Find all School-related info fast with the new School-Specific MBA Forum

It is currently 21 Dec 2014, 12:50

Close

GMAT Club Daily Prep

Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Events & Promotions

Events & Promotions in June
Open Detailed Calendar

A factory was trying out a new process for producing one of

  Question banks Downloads My Bookmarks Reviews Important topics  
Author Message
TAGS:
Manager
Manager
avatar
Joined: 28 Jan 2005
Posts: 83
Followers: 1

Kudos [?]: 27 [0], given: 0

A factory was trying out a new process for producing one of [#permalink] New post 23 Apr 2005, 22:52
00:00
A
B
C
D
E

Difficulty:

(N/A)

Question Stats:

0% (00:00) correct 0% (00:00) wrong based on 0 sessions
A factory was trying out a new process for producing one of its products, with the goal of reducing production costs. A trial production run using the new process showed a 15% reduction in costs compared with past performance using the standard process. The production managers therefore concluded that the new process did produce a cost savings.

Which of the following, if true, casts most doubt on the production manager's conclusion?

A: In the cost reduction project that eventually led to the trial of the new process, production managers had initially been seeking cost reductions of 50%.
B: Anaylysis of the trial of the new process showed that the cost reduction during the trial was entirely attributable to a reduction in the number of finished products rejected by quality control.
C: While the trial was being conducted, production costs at the factory for a smiliar product, produced without benefit of the new process, also showed a 15% reduction.
D: Although some of the factory's managers have been arguing that the product is outdated and ought to be redesigned, the use of the new production process does not involve any changes in the finished product.
E: Since the new process differs from the standard process only in the way in which the stages of production are organized and ordered, the cost of the materials used in the product in the same in both processes.
_________________

Best regards,

Director
Director
User avatar
Joined: 01 Feb 2003
Posts: 854
Location: Hyderabad
Followers: 1

Kudos [?]: 23 [0], given: 0

 [#permalink] New post 23 Apr 2005, 23:18
C should be it
If the old process gave the cost reduction, then the new process did not provide any benefit!
Senior Manager
Senior Manager
User avatar
Joined: 12 Oct 2003
Posts: 265
Location: sydney
Followers: 1

Kudos [?]: 5 [0], given: 0

 [#permalink] New post 23 Apr 2005, 23:22
B or C. i think C is trap.
C, if the process applies to a similar product , it does not mean the same for other product.

B cost reduction is not attributed to new process but to quality control therefore , new process is not required for cost reduction.
_________________

When u r about to make ends meet, someone moves the ends.

VP
VP
avatar
Joined: 26 Apr 2004
Posts: 1225
Location: Taiwan
Followers: 2

Kudos [?]: 125 [0], given: 0

 [#permalink] New post 24 Apr 2005, 05:44
mbamantra wrote:
B or C. i think C is trap.
C, if the process applies to a similar product , it does not mean the same for other product.

B cost reduction is not attributed to new process but to quality control therefore , new process is not required for cost reduction.


Hi, it must be C.

B talked that the practice of new processes was a reduction in the number of finished products rejected by quality control. That strengthens the new processes, saying it is the major factor.

We need to construct another reason to weaken the premise.

So, C is the OA.
VP
VP
avatar
Joined: 30 Sep 2004
Posts: 1490
Location: Germany
Followers: 4

Kudos [?]: 60 [0], given: 0

 [#permalink] New post 24 Apr 2005, 14:15
B)...not the new process but the improvement of the rejected products was responsible for the reduction

i think C) is out because there may be other factor that led to that reduction. so the analogy is too general.
_________________

If your mind can conceive it and your heart can believe it, have faith that you can achieve it.

Manager
Manager
avatar
Joined: 28 Jan 2005
Posts: 83
Followers: 1

Kudos [?]: 27 [0], given: 0

 [#permalink] New post 27 Apr 2005, 04:11
Thanks everyone! The OA is (C).
_________________

Best regards,

  [#permalink] 27 Apr 2005, 04:11
    Similar topics Author Replies Last post
Similar
Topics:
3 Experts publish their posts in the topic One-fifth of the batteries produced by an upstart factory are defectiv Bunuel 4 26 Nov 2014, 06:56
7 Experts publish their posts in the topic A factory was trying out a new process for producing one of Bunuel 1 13 Jun 2014, 06:10
4 A factory was trying out a new process for producing one of Thoughtosphere 5 13 Jun 2013, 15:06
A factory was trying out a new process for producing one of garimavyas 4 12 May 2011, 07:35
try it out.. biggamejames 6 18 Aug 2006, 23:05
Display posts from previous: Sort by

A factory was trying out a new process for producing one of

  Question banks Downloads My Bookmarks Reviews Important topics  


GMAT Club MBA Forum Home| About| Privacy Policy| Terms and Conditions| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group and phpBB SEO

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.