that question and the answer is 24.
|
|
|
|
|
|
Manager
Joined: 10 Dec 2005
Posts: 114
Followers: 1
Kudos [?]:
2
[0], given: 0
|
devilmirror, Can you look at my solution? I think the answer is 21
_________________
"Live as if you were to die tomorrow. Learn as if you were to live forever." - Mahatma Gandhi
|
|
|
|
|
|
Senior Manager
Joined: 04 Jan 2006
Posts: 282
Followers: 1
Kudos [?]:
14
[0], given: 0
|
amorpheus wrote: I solved it like this
Let's say rate of A is R1 work/day, rate of B is R2 work/day, and rate of C is R3 work/day
Based on the information we have we know that
R1 + R2 = 1/12 ---------------------- 1 R2 + R3 = 1/16----------------------- 2 5R1 + 7R2 + 13R3 = 1 -------------- 3
Let's solve equation 3 for R2
5(1/12 - R2) + 7R2 + 13(1/16 - R2) = 1
5/12 - 5R2 + 7R2 + 13/16 - 13R2 = 1
5/12 + 13/16 -11R2 = 1
Therefore, 11R2 = 5/12 + 13/16 R2 = 1/11(5/12 + 13/16) R2 = 0.11
We need to find R3 though, we know from 2 that R3 = 1/16 - R2 R3 = 1/16 - 0.11 R3 = -0.0475
But rate cannot be negative hence R3 = 0.0475 w/day Hence in order to finish 1 work R3 will take 1/0.0475 = 21 days
Amorpheus, you set the equation correctly but you solved it wrong.
R1 + R2 = 1/12 ---------------------- 1
R2 + R3 = 1/16----------------------- 2
5R1 + 7R2 + 13R3 = 1 -------------- 3
5(1/12 - R2) + 7R2 + 13(1/16 - R2) = 1
5/12 - 5R2 + 7R2 + 13/16 - 13R2 = 1
5/12 + 13/16 -11R2 = 1
Therefore, 11R2 = 5/12 + 13/16 - 1 {you missed -1 this line}
11R2 = (20 + 39 - 48)/48 = 11/48
R2 = 1/48
Therefore R3 = C's work rate = 1/16 - 1/48 = (3-1)/48 = 2/48 = 1/24 (work/day)
C will use 24 days to finish this job.
Same as my answer.
I believe some people may like this method better than mine.
Last edited by devilmirror on 05 Feb 2007, 18:36, edited 1 time in total.
|
|
|
|
|
|
Manager
Joined: 10 Dec 2005
Posts: 114
Followers: 1
Kudos [?]:
2
[0], given: 0
|
oh bummer haste creates waste I always do that... I see it now... yeah I think my method is easy to understand and probably quicker also.
Thanks for pointing that out.
_________________
"Live as if you were to die tomorrow. Learn as if you were to live forever." - Mahatma Gandhi
|
|
|
|
|
|
Senior Manager
Joined: 04 Jan 2006
Posts: 282
Followers: 1
Kudos [?]:
14
[0], given: 0
|
amorpheus wrote: oh bummer haste creates waste I always do that... I see it now... yeah I think my method is easy to understand and probably quicker also.
Thanks for pointing that out.
 Nah-ah!
I think both methods can solve the question beautifully.
|
|
|
|
|
|
Intern
Joined: 03 Jan 2006
Posts: 28
Followers: 0
Kudos [?]:
0
[0], given: 0
|
Guys answer is 24.I liked both the ways
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|