Find all School-related info fast with the new School-Specific MBA Forum

It is currently 19 Apr 2015, 07:45

Close

GMAT Club Daily Prep

Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Events & Promotions

Events & Promotions in June
Open Detailed Calendar

A newer machine, working alone at its constant rate

  Question banks Downloads My Bookmarks Reviews Important topics  
Author Message
TAGS:
2 KUDOS received
Manager
Manager
User avatar
Joined: 07 May 2012
Posts: 76
Location: United States
Followers: 2

Kudos [?]: 65 [2] , given: 23

A newer machine, working alone at its constant rate [#permalink] New post 26 Oct 2013, 13:42
2
This post received
KUDOS
7
This post was
BOOKMARKED
00:00
A
B
C
D
E

Difficulty:

  95% (hard)

Question Stats:

27% (02:52) correct 73% (02:01) wrong based on 245 sessions
A newer machine, working alone at its constant rate, can fill a production order in half the time required by two older machines working together at their constant rates. If the three machines are used together, will they require more than 1 hour to fill a production order?

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour
[Reveal] Spoiler: OA

_________________

Jyothi hosamani

2 KUDOS received
Manager
Manager
User avatar
Joined: 07 May 2012
Posts: 76
Location: United States
Followers: 2

Kudos [?]: 65 [2] , given: 23

Re: A newer machine, working alone at its constant rate [#permalink] New post 26 Oct 2013, 13:43
2
This post received
KUDOS
Hi Bunuel,
Could you please help on the below -

This is from Veritas practice test . I got the answer as "A", but as per veritas , the answer is E . Not sure where I went wrong .
Appreciate if experts can comment on this.

Let A and B , be old machines and C be the new machine .

----------- Rate -------------Tiime------------- Work
A -----------x --------------1/x------------------ 1

B ------------y --------------1/y--------------------1

A+B--------- x+y-----------1/(x+y)------------------ 1

C -----------2(x+y)---------1/2(x+y)------------ 1

combined rate of two old and one new machine is = (x+y)+2(x+y) = 3(x+y)
question : is time taken - i.e 1/3(x+y) >1 ? or (x+y) <1/3 ?

Statement 1 :- (1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

1/x <4 and 1/y <4
x>1/4 and y>1/4

hence x+y>1/2 , which answers our question as "No" x+y is not less than 1/3
Sufficient.

Statement 2 :- (2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour
4(x+y) is the new rate . 1/4(x+y) <1 , hence (x+y) >1/4 . Hence (x+y)<1/3 may or may not be true.
Not sufficient.

I do not understand , where is it that I am going wrong on this one .


-Jyothi
_________________

Jyothi hosamani


Last edited by gmacforjyoab on 27 Oct 2013, 07:35, edited 2 times in total.
Intern
Intern
avatar
Joined: 05 Oct 2013
Posts: 15
Followers: 0

Kudos [?]: 4 [0], given: 0

Re: A newer machine, working alone at its constant rate [#permalink] New post 26 Oct 2013, 17:04
1
This post was
BOOKMARKED
Let x, y be the time for 2 old machines to complete the job and z be the time for the newest machine to complete the same job.
When 2 old machine working together, they finish the job in \(\frac{1}{\frac{1}{x}+ \frac{1}{y}} = \frac{xy}{x+y}\). So \(z= \frac{xy}{2(x+y)}\).
(1) implies that x<8 and y<8. So z<2. If all three machines work together, the time \(\frac{1}{\frac{1}{x} + \frac{1}{y} + \frac{1}{z}}\) is less than 4/3.
(2) implies that z< 2. Similarly, If all three machines work together, the time is less than 4/3.
Answer is E
2 KUDOS received
Intern
Intern
avatar
Status: NOT READY TO GIVE UP
Joined: 24 Apr 2013
Posts: 28
Location: India
Concentration: Strategy, Marketing
GMAT Date: 10-30-2013
WE: Engineering (Other)
Followers: 0

Kudos [?]: 3 [2] , given: 45

Re: A newer machine, working alone at its constant rate [#permalink] New post 27 Oct 2013, 04:16
2
This post received
KUDOS
gmacforjyoab wrote:
Hi Bunuel,
Could you please help on the below -

This is from Veritas practice test . I got the answer as "A", but as per veritas , the answer is E . Not sure where I went wrong .
Appreciate if experts can comment on this.

Let A and B , be old machines and C be the new machine .

