John can complete a given task in 20 days. Jane will take

  Question banks Downloads My Bookmarks Reviews  
Author Message
TAGS:
Current Student
User avatar
Joined: 11 May 2008
Posts: 562
Followers: 5

Kudos [?]: 13 [0], given: 0

GMAT Tests User
John can complete a given task in 20 days. Jane will take [#permalink] New post 20 Jul 2008, 05:23
John can complete a given task in 20 days. Jane will take only 12 days to complete the same task. John and Jane set out to complete the task by beginning to work together. However, Jane was indisposed 4 days before the work got over. In how many days did the work get over from the time John and Jane started to work on it together?
1 KUDOS received
Senior Manager
Senior Manager
User avatar
Joined: 16 Aug 2004
Posts: 343
Location: India
Followers: 1

Kudos [?]: 31 [1] , given: 0

GMAT Tests User
Re: time and work [#permalink] New post 20 Jul 2008, 05:36
1
This post received
KUDOS
10 days. Here is the explanation
for 4 days Jane didn't work, hence john would complete (4/20=1/5 of the work). Therefore Jane and John together will complete 4/5 of the work.
Now John and Jane together would complete the work in (1/20+1/12=15/2 days).
Therefore they would take 6 days to complete 4/5 of the work, after which John worked for another 4 days. Hence in total they took 6+4=10 days to complete.
Intern
Intern
Joined: 29 Jun 2008
Posts: 37
Followers: 0

Kudos [?]: 0 [0], given: 0

Re: time and work [#permalink] New post 20 Jul 2008, 05:53
R * T = 1

John's rate = 1/20
Jane's rate = 1/12

(1/20)T + (1/12)(T-4) = 1
T/20 + (T-4)/12 = 1
(12T + 20T - 80)/240 = 1
32T = 320
T=10
Director
Director
Joined: 27 May 2008
Posts: 554
Followers: 4

Kudos [?]: 108 [0], given: 0

GMAT Tests User
Re: time and work [#permalink] New post 20 Jul 2008, 06:03
john's rate = 1/20
jane's rate = 1/12
combined rate = 1/20+1/12 = 2/15

let the work finished in x days
both woked for (x-4) days amd John alone worked for 4 days

(x-4)*2/15 + 4*1/20 = 1
2x - 8 + 3 = 15
x= 10 answer .............
Intern
Intern
Joined: 16 Jul 2008
Posts: 3
Followers: 0

Kudos [?]: 0 [0], given: 0

Re: time and work [#permalink] New post 20 Jul 2008, 07:04
I have a different point of view, solution can be too long, however, it is easy to think and solve with this method.

We know that John completes the task in 20 days, Jane completes the task in 12 days.
We can assume that total of this work is 60 units (which is the least common multiply)

From here; John finishes 3 units of the task in a day (60/20=3)
Jane finishes 5 units of the task in a day (60/12=5)

First 4 days, john complete 4*3=12 units of the task. Remaining part is 48 units (60-12=48)
Both of them complete 3+5=8 units of the task in a day. Accrodingly, they can complete 48 units of tasks in 6 days.

Then, the answer is 4+6=10...
Manager
Manager
User avatar
Joined: 04 Apr 2008
Posts: 229
Location: Pune
Followers: 1

Kudos [?]: 16 [0], given: 3

GMAT Tests User
Re: time and work [#permalink] New post 20 Jul 2008, 20:51
explaination plz...................
_________________

Every Problem Has a Sloution So keep working
AB

Re: time and work   [#permalink] 20 Jul 2008, 20:51
    Similar topics Author Replies Last post
Similar
Topics:
Popular new posts 2 David completes 60% of an assigned task in 8 days and cloaked_vessel 18 06 Mar 2005, 16:39
Popular new posts 3 A can complete a project in 20 days and B can complete the Titleist 67 02 Nov 2005, 13:37
New posts A completes the given task in 12 hours. B completes the bmwhype2 3 02 Nov 2007, 12:32
New posts 4 Experts publish their posts in the topic A can complete a project in 20 days and B can complete the 154238 6 21 Sep 2012, 05:16
New posts 4 Experts publish their posts in the topic Jane and Ashley take 20 days and 40 days respectively to tabsang 5 27 Dec 2012, 14:36
Display posts from previous: Sort by

John can complete a given task in 20 days. Jane will take

  Question banks Downloads My Bookmarks Reviews  


GMAT Club MBA Forum Home| About| Privacy Policy| Terms and Conditions| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group and phpBB SEO

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.