It is currently Tue May 22, 2012 4:39 pm




   Post new topic Reply to topic      [ 19 posts ]  Bookmark and Share Oldest Best Reply
Author Message
  A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Thu Feb 12, 2009 8:45 pm 
Offline
Senior Manager
Senior Manager

Joined: Thu Aug 02, 2007
Posts: 251
Schools: Life
Followers: 1

Kudos (?): 8 (0), given: 0

GMAT Tests User
A contractor estimated that his 10-men crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, after 5 days of rain, on the 61-st day, he hired 6 more people to finish the project early. If the job was done in 100 days, on how many days after day 60 was it raining?

(A) 4
(B) 5
(C) 6
(D) 7
(E) 8

[Reveal] Spoiler: OA
B

Source: GMAT Club Tests - hardest GMAT questions


  Profile  
 
Kaplan Promo CodeKnewton GMAT Discount CodesManhattan GMAT Discount Codes
  Re: A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Thu Jan 14, 2010 7:37 am 
Offline
Manager
Manager

Joined: Thu Nov 26, 2009
Posts: 189
Followers: 3

Kudos (?): 41 (3), given: 5

GMAT ToolKit User GMAT Tests User
10 men ==> 110 days

1 men ==> 1100 days


till 60 days all 10 men worked for 55 days (5 days rain)

55*10==>550 days

reamining 550 days of work was done with 16 men

1 men ==> 550 days
16 men ==> 550/16 => 34.375 so 35 days

no of days rained after 61st day ==> 40-35 = 5

so my ans is B


  Profile  
 
  Re: A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Wed Sep 30, 2009 1:13 pm 
Offline
Manager
Manager
User avatar

Joined: Wed Jul 22, 2009
Posts: 201
Followers: 1

Kudos (?): 109 (2), given: 18

GMAT Tests User
Here's the answer using a RTW chart.

As the gmatclub explanation says,

Round the number of rainy days down to 5 as with 6 rainy days the 16 men crew would have completed less than 1/2 of the job.


Attachments:
SnapS.jpg
SnapS.jpg [ 16.31 KiB | Viewed 4078 times ]

_________________
Please kudos if my post helps.
  Profile  
 
  Re: A contractor estimated that his 10-men crew [#permalink]
New postPosted: Thu Feb 12, 2009 9:17 pm 
Offline
Director
Director

Joined: Tue May 27, 2008
Posts: 600
Followers: 2

Kudos (?): 82 (0), given: 0

GMAT Tests User
xALIx wrote:
A contractor estimated that his 10-men crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, after 5 days of rain, on the 61-st day, he hired 6 more people to finish the project early. If the job was done in 100 days, on how many days after day 60 was it raining?

* 4
* 5
* 6
* 7
* 8


Total man-days needed = 10 X 110 = 1100

Man-days worked before 61st day =(60-5)X10 = 550

Man-days worked after 61st day = 16 X (40-x), where x is the number of days it rained after day 60.

1100 = 550 + 16(40-x)

16x = 90 ---> x = 5.6....

number of days it rained after day 60 = 5 ... option B.


  Profile  
 
  Re: A contractor estimated that his 10-men crew [#permalink]
New postPosted: Fri Feb 13, 2009 8:49 am 
Offline
Director
Director

Joined: Sun Nov 30, 2008
Posts: 504
Schools: Fuqua
Followers: 8

Kudos (?): 94 (0), given: 15

GMAT Tests User
10 persons take 110 days ==> 10 persons complete 1/110 th work in one day ==> 1 person can work 1/1100 th work per day.

After 5 days of rain, on 61st day means 1o people worked for 55 day in 60 days.

Work completed in 60 days is 55 * 10 / 1100 = 1/2 ==> half of the work is done in 60 days.

6 More people were added to the list. Now with 16 people how much time does it take?

16 /1100 * x = 1 /2 ==> Solving x = 34.37 approximately 35 days.

Of the 40 days remaining 16 people took 35 days to complete the rest of the work.

So there should be 5 days raining.

IMO B.


  Profile  
 
  Re: A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Fri Sep 18, 2009 4:48 am 
Offline
Director
Director
User avatar

Joined: Sat Oct 25, 2008
Posts: 635
Location: Kolkata,India
Followers: 5

Kudos (?): 71 (0), given: 100

GMAT Tests User
The OE states:
Quote:
x=5.625 Round the number of rainy days down to 5 as with 6 rainy days the crew would have worked less than 550 mh and not have completed the job.


Could somebody please explain this part in detail?I rounded it to 6 as this no. should have been in any other context..

