m6 ques 21 [#permalink] New post 06 Apr 2010, 19:10
A furniture manufacturer has two machines, but only one can be used at a time. Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift. If Machine A can do the job in 12 days working two shifts and Machine B can do the job in 15 days working two shifts, how many days will it take to do the job with the current work schedule?


* 14
* 13
* 11
* 9
* 7

In this question, shouldn't Machine A's no. of days to do the job working 1.5 shifts be 18?
Because working 2 shifts, its 12 and working 1 shift its 24.
Please tell me what am I missing here
.
_________________

-Underline your question. It takes only a few seconds!
-Search before you post.

Manager
Manager
Joined: 29 Oct 2009
Posts: 203
Concentration: General Management, Sustainability
WE: Consulting (Computer Software)
Followers: 2

Kudos [?]: 37 [0], given: 12

GMAT Tests User
Re: m6 ques 21 [#permalink] New post 07 Apr 2010, 09:13
This is my approach.
A can do the job in 12 days working two shifts => Number of shifts A takes to complete the job is = 2*12 = 24 shifts.
Work done by A per shift = 1/24

B can do the job in 15 days working two shifts =>Number of shifts B takes to complete the job is = 2*15 = 30 shifts.
Work done by B per shift = 1/30

Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift => Per day there are three shifts.

First shift A is utilized => work done = 1/24
Second shift B is utilized => work done = 1/30
Work done by A in half shift + Work done by B in half shift = 1/(2*24) + 1/(2*30) = 1/48+1/60.

Total work done in a day (shift1+shift2+shift3) = 1/24+1/30+(1/48+1/60)
Solving this gives us 9/80 as the work done per day.
So number of days required to complete the job = 80/9 which is nearly equal to 9 days.

My Answer is D.

Please post the OA.
Re: m6 ques 21   [#permalink] 07 Apr 2010, 09:13
    Similar topics Author Replies Last post
Similar
Topics:
New posts The equation M+6/36 =P-7/21 relates two temperature scales, mandy 5 11 Jun 2005, 09:32
Popular new posts The equation (M+6)/36=(p-7)/21 relates two temperature SimaQ 17 19 Oct 2006, 10:32
New posts SET 21 - Ques 13 s_positive 8 19 Oct 2007, 13:01
New posts 5 M6 bertlacy 5 04 Dec 2008, 20:58
New posts M21 Ques36 Doubt Gmatter111 1 30 Nov 2009, 19:48
Display posts from previous: Sort by

m6 ques 21

  Question banks Downloads My Bookmarks Reviews  

Moderator: Bunuel



GMAT Club MBA Forum Home| About| Privacy Policy| Terms and Conditions| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group and phpBB SEO

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.