Find all School-related info fast with the new School-Specific MBA Forum

It is currently 18 May 2013, 10:48
Customize  |  Hide

Municipal officials originally estimated that it would be

  Question banks Downloads My Bookmarks Reviews  
Author Message
TAGS:
VP
VP
Joined: 26 Apr 2004
Posts: 1255
Location: Taiwan
Followers: 1

Kudos [?]: 7 [0], given: 0

GMAT Tests User
Municipal officials originally estimated that it would be [#permalink] New post 09 Mar 2005, 01:42
00:00

Question Stats:

0% (00:00) correct 0% (00:00) wrong based on 0 sessions
Municipal officials originally estimated that it would be six months before municipal road crews could complete repaving a stretch of road. The officials presumed that private contractors could not finish any sooner. However, when the job was assigned to a private contractor, it was completed in just 28 days.

Which one of the following, if true, does most to resolve the discrepancy between the time estimated for completion of the repaving job and the actual time taken by the private contractor?

(A) Road repaving work can only be done in the summer months of June, July and August.

(B) The labor union contract for road crews employed by both municipal agencies and private contractors stipulates that employees can work only eight hours a day, five day a week, before being paid overtime.

(C) Many road-crew workers for private contractors have previously worked for municipal road crews and vice versa.

(D) Private contractors typically assign 25 workers to each road-repaving job site whereas the number assigned to municipal road crews is usually 30.

(E) Municipal agencies must conduct a lengthy bidding process to procure supplies after repaving work is ordered and before they can actually start work, whereas private contractors can obtain supplies readily as needed.
GMAT Club Legend
GMAT Club Legend
User avatar
Joined: 07 Jul 2004
Posts: 5134
Location: Singapore
Followers: 9

Kudos [?]: 87 [0], given: 0

GMAT Tests User
 [#permalink] New post 09 Mar 2005, 01:51
Municipal officials originally estimated that it would be six months before municipal road crews could complete repaving a stretch of road.
The officials presumed that private contractors could not finish any sooner.
However, when the job was assigned to a private contractor, it was completed in just 28 days.

Which one of the following, if true, does most to resolve the discrepancy between the time estimated for completion of the repaving job and the actual time taken by the private contractor?

(A) Road repaving work can only be done in the summer months of June, July and August.
- Not important. Does not explain why company took just 28 days to complete, ahead of schedule

(B) The labor union contract for road crews employed by both municipal agencies and private contractors stipulates that employees can work only eight hours a day, five day a week, before being paid overtime.
- still does not explain why there is a difference between 6 months and 28 days

(C) Many road-crew workers for private contractors have previously worked for municipal road crews and vice versa.
- Out of scope

(D) Private contractors typically assign 25 workers to each road-repaving job site whereas the number assigned to municipal road crews is usually 30.
- In that case, municipal road crews should complete the work faster

(E) Municipal agencies must conduct a lengthy bidding process to procure supplies after repaving work is ordered and before they can actually start work, whereas private contractors can obtain supplies readily as needed.
- This does most to explain the time difference. Before work actually starts, there is a lenthy process of bidding for supply procurement . This cuould be the reason why the officials gave a longer estimate for the date of completion.

E it is.
SVP
SVP
Joined: 18 Nov 2004
Posts: 1544
Followers: 2

Kudos [?]: 9 [0], given: 0

GMAT Tests User
 [#permalink] New post 09 Mar 2005, 13:26
Has to be "E"
Director
Director
Joined: 07 Nov 2004
Posts: 511
Followers: 2

Kudos [?]: 1 [0], given: 0

GMAT Tests User
 [#permalink] New post 09 Mar 2005, 16:30
easy E
Director
Director
Joined: 05 Jul 2004
Posts: 993
Followers: 2

Kudos [?]: 8 [0], given: 0

GMAT Tests User
 [#permalink] New post 09 Mar 2005, 18:25
yes.. (E).
VP
VP
Joined: 26 Apr 2004
Posts: 1255
Location: Taiwan
Followers: 1

Kudos [?]: 7 [0], given: 0

GMAT Tests User
 [#permalink] New post 09 Mar 2005, 19:28
ywilfred, thanks

OA is E
  [#permalink] 09 Mar 2005, 19:28
    Similar topics Author Replies Last post
Similar
Topics:
New posts Each year, an official estimate of the stock of cod in the anandnk 4 07 Jan 2004, 10:11
New posts Officials in Australia estimate that revenues from casinos vivek_dj 6 26 Feb 2004, 17:03
Popular new posts 9 Each year, an official estimate of the stock of cod in the saurya_s 23 04 Mar 2005, 13:57
Popular new posts 15 Each year, an official estimate of the stock of cod in the prude_sb 15 12 Mar 2007, 21:14
Popular new posts 7 EXPERTS_POSTS_IN_THIS_TOPIC Originally a trading port, Hong-Kong, currently estimated to gmatpapa 19 05 May 2011, 08:01
Display posts from previous: Sort by

Municipal officials originally estimated that it would be

  Question banks Downloads My Bookmarks Reviews  


GMAT Club MBA Forum Home| About| Privacy Policy| Terms and Conditions| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group and phpBB SEO

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.