Last visit was: 25 Apr 2024, 14:20 It is currently 25 Apr 2024, 14:20

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
User avatar
Manager
Manager
Joined: 03 Jul 2013
Posts: 76
Own Kudos [?]: 704 [70]
Given Kudos: 14
GMAT 1: 660 Q48 V32
Send PM
Most Helpful Reply
Tutor
Joined: 20 Apr 2012
Posts: 82
Own Kudos [?]: 757 [42]
Given Kudos: 39
Location: Ukraine
GMAT 1: 690 Q51 V31
GMAT 2: 730 Q51 V38
WE:Education (Education)
Send PM
avatar
Intern
Intern
Joined: 20 Sep 2013
Posts: 3
Own Kudos [?]: 23 [15]
Given Kudos: 0
Concentration: Finance, Strategy
GPA: 3.81
WE:Design (Aerospace and Defense)
Send PM
General Discussion
avatar
Intern
Intern
Joined: 22 Feb 2015
Posts: 7
Own Kudos [?]: 4 [1]
Given Kudos: 21
Send PM
Re: A contractor hires 100 men to finish a job in 50 days. After 14 days, [#permalink]
1
Bookmarks
Total work by 50 days =50*100=5000units
Work done for 14 days=14*100=1400units
WOrk remaining=3600units
The remaining work is done as follows----- {(100-n)*(36-x)---n being no. of workers left job and x ,no. of days work done by 2n men and 36 no. of days left} + {(100+n-2n)*x }
equating the above to 3600 yields 18 as our answer
Manager
Manager
Joined: 14 Jul 2014
Posts: 126
Own Kudos [?]: 49 [8]
Given Kudos: 110
Location: United States
Schools: Duke '20 (D)
GMAT 1: 720 Q50 V37
GMAT 2: 600 Q48 V27
GPA: 3.2
Send PM
Re: A contractor hires 100 men to finish a job in 50 days. After 14 days, [#permalink]
3
Kudos
5
Bookmarks
First attempt took 6 mins long. I believe it's because I was confused about how many days in total this job took even after making changes.

The rate of each worker is (1/5000).

After 14 days, 3600/5000 of the job is left.

If x = some days that 100 - n workers worked for,

3600 = (100 - n) x + (100 - n + 2n) (36 - x)

This will result in x = 18. 36 - 18 = 18. So, it took 18 days to complete the job with 2n additional workers.
User avatar
Manager
Manager
Joined: 16 Feb 2010
Posts: 77
Own Kudos [?]: 128 [0]
Given Kudos: 17
Send PM
Re: A contractor hires 100 men to finish a job in 50 days. After 14 days, [#permalink]
aadikamagic wrote:
A contractor hires 100 men to finish a job in 50 days. After 14 days, n men leave. After some more days, the contractor hires 2n more men to complete the job on time. For how many days did these 2n men work?

A. 20
B. 18
C. 16
D. 12
E. 8




Let us say that "n = 1". Also, let us assume that "some = 1000000".

Therefore, the question should now read as:

A contractor hires 100 men to finish a job in 50 days. After 14 days, 1 man leaves. After 1000000 more days, the contractor hires 2 more men to complete the job on time. For how many days did these 2 men work?

So during those 1000000 days, 99 men were still working, correct? So the work would have been finished before hiring 2 more men. So the 2 men need to work 0 days.

Please help me understand what mistake I have made.
Intern
Intern
Joined: 03 May 2016
Posts: 9
Own Kudos [?]: 51 [0]
Given Kudos: 32
Send PM
Re: A contractor hires 100 men to finish a job in 50 days. After 14 days, [#permalink]
dixitraghav wrote:
aadikamagic wrote:
A contractor hires 100 men to finish a job in 50 days. After 14 days, n men leave. After some more days, the contractor hires 2n more men to complete the job on time. For how many days did these 2n men work?

A. 20
B. 18
C. 16
D. 12
E. 8




Let us say that "n = 1". Also, let us assume that "some = 1000000".

Therefore, the question should now read as:

A contractor hires 100 men to finish a job in 50 days. After 14 days, 1 man leaves. After 1000000 more days, the contractor hires 2 more men to complete the job on time. For how many days did these 2 men work?

So during those 1000000 days, 99 men were still working, correct? So the work would have been finished before hiring 2 more men. So the 2 men need to work 0 days.

