If ‘A’ can complete a task in 3 hours and ‘B’ can complete [#permalink]
08 Mar 2010, 03:00
Question Stats:
60% (01:21) correct
40% (00:15) wrong based on 1 sessions
If ‘A’ can complete a task in 3 hours and ‘B’ can complete the same task in 6 hours, how long will it take if both of them work together to complete the task? This is a problem of Arithmetic, related to work and time. It is a very interesting problem but I am unable to solve it. I am still trying to solve it, I am thinking that it took (3 + 6) / 2 = 4.5, mean of the time taken by the two. But, my answer is wrong.
Please explain the logic.
Thanks
Last edited by walker on 08 Mar 2010, 06:08, edited 1 time in total.
|
|
|
|
|
|
|
GMAT Club team member
Joined: 02 Sep 2009
Posts: 11610
Followers: 1800
Kudos [?]:
9593
[2] , given: 828
|
Re: Facing problem with this question...... [#permalink]
09 Mar 2010, 02:43
2
This post received KUDOS
nickk wrote: I haven't seen anyone post the formula so I'll go ahead and do it
1/T = 1/A + 1/B + .... 1/N
so if you have N entities which can do the same job in different amounts of time (denoted by A, B, ..., N above), the total amount of time it takes them to do the same tas working together is T.
I think you can solve all similar problems using this formula. The above is correct and it's good to memorize cases for two and three entities (workers, pumps, ...): General formula for calculating the time needed for two workers A and B working simultaneously to complete one job:Given that a and b are the respective individual times needed for A and B workers (pumps, ...) to complete the job, then time needed for A and B working simultaneously to complete the job equals to T_{(A&B)}=\frac{a*b}{a+b} hours, which is reciprocal of the sum of their respective rates ( \frac{1}{a}+\frac{1}{b}=\frac{1}{t}). General formula for calculating the time needed for three A, B and C workers working simultaneously to complete one job:T_{(A&B&C)}=\frac{a*b*c}{ab+ac+bc} hours. Also for rate problems it's good to know that: TIME to complete one job=Reciprocal of rate. eg 6 hours needed to complete one job (time) --> 1/6 of the job done in 1 hour (rate). Time, rate and job in work problems are in the same relationship as time, speed (rate) and distance. Time*Rate=Distance Time*Rate=JobHope it helps.
_________________
PLEASE READ AND FOLLOW: 11 Rules for Posting!!!
RESOURCES: [GMAT MATH BOOK]; 1. Triangles; 2. Polygons; 3. Coordinate Geometry; 4. Factorials; 5. Circles; 6. Number Theory
COLLECTION OF QUESTIONS: PS: 1. Tough and Tricky questions; 2. Hard questions; 3. Hard questions part 2; 4. Standard deviation; 5. Tough Problem Solving Questions With Solutions; 6. Probability and Combinations Questions With Solutions; 7 Tough and tricky exponents and roots questions; 8 12 Easy Pieces (or not?); 9 Bakers' Dozen; 10 Algebra set. NEW!!!
DS: 1. DS tough questions; 2. DS tough questions part 2; 3. DS tough questions part 3; 4. DS Standard deviation; 5. Inequalities; 6. 700+ GMAT Data Sufficiency Questions With Explanations; 7 Tough and tricky exponents and roots questions; 8 The Discreet Charm of the DS ; 9 Devil's Dozen!!!; 10 Number Properties set. NEW!!!
 What are GMAT Club Tests? 25 extra-hard Quant Tests
Find out what's new at GMAT Club - latest features and updates
|
|
|
|
|
|
Senior Manager
Status: Yeah well whatever.
Joined: 18 Sep 2009
Posts: 351
Location: United States
GMAT 1: 660 Q42 V39 GMAT 2: 730 Q48 V42
GPA: 3.49
WE: Analyst (Insurance)
Followers: 4
Kudos [?]:
40
[0], given: 17
|
Re: Facing problem with this question...... [#permalink]
08 Mar 2010, 08:08
I made tables. I hope this is right or I did a bunch of work for no reason. I picked the work to be traveling a distance of 12 miles [list=]Separate A B R 4 mph 2 mph T 3 hrs 6 hrs D 12 mi 12 mi Together A B Together R 4 mph 2 mph T t t t D 12-d d 12 mi 4t=12-d and 2t=d t=3-d/4 so 2(3-d/4)=d 6-.5d=d 6=1.5d d=4 so Together with d set to 4 A B Together R 4 mph 2 mph T t t t D 8 mi 4 mi 12 mi 4t=8 so t=2 hrs [/list]
_________________
He that is in me > he that is in the world. - source 1 John 4:4
Last edited by vannbj on 08 Mar 2010, 08:20, edited 1 time in total.
|
|
|
|
|
|
Senior Manager
Joined: 01 Feb 2010
Posts: 275
Followers: 1
Kudos [?]:
30
[0], given: 2
|
Re: Facing problem with this question...... [#permalink]
08 Mar 2010, 08:17
david01 wrote: If ‘A’ can complete a task in 3 hours and ‘B’ can complete the same task in 6 hours, how long will it take if both of them work together to complete the task?