----------- Rate -------------Tiime------------- Work
A -----------x --------------1/x------------------ 1

B ------------y --------------1/y--------------------1

A+B--------- x+y-----------(x+y)------------------ 1

C -----------2(x+y)---------1/2(x+y)------------ 1

combined rate of two old and one new machine is = (x+y)=2(x+y) = 3(x+y)
question : is time taken - i.e 1/3(x+y) >1 ? or (x+y) <1/3 ?

Statement 1 :- (1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

1/x <4 and 1/y <4
x>1/4 and y>1/4

hence x+y>1/2 , which answers our question as "No" x+y is not less than 1/3
Sufficient.

Statement 2 :- (2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour
4(x+y) is the new rate . 1/4(x+y) <1 , hence (x+y) >1/4 . Hence (x+y)<1/3 may or may not be true.
Not sufficient.

I do not understand , where is it that I am going wrong on this one .


-Jyothi




the analysis of the argument is wrongly done.

If Old m/c takes T time to complete the work, then the newer one will take T/2

so the equation for combined work will look like:

2/T(for new m/c)+ 2/T(for 2 old m/c)=4/T

Now the asked ques is-weather 4/T>1 or not?

which can be answered using both the given statements....
Manager
Manager
User avatar
Joined: 07 May 2012
Posts: 76
Location: United States
Followers: 2

Kudos [?]: 65 [0], given: 23

Re: A newer machine, working alone at its constant rate [#permalink] New post 27 Oct 2013, 07:28
himang wrote:
gmacforjyoab wrote:
Hi Bunuel,
Could you please help on the below -

This is from Veritas practice test . I got the answer as "A", but as per veritas , the answer is E . Not sure where I went wrong .
Appreciate if experts can comment on this.

Let A and B , be old machines and C be the new machine .

----------- Rate -------------Tiime------------- Work
A -----------x --------------1/x------------------ 1

B ------------y --------------1/y--------------------1

A+B--------- x+y-----------(x+y)------------------ 1

C -----------2(x+y)---------1/2(x+y)------------ 1

combined rate of two old and one new machine is = (x+y)=2(x+y) = 3(x+y)
question : is time taken - i.e 1/3(x+y) >1 ? or (x+y) <1/3 ?

Statement 1 :- (1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

1/x <4 and 1/y <4
x>1/4 and y>1/4

hence x+y>1/2 , which answers our question as "No" x+y is not less than 1/3
Sufficient.

Statement 2 :- (2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour
4(x+y) is the new rate . 1/4(x+y) <1 , hence (x+y) >1/4 . Hence (x+y)<1/3 may or may not be true.
Not sufficient.

I do not understand , where is it that I am going wrong on this one .


-Jyothi




the analysis of the argument is wrongly done.

If Old m/c takes T time to complete the work, then the newer one will take T/2

so the equation for combined work will look like:

2/T(for new m/c)+ 2/T(for 2 old m/c)=4/T

Now the asked ques is-weather 4/T>1 or not?

which can be answered using both the given statements....


Couple of issues in what you have explained above.

1. You cannot assume that time required for both the old machines is the same ( which you have assumed to be T). The problem just says , "work at THEIR CONSTANT RATE" .

2. Secondly , you can add the rates of three machines working together , which gives you a combined rate. But you cannot add the time taken by three machines and call that the combined time .
for instance - Lets say Machine L takes 2 hrs , M takes 2 hrs and N takes 2 hrs to complete a work independently. If they all work together , then as per your analysis , they take 2+2+2=6 hrs to complete . If they all work together , they would definitely complete it in less than 2 hrs.

3. Also, the answer to the question , from what veritas says , is E and not C/D as you mentioned.


-Jyothi
_________________

Jyothi hosamani

Current Student
avatar
Joined: 07 Jan 2013
Posts: 46
Location: India
Concentration: Finance, Strategy
GMAT 1: 570 Q46 V23
GMAT 2: 710 Q49 V38
GPA: 2.9
WE: Information Technology (Computer Software)
Followers: 1

Kudos [?]: 14 [0], given: 23

Re: A newer machine, working alone at its constant rate [#permalink] New post 27 Oct 2013, 20:23
gmacforjyoab wrote:
A newer machine, working alone at its constant rate, can fill a production order in half the time required by two older machines working together at their constant rates. If the three machines are used together, will they require more than 1 hour to fill a production order?