Please help me understand what mistake I have made.


To be able to complete the work in time the contractor needs to hire men before the ones already working complete it (in delayed time). I think this is the unstated and understood part of the question. Extrapolation of given conditions help you arrive at an answer sometimes but not in this case. Liked your line of thought though. :)
Director
Director
Joined: 28 Nov 2014
Posts: 754
Own Kudos [?]: 1264 [0]
Given Kudos: 86
Concentration: Strategy
GPA: 3.71
Send PM
Re: A contractor hires 100 men to finish a job in 50 days. After 14 days, [#permalink]
A good question by Veritas. Thanks team.
Manager
Manager
Joined: 03 Apr 2013
Posts: 222
Own Kudos [?]: 239 [5]
Given Kudos: 872
Location: India
Concentration: Marketing, Finance
GMAT 1: 740 Q50 V41
GPA: 3
Send PM
Re: A contractor hires 100 men to finish a job in 50 days. After 14 days, [#permalink]
4
Kudos
1
Bookmarks
aadikamagic wrote:
A contractor hires 100 men to finish a job in 50 days. After 14 days, n men leave. After some more days, the contractor hires 2n more men to complete the job on time. For how many days did these 2n men work?

A. 20
B. 18
C. 16
D. 12
E. 8


Logical approach..here it goes..

We will do this with the law of averages...
For the first 14 days some work was done..
left days? 36.

Now for some days \(100-n\) people were working...

after some days \(2n\) people joined..or in other words..

we then had a total of \(100+n\) men with us.
We know that every man does the same amount of work everyday(the efficiency is constant).

Now think about this..
the same 100 people were there when we had \(n\) less men, and when we had \(n\) more men. What comes in your mind? we had to employ \(n\) more men than usual to make up for the work that we lost when we had exactly \(n\) less men. These days have to be the same..why? because if we have these \(n\) extra than usual(100 men) men work for more days than when we had \(n\) less men, then we will have more than needed work done, and vice versa.

This brings us to think that there were less men and more men for the same number of days..which is?

36/2 = 18 days

(B) :)
Manager
Manager
Joined: 24 Mar 2015
Status:love the club...
Posts: 220
Own Kudos [?]: 112 [0]
Given Kudos: 527
Send PM
Re: A contractor hires 100 men to finish a job in 50 days. After 14 days, [#permalink]
smyarga wrote:
Solution 1
Suppose a job is to make 5000 details. So 1 men in 1 day can do \(5000/100*50=1\) detail.

After 14 days they make 14*100=1400 details.

After \(x\) more days they do \(1400+x\cdot (100-n)\) details. So, we have \(5000-1400-x(100-n)=3600-x(100-n)\) details to do and \(50-14-x=36-x\) days.

We have an equation: \(3600-x(100-n)=(36-x)*(100-n+2n)\)

\(3600-100x+xn=3600+36n-100x-xn\)

\(2xn=36n\)

\(x=18\)

So, these \(2n\) men work for \(36-18=18\) days.


Solution 2
After 14 days we have 36 days to finish the work. And after \(x\) more days we didn't do \(x\cdot n\) details, because \(n\) people leave the work.

To make everything on time we hire \(2n\) people or just \(n\) people more to finish the undone work in \(36-x\) days. So, \(x\cdot n=(36-x)\cdot n\) or \(x=18\).


The correct answer is 18.


hi

the solution 1 is beautifully done...

anyway, would you please speak something more about solution 2....? Is it not such that, since it is assumed that the work was completed on time, then (36-x)*2n = the remaining job..? So how can this expression equals x*2n....?

thanks in advance .....
Senior Manager
Senior Manager
Joined: 28 Jun 2015
Posts: 250
Own Kudos [?]: 293 [4]
Given Kudos: 47
Concentration: Finance
GPA: 3.5
Send PM
Re: A contractor hires 100 men to finish a job in 50 days. After 14 days, [#permalink]
4
Bookmarks
Total job = \(100m*50d = 5000md\) (\(md\)=man-days)

Job done in 14 days = \(100m*14d = 1400md\). Remaining job = \(5000md - 1400md = 3600md\).

Let the number of days that \((100-n)\) men worked be \(k\), then \((100-n)*k + (100+n)*(50-14-k) = 3600\).

\(100k - nk + 3600 - 100k + 36n - nk = 3600\).