This is a problem of Arithmetic, related to work and time. It is a very interesting problem but I am unable to solve it. I am still trying to solve it, I am thinking that it took (3 + 6) / 2 = 4.5, mean of the time taken by the two. But, my answer is wrong.
Please explain the logic. Thanks A do 1/3 task in 1 hour B do 1/6 task in 1 hour A & B together do 1/3 + 1/6 = 1/2 task in 1 hour. So they complete task in 2 hours.
|
|
|
|
|
|
Manager
Joined: 29 Oct 2009
Posts: 203
Concentration: General Management, Sustainability
WE: Consulting (Computer Software)
Followers: 2
Kudos [?]:
37
[0], given: 12
|
Re: Facing problem with this question...... [#permalink]
08 Mar 2010, 08:19
If ‘A’ can complete a task in 3 hours and ‘B’ can complete the same task in 6 hours, how long will it take if both of them work together to complete the task?
A can complete task in 3 hours. In 1 hour A can complete 1/3 of the work. B can complete task in 6 hours. In 1 hour B can complete 1/6 of the work.
Both together can complete how much work in an hour = 1/3 + 1/6 = 3/6 = 1/2
So 1/2 work can be completed in 1 hour by A and B together. How much time it takes to complete the work = 2/1 hours = 2 hours.
Hope it is clear.
|
|
|
|
|
|
Manager
Joined: 10 Aug 2009
Posts: 125
Followers: 2
Kudos [?]:
11
[0], given: 13
|
Re: Facing problem with this question...... [#permalink]
08 Mar 2010, 13:06
I haven't seen anyone post the formula so I'll go ahead and do it
1/T = 1/A + 1/B + .... 1/N
so if you have N entities which can do the same job in different amounts of time (denoted by A, B, ..., N above), the total amount of time it takes them to do the same tas working together is T.
I think you can solve all similar problems using this formula.
|
|
|
|
|
|
Manager
Joined: 18 Feb 2010
Posts: 174
Schools: ISB
Followers: 3
Kudos [?]:
80
[0], given: 0
|
Re: Facing problem with this question...... [#permalink]
09 Mar 2010, 02:55
david01 wrote: If ‘A’ can complete a task in 3 hours and ‘B’ can complete the same task in 6 hours, how long will it take if both of them work together to complete the task?
This is a problem of Arithmetic, related to work and time. It is a very interesting problem but I am unable to solve it. I am still trying to solve it, I am thinking that it took (3 + 6) / 2 = 4.5, mean of the time taken by the two. But, my answer is wrong.
Please explain the logic.
Thanks Let task be writing 18 pages (multiple of 3 and 6)\ A writes 18/3 = 6 pages an hour B write 18/6 = 3 pages per hour Both write 9 pages per hour So total time required is 18/9=2 hours while working together... Hope this helps you in solving such problems without working with x, y fractions.
_________________
CONSIDER AWARDING KUDOS IF MY POST HELPS !!!
|
|
|
|
|
|
VP
Status: The last round
Joined: 18 Jun 2009
Posts: 1327
Concentration: Strategy, General Management
GMAT 1: 680 Q48 V34
Followers: 43
Kudos [?]:
383
[0], given: 156
|
Re: Facing problem with this question...... [#permalink]
13 Mar 2010, 11:22
Bunuel wrote: nickk wrote: I haven't seen anyone post the formula so I'll go ahead and do it
1/T = 1/A + 1/B + .... 1/N
so if you have N entities which can do the same job in different amounts of time (denoted by A, B, ..., N above), the total amount of time it takes them to do the same tas working together is T.