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour



Hi jyothi,

I think picking up few nos for each statements is perhaps the fastest way to do this.Before doing this assume x+y is time taken by older machines and z by new machine

1)for 1st statement the older machines can fill the order in less than 4 hours , take for instance the time taken by 2 older machines be 6 hours,
so half-the production order will be in x+y/2=3 hours

time taken by new machine is 3 hours,

so in 6 hours 1.5 production order is filled
=> 1 production order in= 6/1.5= 4 hours (so answer to the statement is no)

but let us assume time taken by older machines x+y=1/4 hours

so half the prod order = 1/4*1/2=1/8

and z takes (1/4*1/2)=1/8

so in 1/4 hours 1.5 orders


1 prod order in 1/4*1/1.5 (which will be less than 1 hour, so answer is yes)

clearly therefore statment 1 is insufficient
so


2)for the answer to be yes (i,e statement sufficient to state it will take less than 1hour you can pick the same values as in 2 conditio of 1st statement i,e x+y=1/2 hours)

for the yes condition pick time taken by z = 10/6 ,, so if rate doubled it will be able to do in 5/6 hours,,
so x+y= 20/6
so in 30/6 2 orders are completed,

=> 1 order in 5/2 hours (so answer is no as order cannot be completed in less than in 1 hour),,
you can have the same value (z=10/6) and use it for statemet 1 as well.

hence both the values are insufficient.E is correct
_________________

Help with Kudos if I add to your knowledge realm.

Expert Post
1 KUDOS received
Veritas Prep GMAT Instructor
User avatar
Joined: 16 Oct 2010
Posts: 5417
Location: Pune, India
Followers: 1320

Kudos [?]: 6668 [1] , given: 176

Re: A newer machine, working alone at its constant rate [#permalink] New post 06 Nov 2013, 19:55
1
This post received
KUDOS
Expert's post
gmacforjyoab wrote:
Hi Bunuel,
Could you please help on the below -

This is from Veritas practice test . I got the answer as "A", but as per veritas , the answer is E . Not sure where I went wrong .
Appreciate if experts can comment on this.

Let A and B , be old machines and C be the new machine .

----------- Rate -------------Tiime------------- Work
A -----------x --------------1/x------------------ 1

B ------------y --------------1/y--------------------1

A+B--------- x+y-----------1/(x+y)------------------ 1

C -----------2(x+y)---------1/2(x+y)------------ 1

combined rate of two old and one new machine is = (x+y)+2(x+y) = 3(x+y)
question : is time taken - i.e 1/3(x+y) >1 ? or (x+y) <1/3 ?

Statement 1 :- (1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

1/x <4 and 1/y <4
x>1/4 and y>1/4

hence x+y>1/2 , which answers our question as "No" x+y is not less than 1/3
Sufficient.

Statement 2 :- (2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour
4(x+y) is the new rate . 1/4(x+y) <1 , hence (x+y) >1/4 . Hence (x+y)<1/3 may or may not be true.
Not sufficient.

I do not understand , where is it that I am going wrong on this one .


-Jyothi


You misread statement (1).

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.
Each of the older machines cannot fill a production order in less than 4 hrs. They can fill half the production order in less than 4 hrs. The actual time taken by them could be 1 hr, 2 hrs, 3 hrs, 3.9 hrs etc to fill HALF the order. Hence they can fill the complete order is less than 8 hrs.

1/x < 8
1/y < 8
x + y > 1/4
Not sufficient.
_________________

Karishma
Veritas Prep | GMAT Instructor
My Blog

Veritas Prep GMAT course is coming to India. Enroll in our weeklong Immersion Course that starts March 29!

Veritas Prep Reviews

Manager
Manager
User avatar
Joined: 07 May 2012
Posts: 76
Location: United States
Followers: 2

Kudos [?]: 65 [0], given: 23

Re: A newer machine, working alone at its constant rate [#permalink] New post 07 Nov 2013, 05:51
VeritasPrepKarishma wrote:
gmacforjyoab wrote:
Hi Bunuel,
Could you please help on the below -

This is from Veritas practice test . I got the answer as "A", but as per veritas , the answer is E . Not sure where I went wrong .
Appreciate if experts can comment on this.

Let A and B , be old machines and C be the new machine .

----------- Rate -------------Tiime------------- Work
A -----------x --------------1/x------------------ 1

B ------------y --------------1/y--------------------1

A+B--------- x+y-----------1/(x+y)------------------ 1

C -----------2(x+y)---------1/2(x+y)------------ 1

combined rate of two old and one new machine is = (x+y)+2(x+y) = 3(x+y)
question : is time taken - i.e 1/3(x+y) >1 ? or (x+y) <1/3 ?

Statement 1 :- (1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

1/x <4 and 1/y <4
x>1/4 and y>1/4

hence x+y>1/2 , which answers our question as "No" x+y is not less than 1/3
Sufficient.

Statement 2 :- (2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour
4(x+y) is the new rate . 1/4(x+y) <1 , hence (x+y) >1/4 . Hence (x+y)<1/3 may or may not be true.
Not sufficient.

I do not understand , where is it that I am going wrong on this one .


-Jyothi


You misread statement (1).

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.
Each of the older machines cannot fill a production order in less than 4 hrs. They can fill half the production order in less than 4 hrs. The actual time taken by them could be 1 hr, 2 hrs, 3 hrs, 3.9 hrs etc to fill HALF the order. Hence they can fill the complete order is less than 8 hrs.

1/x < 8
1/y < 8
x + y > 1/4
Not sufficient.



Oh right !!
Thank you so much for clarifying !

-Jyothi
_________________

Jyothi hosamani

GMAT Club Legend
GMAT Club Legend
User avatar
Joined: 09 Sep 2013
Posts: 4582
Followers: 283

Kudos [?]: 52 [0], given: 0

Premium Member
Re: A newer machine, working alone at its constant rate [#permalink] New post 17 Nov 2014, 13:16
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
_________________

GMAT Books | GMAT Club Tests | Best Prices on GMAT Courses | GMAT Mobile App | Math Resources | Verbal Resources

Manager
Manager
avatar
Joined: 27 Aug 2014
Posts: 69
Concentration: Finance, Strategy
GPA: 3.9
WE: Analyst (Energy and Utilities)
Followers: 0

Kudos [?]: 27 [0], given: 14

Machines, work/rate problem [#permalink] New post 28 Jan 2015, 13:03
A newer machine, working alone at its constant rate, can fill a production order in half the time required by two older machines working together at their constant rates. If the three machines are used together, will they require more than 1 hour to fill a production order?

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour
Expert Post
Math Expert
User avatar
Joined: 02 Sep 2009
Posts: 26932
Followers: 4152

Kudos [?]: 39910 [0], given: 5310

Re: A newer machine, working alone at its constant rate [#permalink] New post 29 Jan 2015, 03:51
Expert's post
santorasantu wrote:
A newer machine, working alone at its constant rate, can fill a production order in half the time required by two older machines working together at their constant rates. If the three machines are used together, will they require more than 1 hour to fill a production order?

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour


Please search before posting and name topics properly (check rule 3: rules-for-posting-please-read-this-before-posting-133935.html). Thank you.
_________________

NEW TO MATH FORUM? PLEASE READ THIS: ALL YOU NEED FOR QUANT!!!

PLEASE READ AND FOLLOW: 11 Rules for Posting!!!

RESOURCES: [GMAT MATH BOOK]; 1. Triangles; 2. Polygons; 3. Coordinate Geometry; 4. Factorials; 5. Circles; 6. Number Theory; 7. Remainders; 8. Overlapping Sets; 9. PDF of Math Book; 10. Remainders; 11. GMAT Prep Software Analysis NEW!!!; 12. SEVEN SAMURAI OF 2012 (BEST DISCUSSIONS) NEW!!!; 12. Tricky questions from previous years. NEW!!!;

COLLECTION OF QUESTIONS:
PS: 1. Tough and Tricky questions; 2. Hard questions; 3. Hard questions part 2; 4. Standard deviation; 5. Tough Problem Solving Questions With Solutions; 6. Probability and Combinations Questions With Solutions; 7 Tough and tricky exponents and roots questions; 8 12 Easy Pieces (or not?); 9 Bakers' Dozen; 10 Algebra set. ,11 Mixed Questions, 12 Fresh Meat

DS: 1. DS tough questions; 2. DS tough questions part 2; 3. DS tough questions part 3; 4. DS Standard deviation; 5. Inequalities; 6. 700+ GMAT Data Sufficiency Questions With Explanations; 7 Tough and tricky exponents and roots questions; 8 The Discreet Charm of the DS ; 9 Devil's Dozen!!!; 10 Number Properties set., 11 New DS set.


What are GMAT Club Tests?
25 extra-hard Quant Tests

GMAT Club Premium Membership - big benefits and savings

Manager
Manager
avatar
Joined: 27 Aug 2014
Posts: 69
Concentration: Finance, Strategy
GPA: 3.9
WE: Analyst (Energy and Utilities)
Followers: 0

Kudos [?]: 27 [0], given: 14

Re: A newer machine, working alone at its constant rate [#permalink] New post 29 Jan 2015, 12:19
Bunuel wrote:
santorasantu wrote:
A newer machine, working alone at its constant rate, can fill a production order in half the time required by two older machines working together at their constant rates. If the three machines are used together, will they require more than 1 hour to fill a production order?