\(36n - 2nk = 0\)

\(2nk = 36n\)

\(k = \frac{36}{2} = 18.\)

So, the \(2n\) men worked for \((36-18) = 18\) days.
Target Test Prep Representative
Joined: 14 Oct 2015
Status:Founder & CEO
Affiliations: Target Test Prep
Posts: 18761
Own Kudos [?]: 22052 [9]
Given Kudos: 283
Location: United States (CA)
Send PM
Re: A contractor hires 100 men to finish a job in 50 days. After 14 days, [#permalink]
6
Kudos
3
Bookmarks
Expert Reply
aadikamagic wrote:
A contractor hires 100 men to finish a job in 50 days. After 14 days, n men leave. After some more days, the contractor hires 2n more men to complete the job on time. For how many days did these 2n men work?

A. 20
B. 18
C. 16
D. 12
E. 8


We are given that 100 men will finish a job in 50 days; thus, the rate of the 100 men is 1/50 and the rate of each man is (1/50)/100 = 1/5000.

This is what we know:

The 100 men work for the first 14 days. Then n men leave and the (100 - n) men work for some number of days. Then 2n men join in (so now there are 100 - n + 2n = 100 + n men) and they all work for the remaining days and complete the job on time, in 50 days.

If we let x = the number of days the (100 - n) men work (after the first 14 days but before the 2n men join in), then (100 + 2n) men (after the 2n men join in) work for (36 - x) days, since the total number of days for the job is still 50. Thus, we can create the following equation:

100(1/5000)(14) + (100 - n)(1/5000)(x) + (100 + n)(1/5000)(36 - x) = 1

The 1 on the right-hand side of the equation represents the complete job and each of the addends on the left-hand side represents the fraction of the job the 100 men, (100 - n) men, and (100 + n) men contribute at different stages of the job, respectively.

Multiplying the equation by 5000, we have:

100(14) + (100 - n)(x) + (100 + n)(36 - x) = 5000

1400 + 100x - nx + 3600 - 100x + 36n - nx = 5000

5000 + 36n - 2nx = 5000

36n = 2nx

36 = 2x

18 = x

Since the extra 2n men actually work (36 - x) days, they work 36 - 18 = 18 days.

Answer: B
Manager
Manager
Joined: 14 Oct 2012
Posts: 117
Own Kudos [?]: 258 [0]
Given Kudos: 1023
Send PM
Re: A contractor hires 100 men to finish a job in 50 days. After 14 days, [#permalink]
Here is my solutions -






Please let me know if i am doing anything wrong!!!
Attachments

my 2 cents.png
my 2 cents.png [ 28.15 KiB | Viewed 13590 times ]

Manager
Manager
Joined: 06 Oct 2015
Posts: 68
Own Kudos [?]: 112 [0]
Given Kudos: 73
Location: Bangladesh
Concentration: Accounting, Leadership
Send PM
Re: A contractor hires 100 men to finish a job in 50 days. After 14 days, [#permalink]
Let, the 2n people were hired d days after the n people leave.

nd=n(36-d)
d=36-d
d=18


This is so, because half of the 2n people will work just to cover the gap created by the leave of the n people.
Senior Manager
Senior Manager
Joined: 02 Jan 2022
Posts: 266
Own Kudos [?]: 94 [0]
Given Kudos: 3
GMAT 1: 760 Q50 V42
Send PM
Re: A contractor hires 100 men to finish a job in 50 days. After 14 days, [#permalink]
Considering the total work to be 5000 units.
(100)*(50) = 5000 units.
Assuming after n people left 100 - n workers worked for x days.
For the remaining 50 - (14+x) days = 36 - x days 100+n workers worked as 2n workers were added.
Hence this can be represented as the total work done on time.
100*(14) + (x)*(100-n) + (36 - x)*(100 + n) = 5000.
3600 = 100x - x*n + 3600 + 36n - 100x - n*x.
36n = 2nx.
x = 18 days

User avatar
Non-Human User
Joined: 09 Sep 2013
Posts: 32679
Own Kudos [?]: 822 [0]
Given Kudos: 0
Send PM
Re: A contractor hires 100 men to finish a job in 50 days. After 14 days, [#permalink]
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
GMAT Club Bot
Re: A contractor hires 100 men to finish a job in 50 days. After 14 days, [#permalink]
Moderators:
Math Expert
92915 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne