Find all School-related info fast with the new School-Specific MBA Forum

It is currently 18 May 2013, 14:19
Customize  |  Hide

Basic Time & Work problems

  Question banks Downloads My Bookmarks Reviews  
Author Message
TAGS:
Intern
Intern
Joined: 04 Sep 2010
Posts: 10
Followers: 0

Kudos [?]: 3 [0], given: 6

Basic Time & Work problems [#permalink] New post 23 Oct 2010, 09:42
00:00

Question Stats:

66% (03:03) correct 33% (03:12) wrong based on 0 sessions
Hi,

I was hoping to get the correct approach for the following types of basic problems in Time & Work.

Type I - Extra number of men required/employed

1) An engineer undertakes a project to build a road 15 km long in 300 days with 45 men employed. After 100 days, only 2.5 km of the road has been completed. Find the (approx.) number of extra men needed to complete the work in time.

a) 43
b) 45
c) 55
d) 68
e) 60

OA -
[Reveal] Spoiler:
D


Type II - when amount paid is included

1) A can do a piece of work in 12 days. A and B complete the work together and were paid Rs. 54 and Rs. 81 respectively. How many days must they have taken to complete the work together?

a) 4 days
b) 4.5 days
c) 4.8 days
d) 5 days
e) 4.2 days

OA -
[Reveal] Spoiler:
C


Type 3 - men leave halfway through work

1) In a fort, there was sufficient food for 200 soldiers for 31 days. After 27 days 120 soldiers left the fort. For how many extra days will the rest of the food last for the remaining soldiers?

a) 12 days
b) 10 days
c) 8 days
d) 6 days

OA -
[Reveal] Spoiler:
D


Any pointers would be helpful.
1 KUDOS received
Senior Manager
Senior Manager
User avatar
Status: Time to step up the tempo
Joined: 24 Jun 2010
Posts: 420
Location: Milky way
Schools: ISB, Tepper - CMU, Chicago Booth, LSB
Followers: 6

Kudos [?]: 75 [1] , given: 50

GMAT Tests User
Re: Basic Time & Work problems [#permalink] New post 23 Oct 2010, 17:44
1
This post received
KUDOS
Type 3 - men leave halfway through work

1) In a fort, there was sufficient food for 200 soldiers for 31 days. After 27 days 120 soldiers left the fort. For how many extra days will the rest of the food last for the remaining soldiers?

a) 12 days
b) 10 days
c) 8 days
d) 6 days






Food Availability
MenDaysQuantity
Given200316200
Till 27 days200275400
From 28th day80x800
[/quote]

Hence the number of days the remaining quantity will last = 10 days. However the original quantity was to last for only 4 more days if none of the soldiers had left.

Hence extra days is 10-4 = 6 days (D).
_________________

:good Support GMAT Club by putting a GMAT Club badge on your blog :thanks


Last edited by ezhilkumarank on 23 Oct 2010, 17:57, edited 1 time in total.
Senior Manager
Senior Manager
User avatar
Status: Time to step up the tempo
Joined: 24 Jun 2010
Posts: 420
Location: Milky way
Schools: ISB, Tepper - CMU, Chicago Booth, LSB
Followers: 6

Kudos [?]: 75 [0], given: 50

GMAT Tests User
Re: Basic Time & Work problems [#permalink] New post 23 Oct 2010, 17:56
Type II - when amount paid is included

1) A can do a piece of work in 12 days. A and B complete the work together and were paid Rs. 54 and Rs. 81 respectively. How many days must they have taken to complete the work together?

a) 4 days
b) 4.5 days
c) 4.8 days
d) 5 days
e) 4.2 days

Given A can do the work in 12 days. Hence A's rate is 1/12.

Also amount payment made to A and B is Rs 54 and Rs 81 respectively -- which is the ratio of 2:3.

Viewing only A's data: Since payment is proportional to the amount of work done.

Fraction of the total work done by A * Days in which A would have completed the work alone.

Hence (2/5) * 12 = 4.8 days. Hence A worked for 4.8 days @ a rate of (1/12) along with B to complete the work.

Answer C (4.8).
_________________

:good Support GMAT Club by putting a GMAT Club badge on your blog :thanks

1 KUDOS received
Veritas Prep GMAT Instructor
User avatar
Joined: 16 Oct 2010
Posts: 3104
Location: Pune, India
Followers: 567

Kudos [?]: 1994 [1] , given: 92

Re: Basic Time & Work problems [#permalink] New post 23 Oct 2010, 18:13
1
This post received
KUDOS
Type I:

To complete 2.5 km in 100 days, we need 45 men
To complete 12.5 km (leftover road) in 100 days, we need 45 x 12.5/2.5 men (It will be 12.5/2.5 and not 2.5/12.5 because more work will need more men. So we have to make 45 greater. Direct variation.) = 225 men

To complete 12.5 km in 100 days we need 225 men.
To complete 12.5 km in 200 days (this is the number of leftover days), we need 225 x 100/200 (Now if we have more days for same work, we need less men so 100/200 to make 225 smaller. Inverse Variation) = 112.5 men i.e. 113 men (112 men cannot finish the work. Even if this was 112.3, I would have made it 113)

We already have 45 men, we need 68 more.

Note: I could have done the above in a single step by saying 45 x 12.5/2.5 x 100/200 = 112.5
I used two steps to clarify.

Type II:
If we are given how much they were paid, we know the ratio of their rate of work. It will be the ratio in which they were paid. This is so because if you are twice as fast as me, you will be paid twice as much as me.
Ratio of rate of work = 54:81 = 2:3
Then, ratio of time taken will be 3:2 (Ratio of rate of work is inverse of ratio of time taken. If this is unclear, just check out work theory)
Then, B can do the work in 8 days.
Together, they will take 8 x 12/ (8 + 12) = 4.8 days

Type III:
Let me say that the amount of food one soldier consumes in one day is 1 soldier-day food.

Total amount of food was 200 x 31 soldier-days = 6200 soldier-days
In 27 days, 200 soldiers consumed the food which is equal to 27 x 200 = 5400 soldier-days.
Left over food = 800 soldier-days
Now 800 soldier-days food will last 80 soldiers 10 days. Since 27 days are already over, it would have lasted only 4 more days but now it is going to last 10 days so it will last an extra 6 days.
_________________

Karishma
Veritas Prep | GMAT Instructor
My Blog

Save 10% on Veritas Prep GMAT Courses And Admissions Consulting
Enroll now. Pay later. Take advantage of Veritas Prep's flexible payment plan options.

Veritas Prep Reviews

Senior Manager
Senior Manager
User avatar
Status: Time to step up the tempo
Joined: 24 Jun 2010
Posts: 420
Location: Milky way
Schools: ISB, Tepper - CMU, Chicago Booth, LSB
Followers: 6

Kudos [?]: 75 [0], given: 50

GMAT Tests User
Re: Basic Time & Work problems [#permalink] New post 23 Oct 2010, 18:26
Type I - Extra number of men required/employed

1) An engineer undertakes a project to build a road 15 km long in 300 days with 45 men employed. After 100 days, only 2.5 km of the road has been completed. Find the (approx.) number of extra men needed to complete the work in time.

a) 43
b) 45
c) 55
d) 68
e) 60

Answer:



Work and Rate
RateMenDaysWork completed in meters
First 100 daysx451002.5*1000



We can find out the actual rate (x) at which the men are working.
=> x*45*100 = 2500
=> x = 5/9.

Now we will use the actual rate at which the men are working to find out the extra men required to complete the work in the remaining 200 days. [We should only use the actual rate at which the men are working not the rate which they were expected to work.]




Work and Rate
RateMenDaysWork completed in meters
First 100 days5/9451002.5*1000
Next 100 days5/9x20012.5*1000


(5/9)*x*200 = 12500
=> x = 112.5 ~ 113. So the number of extra men required to complete the work in the remaining 200 days is 113 - 45 = 68.

Answer
_________________

:good Support GMAT Club by putting a GMAT Club badge on your blog :thanks

Intern
Intern
Joined: 04 Sep 2010
Posts: 10
Followers: 0

Kudos [?]: 3 [0], given: 6

Re: Basic Time & Work problems [#permalink] New post 23 Oct 2010, 22:05
Great! Thank you for the help ezhilkumarank and VeritasPrepKarishma. For Time & Work, i tend to directly solve problems using the one days work approach. And for the above problems that approach did not get me the right answer.
Thank you for the help!
Re: Basic Time & Work problems   [#permalink] 23 Oct 2010, 22:05
    Similar topics Author Replies Last post
Similar
Topics:
New posts 1 Time & Work problem maheshkrishna 3 17 Jun 2008, 02:18
This topic is locked, you cannot edit posts or make further replies. New Time and work problems mahasane 3 25 Jul 2010, 07:29
New posts Time and work problems-Need answers mahasane 1 17 Aug 2010, 07:57
This topic is locked, you cannot edit posts or make further replies. New help plz time and work problem fmnadeem 2 26 Aug 2010, 11:43
New posts 2 EXPERTS_POSTS_IN_THIS_TOPIC Basic work/rate problems and algebra Monkeybiz 3 31 Jan 2013, 11:29
Display posts from previous: Sort by

Basic Time & Work problems

  Question banks Downloads My Bookmarks Reviews  


GMAT Club MBA Forum Home| About| Privacy Policy| Terms and Conditions| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group and phpBB SEO

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.