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour


Please search before posting and name topics properly (check rule 3: rules-for-posting-please-read-this-before-posting-133935.html). Thank you.


Thanks Bunuel for redirecting and also on rules.

Could anybody please give an alternate quick solution for this question?
Expert Post
1 KUDOS received
Veritas Prep GMAT Instructor
User avatar
Joined: 16 Oct 2010
Posts: 5417
Location: Pune, India
Followers: 1320

Kudos [?]: 6668 [1] , given: 176

Re: A newer machine, working alone at its constant rate [#permalink] New post 29 Jan 2015, 21:46
1
This post received
KUDOS
Expert's post
1
This post was
BOOKMARKED
gmacforjyoab wrote:
A newer machine, working alone at its constant rate, can fill a production order in half the time required by two older machines working together at their constant rates. If the three machines are used together, will they require more than 1 hour to fill a production order?

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour


Here is another solution:

New machine takes half the time taken by 2 old machines i.e. rate of new machine is twice the rate of 2 old machines. Say rate of old machine is R. Then rate of 2 old machines is 2R. Then rate of a new machine is 2*2R = 4R.
If all 3 machines work together, their combined rate is R + R + 4R = 6R

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.
This means the old machine takes less than 8 hrs to fill a complete order i.e. its rate is at least 1/8.
R is at least 1/8 so 6R is atleast 6/8 = 3/4. So time taken by all 3 machines together to complete 1 lot is maximum 4/3 hrs. Is it actually less than 1 hr, we can't say. Not sufficient.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour
If rate is 2*4R =8R, time taken is less than 1 hour to complete 1 full production lot. So rate is at least 1/8. This is exactly the same information as obtained in statement 1. This alone will also be insufficient.

Both statements give the same information and are insufficient. So together they will be insufficient.

Answer (E)
_________________

Karishma
Veritas Prep | GMAT Instructor
My Blog

Veritas Prep GMAT course is coming to India. Enroll in our weeklong Immersion Course that starts March 29!

Veritas Prep Reviews

Manager
Manager
avatar
Joined: 27 Aug 2014
Posts: 69
Concentration: Finance, Strategy
GPA: 3.9
WE: Analyst (Energy and Utilities)
Followers: 0

Kudos [?]: 27 [0], given: 14

Re: A newer machine, working alone at its constant rate [#permalink] New post 30 Jan 2015, 10:37
VeritasPrepKarishma wrote:
gmacforjyoab wrote:
A newer machine, working alone at its constant rate, can fill a production order in half the time required by two older machines working together at their constant rates. If the three machines are used together, will they require more than 1 hour to fill a production order?

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour


Here is another solution:

New machine takes half the time taken by 2 old machines i.e. rate of new machine is twice the rate of 2 old machines. Say rate of old machine is R. Then rate of 2 old machines is 2R. Then rate of a new machine is 2*2R = 4R.
If all 3 machines work together, their combined rate is R + R + 4R = 6R

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.
This means the old machine takes less than 8 hrs to fill a complete order i.e. its rate is at least 1/8.
R is at least 1/8 so 6R is atleast 6/8 = 3/4. So time taken by all 3 machines together to complete 1 lot is maximum 4/3 hrs. Is it actually less than 1 hr, we can't say. Not sufficient.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour
If rate is 2*4R =8R, time taken is less than 1 hour to complete 1 full production lot. So rate is at least 1/8. This is exactly the same information as obtained in statement 1. This alone will also be insufficient.

Both statements give the same information and are insufficient. So together they will be insufficient.

Answer (E)



Thanks a lot, Karishma. I find this a bit more easier. +1
Re: A newer machine, working alone at its constant rate   [#permalink] 30 Jan 2015, 10:37
    Similar topics Author Replies Last post
Similar
Topics:
Working alone at its constant rate, machine K took 3 hours caiyun 1 06 Nov 2008, 08:41
Working alone at its own constant rate, a machine seals k marcodonzelli 7 12 Mar 2008, 12:18
Working alone at its own constant rate, a machine seals k $uckafr33 4 02 Oct 2006, 10:39
Working alone at its own constant rate, a machine seals k acfuture 4 28 May 2006, 18:52
Working alone at it's own constant rate, a machine seals K ellisje22 2 03 Jan 2006, 17:45
Display posts from previous: Sort by

A newer machine, working alone at its constant rate

  Question banks Downloads My Bookmarks Reviews Important topics  


GMAT Club MBA Forum Home| About| Privacy Policy| Terms and Conditions| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group and phpBB SEO

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.