_________________
countdown-beginshas-ended-85483-40.html#p649902


  Profile  
 
  Re: A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Fri Sep 18, 2009 6:05 am 
Offline
Current Student

Joined: Thu Sep 17, 2009
Posts: 102
WE 1: 5- hr
Followers: 1

Kudos (?): 2 (0), given: 1

well,
I solved the question a little bit differently but I think it can help you about the explanation,
it took 34,37 days for 16 workers to finish the left over job without any rainy days.
the whole job was completed in 100 days,
the first 10 worker group worked for 60 days (55+5rainy), so total time spent with 16 workers was 40 (100-60),
so we are left with the days that people worked for 34,37 which we round up to 35 because even if they don't work the whole day they were able work in some part of that day so we understand it didn't rain that day, too.
so the number of days it rained is 40-35=5


  Profile  
 
  Re: A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Fri Sep 18, 2009 6:00 pm 
Offline
Director
Director
User avatar

Joined: Sat Oct 25, 2008
Posts: 635
Location: Kolkata,India
Followers: 5

Kudos (?): 71 (0), given: 100

GMAT Tests User
ya i was having trouble with the last part as i rounded it to 6..its pretty tricky..does it mean that if the 5.6 goes to 6 it means it rained for MORE days n' so the workers would take MORE than 100 days to complete?Thats the reason we are rounding down?

_________________
countdown-beginshas-ended-85483-40.html#p649902


  Profile  
 
  Re: A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Thu Jan 14, 2010 7:59 am 
Offline
Intern
Intern

Joined: Mon Nov 02, 2009
Posts: 21
Followers: 0

Kudos (?): 1 (0), given: 9

10 persons take 110 days ==> 10 persons complete 1/110 th work in one day ==> 1 person can work 1/1100 th work per day.

After 5 days of rain, on 61st day---->>>> 10 people worked for 55 day in 60 days.

Work completed in 60 days is 55 * 10 / 1100 = 1/2 total work

Now, we got 16 persons:

16 /1100 * x = 1 /2 ==> Solving x = 34.37 ---->>35 days

40 days 16 persons have worked, so 40-35=5 raining days

B


  Profile  
 
  Re: A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Fri Jan 15, 2010 3:06 am 
Offline
Intern
Intern

Joined: Sat Aug 01, 2009
Posts: 2
Followers: 0

Kudos (?): 0 (0), given: 0

10 men can do a work in 110 days
they worked for 55 days ( 60-5 days)
so they worked for half of days required and hence completed half of the work.
balance half was to be done by 16 men ( 10 + 6 new hires)
10 man can do in 55 days
16 man can do in X days.....(solving we get x = 34.37 ~ 35 days).
40 days - 35 days = 5 days


  Profile  
 
  Re: A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Fri Jan 15, 2010 5:58 am 
Offline
Intern
Intern

Joined: Wed Feb 04, 2009
Posts: 7
Followers: 0

Kudos (?): 1 (0), given: 1

Hi,

If someone wants to avoid decimal/round-off approach then try this alternative

Total work= 1100 man-days
Work done after 60 days (including 5 rainydays)= 550 man-days

After addition on 6 men into the crew total work per day = 16 man-days
therefore, from day 61-100 total work (considering no rainy day in between)= 40*16=640 man-days.
No. of man- hours lost due to rain between day 61-100= 640-550=90 man-days
So, no. of rainy days between day 61-100=90/16= 5 days

Answer (B)

- Jay


  Profile  
 
  Re: A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Wed Jan 19, 2011 6:56 am 
Offline
Manager
Manager

Joined: Sat Oct 23, 2010
Posts: 95
Location: India
Followers: 1

Kudos (?): 11 (0), given: 6

B.

total work required for one person to complete the job= 110 * 10 = 1100
61st day .. 5 days of rain.. hence work done in number of days = 60-5 = 55 d
half of the work remians... = 550 d of work for one person
if 10 + 6 people are deployed to complete work then => 550/16 = 34.4 d
we will consider this as 35 d as full day of work is counted even if you spent an hour working on the last day.

100 - ( 55 + 5d of rain + 35 d of work) = 100 - 95 = 5 d of rain


  Profile  
 
  Re: A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Wed Jan 19, 2011 7:22 am 
Offline
Manager
Manager

Joined: Sat Dec 26, 2009
Posts: 165
Location: United Kingdom
Concentration: Strategy, Technology
GMAT 1: 500 Q45 V16
WE: Consulting (Computer Software)
Followers: 2

Kudos (?): 11 (0), given: 10

GMAT Tests User
10 men completed work in 110 days.
In 55 working days half of the work was done by 10 men.
so, 1 man can do half of the work in 550 days.
16 men can do the same work in 550/16 days = 34.37
Total days to complete = 40
Rainy days = 40-34.37 = 5.63 ~ 5 days.

B is the answer


  Profile  
 
  Re: A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Thu Jan 20, 2011 12:51 am 
Offline
Intern
Intern

Joined: Thu Jan 13, 2011
Posts: 7
Followers: 0

Kudos (?): 0 (0), given: 0

I explain:
Call a man with a working day is Y
Total working part to finish the construction : 10Y x 110 = 1100Y ( without rainny)
According to the data above, It rains from 57th to 61st day-5days.
So, the working is 56x 10Y=560 Y
And, the working requirement is 1100Y
So that, the rest working requirement is 1.100 Y- 560Y = 540 Y
In the data, the construction finish with 100days.
We have working day from 62 from 100days. That mean : 39 working day x 16Y=624Y
The balance is 540 Y and 624Y : 84Y - a day with rain and no working
with 16 man ,
84Y : 16= 5.3
So, B is correct.


  Profile  
 
  Re: A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Thu Jan 20, 2011 1:58 am 
Offline
Manager
Manager
User avatar

Joined: Mon Nov 01, 2010
Posts: 201
Location: India
Concentration: Technology, Marketing
GPA: 3.61
WE: Marketing (Manufacturing)
Followers: 2

Kudos (?): 26 (0), given: 21

GMAT Tests User
tejal777 wrote:
The OE states:
Quote:
x=5.625 Round the number of rainy days down to 5 as with 6 rainy days the crew would have worked less than 550 mh and not have completed the job.


Could somebody please explain this part in detail?I rounded it to 6 as this no. should have been in any other context..





i did the calculation and got the same result.
it should rain for 5.625 day, which we can round off to 6(0.625 can be rounded to1).
apart from this i didnt get the anyidea why OE gives such an explanation.
if it rains for 6 day, then total men work will be = 16*34=544mendays work(which is less than required) but acc to problem it should be 550mendays work.

the answer should be 5.

_________________
kudos me if you like my post.

Attitude determine everything.
all the best and God bless you.


  Profile E-mail  
 
  Re: A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Mon Jan 23, 2012 11:14 am 
Offline
Intern
Intern

Joined: Sun Jun 19, 2011
Posts: 36
Followers: 1

Kudos (?): 0 (0), given: 10

powerka wrote:
Here's the answer using a RTW chart.

As the gmatclub explanation says,

Round the number of rainy days down to 5 as with 6 rainy days the 16 men crew would have completed less than 1/2 of the job.


Could you explain how you got 16/10 for the 2nd part of this table please. The chart does help out significantly in doing the problem I just don't understand that part nor the part where u got the equation below the chart. Also do you know where I can find a thread that discusses using a wrt table? In my Veritas Prep book they don't mention any tables for that equation just manipulating the equation to find the answers. Thanks!


  Profile  
 
  Re: A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Mon Jan 23, 2012 7:43 pm 
Offline
GMAT Club Legend
GMAT Club Legend
User avatar

Joined: Wed Sep 02, 2009
Posts: 7434
Followers: 851

Kudos (?): 4516 (0), given: 213

GMAT Tests User
Top Member of the Month
AzWildcat1 wrote:
powerka wrote:
Here's the answer using a RTW chart.

As the gmatclub explanation says,

Round the number of rainy days down to 5 as with 6 rainy days the 16 men crew would have completed less than 1/2 of the job.


Could you explain how you got 16/10 for the 2nd part of this table please. The chart does help out significantly in doing the problem I just don't understand that part nor the part where u got the equation below the chart. Also do you know where I can find a thread that discusses using a wrt table? In my Veritas Prep book they don't mention any tables for that equation just manipulating the equation to find the answers. Thanks!


Below approach might help to understand better the problem as well as the solution provided by powerka:
A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?
A. 4
B. 5
C. 6
D. 7
E. 8

Given: 10-man crew needs 110 days to complete the construction.

"On the 61-st day, after 5 days of rain ..." --> as it was raining for 5 days then they must have bee working for 55 days thus completed 1/2 of the job, 1/2 is left (55 days of work for 10 men).

Then contractor "hired 6 more people" --> speed of construction increased 1.6 times, so the new 16-man crew needed 55/1.6=~34.4 days to complete the construction, but after they were hired job was done in 100-60=40 days --> so 5 days rained. (They needed MORE than 34 days to finish the job, so if it rained for 6 days they wouldn't be able to finish the job in 100(40) days.)

Answer: B.

This question is also discussed here: a-contractor-estimated-that-his-10-man-126158.html

Hope it helps.

_________________
RESOURCES: [GMAT MATH BOOK]; 1. Triangles; 2. Polygons; 3. Coordinate Geometry; 4. Factorials; 5. Circles; 6. Number Theory

COLLECTION OF QUESTIONS:
PS: 1. Tough and Tricky questions; 2. Hard questions; 3. Hard questions part 2; 4. Standard deviation; 5. Tough Problem Solving Questions With Solutions; 6. Probability and Combinations Questions With Solutions; 7 Tough and tricky exponents and roots questions; 8 12 Easy Pieces (or not?) - NEWEST SET OF TRICKY QUESTIONS!!!; 9 Bakers' Dozen (13 questions) - THIS WEEK'S ADDITION!!!

DS: 1. DS tough questions; 2. DS tough questions part 2; 3. DS tough questions part 3; 4. DS Standard deviation; 5. Inequalities; 6. 700+ GMAT Data Sufficiency Questions With Explanations; 7 Tough and tricky exponents and roots questions; 8 The Discreet Charm of the DS - Latest set of tough DS questions; 9 Devil's Dozen!!! (13 questions) - THIS WEEK'S ADDITION!!!


What are GMAT Club Tests?
25 extra-hard Quant Tests

Facebook TwitterGoogle+LinkedIn

GMAT Club New Features

[May 22] New Update on GMAT Club 2.0 Released!

New Features and Content Coming to GMAT Club on June 5th! See what they are....

 



  Profile  
 
  Re: A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Mon Jan 23, 2012 11:46 pm 
Offline
Intern
Intern

Joined: Sun Jun 19, 2011
Posts: 36
Followers: 1

Kudos (?): 0 (0), given: 10

Thanks Bunuel, that helped and made a lot more sense. I wish I could understand some of these harder problems more, it usually takes me a solid min or 90 seconds to sometimes comprehend and write out the equations or logic of the problems for these harder Q on the quant section


  Profile  
 
  Re: A contractor estimated that his 10-men crew (m07q06) [#permalink]
New postPosted: Tue Jan 24, 2012 4:00 am 
Offline
Intern
Intern

Joined: Tue Jan 10, 2012
Posts: 9
Location: India
GMAT Date: 05-30-2012
Followers: 0

Kudos (?): 5 (0), given: 9

Hi My Solution is :

Total Work = 10 x 110 = 1100 men-days
Work competed = (Days 10 men work for) = 10 x 55 = 550 (no. of days are 55 because 5 days before 61st day are 55 days)
Work remainig = 1100 - 550 = 550.
Now, if 16 men work to complete this remaining work they will take = 550/16 = 34. 3 = ~ 35 Days.

No of days actually taken = 100 - 61 + 1 (this is to calulate the numbers between 100 and 61) = 40
Total no days it rained = 40 - 35 = 5
[B]

_________________
Thanks & Regards
Yody


‘A good plan violently executed now is better than a
perfect plan executed next week.’

- General Georg S. Patton


  Profile  
 
Online
gmatclubot
Display posts from previous:  Sort by  

GMAT Heavy Lifting

GMAT Club Tests

Post new topic Reply to topic  [ 19 posts ] 

 Similar topics   Author   Replies   Views   Last post 
From challenge x A contractor estimated that his 10-man

in GMAT Problem Solving (PS)

Titleist

7

422

Fri Nov 04, 2005 8:52 pm

Work Crew

in GMAT Problem Solving (PS)

TheRob

5

430

Thu Sep 17, 2009 10:33 am

Working as a Contractor

in Ask Admission Consultants

shellarun

5

221

Sun May 16, 2010 8:38 pm

ESTIMATE

in GMAT Math Questions and Intellectual Discussions

LEE SANG IL

1

175

Sun Feb 03, 2008 7:13 am

Estimations

in GMAT Problem Solving (PS)

vwjetty

3

505

Mon Aug 23, 2010 9:32 am





Who is online

Users browsing this forum: No registered users and 0 guests


Search for:
Jump to:





[ Mobile Version ] GMAT Club MBA Forum Home | About | Privacy Policy | Terms and Conditions | GMAT Club Rules | Contact | Sitemap
Powered by phpBB © phpBB Group and phpBB SEO
Kindly note that GMAT (C) is a registered trademark of the Graduate Management Admission Council, and this site has neither been reviewed nor endorsed by GMAC.