I think you can solve all similar problems using this formula. The above is correct and it's good to memorize cases for two and three entities (workers, pumps, ...): General formula for calculating the time needed for two workers A and B working simultaneously to complete one job:Given that a and b are the respective individual times needed for A and B workers (pumps, ...) to complete the job, then time needed for A and B working simultaneously to complete the job equals to T_{(A&B)}=\frac{a*b}{a+b} hours, which is reciprocal of the sum of their respective rates ( \frac{1}{a}+\frac{1}{b}=\frac{1}{t}). General formula for calculating the time needed for three A, B and C workers working simultaneously to complete one job:T_{(A&B&C)}=\frac{a*b*c}{ab+ac+bc} hours. Also for rate problems it's good to know that: TIME to complete one job=Reciprocal of rate. eg 6 hours needed to complete one job (time) --> 1/6 of the job done in 1 hour (rate). Time, rate and job in work problems are in the same relationship as time, speed (rate) and distance. Time*Rate=Distance Time*Rate=JobHope it helps. Kudos Bunuel!! Well, in some cases there are multiple persons doing the same job. e.g 5 men doing a job in 6 hours, while 9 women doing the same job in 6 hours & 10 boys doing the same job in 8 hours. What's the formula for such cases?
_________________
[ From 470 to 680-My Story ] [ My Last Month Before Test ] [ GMAT Prep Analysis Tool ] [ US. Business School Dashboard ] [ Int. Business School Dashboard ]
I Can, I Will
Find out what's new at GMAT Club - latest features and updates
|
|
|
|
|
|
Senior Manager
Joined: 12 Oct 2011
Posts: 283
Followers: 0
Kudos [?]:
13
[0], given: 110
|
Re: Facing problem with this question...... [#permalink]
06 Jan 2012, 06:12
Hussain15 wrote: Well, in some cases there are multiple persons doing the same job. e.g 5 men doing a job in 6 hours, while 9 women doing the same job in 6 hours & 10 boys doing the same job in 8 hours. What's the formula for such cases? Even I would be interested to know if there exists a formula for such problems. I am unusually weak in such work-rate problems and I struggle frequently. Any help would be appreciated.
_________________
Consider KUDOS if you feel the effort's worth it
|
|
|
|
|
|
Manager
Joined: 29 Jul 2011
Posts: 113
Location: United States
Followers: 1
Kudos [?]:
21
[0], given: 6
|
Re: Facing problem with this question...... [#permalink]
06 Jan 2012, 21:05
This is a unit rate problem. RULE: 1. When you are given something like, something takes x hours to complete, then the rate is 1/x 2.When working together, the rates add. Here, A's rate is 1/3, B's rate is 1/6 So, working together, A + B = 1/3 + 1/6 = 3/6 = 1/2 Now inverse again to find the number of hours (since unit rate) = 2 hours
_________________
I am the master of my fate. I am the captain of my soul. Please consider giving +1 Kudos if deserved!
DS - If negative answer only, still sufficient. No need to find exact solution. PS - Always look at the answers first CR - Read the question stem first, hunt for conclusion SC - Meaning first, Grammar second RC - Mentally connect paragraphs as you proceed. Short = 2min, Long = 3-4 min
|
|
|
|
|
|
Senior Manager
Status: D-Day is on February 10th. and I am not stressed
Affiliations: American Management association, American Association of financial accountants
Joined: 12 Apr 2011
Posts: 278
Location: Kuwait
Schools: Columbia university
Followers: 4
Kudos [?]:
13
[0], given: 52
|
Re: Facing problem with this question...... [#permalink]
07 Jan 2012, 12:26
here is the easiest approach. A can complete 1/3 of the task in one hour, while B can complete 1/6 of the task is one hour. the formula to use is as following to get how much can they both achieve in one hour: 1/3+1/6=1/x common denominator====>6 2/6+1/6=3/6 after simplification becomes 1/2 so both of them can finish the one half of the task in one hour, and in order to get the number of hours for the whole task just reverse the fraction, which will be 2 hope this helps
_________________
Sky is the limit
|
|
|
|
|
|
Intern
Joined: 01 Apr 2012
Posts: 27
Followers: 0
Kudos [?]:
0
[0], given: 11
|
Re: Facing problem with this question...... [#permalink]
10 Sep 2012, 07:56
Though this was posted long ago, the questions raised by Hussain and Siddrat are quite good.I also need Bunuel here. But, my take on Hussain's question is: if m, w and b represent the times a man, a woman and a boy take in that order. I think we could get the rate for a single person of each category: 1/( No. of worker * Time for all workers) Thus, the rates for a single person: man=1/(5*6) , woman =1/(9*6), boy=1/(10*8)
|
|
|
|
|
|
Senior Manager
Joined: 13 Aug 2012
Posts: 468
Followers: 12
Kudos [?]:
75
[0], given: 11
|
Re: If ‘A’ can complete a task in 3 hours and ‘B’ can complete [#permalink]
13 Nov 2012, 23:00
\frac{1}{6}+\frac{1}{3}=\frac{1}{x}
\frac{1}{x}=\frac{1}{2}
Answer: time = reciprocal of rate = 2 hours
|
|
|
|
|
|
|