Ram can do a piece of work in 8 days which syam can finsih in 12 days.If they work at it on alternate days,with Ram begining,in how many days,the work will be finished?
Senior Manager
Senior Manager
User avatar
Joined: 04 Jan 2006
Posts: 282
Followers: 1

Kudos [?]: 14 [0], given: 0

GMAT Tests User
Re: Ram and Shyam [#permalink] New post 05 Feb 2007, 13:59
sravan_m444 wrote:
Ram can do a piece of work in 8 days which syam can finsih in 12 days.If they work at it on alternate days,with Ram begining,in how many days,the work will be finished?


Ram's Work Rate = R = 1/8 (work/day)
Syam's Work Rate = S = 1/12 (work/day)

Before the job is done, if Ram work n days, Syam will also works n days.
Therefore, work done by Ram = n/8 work
work done by Syam = n/12

As mentioned above that both work is not done, we can write this statement
n/8 + n/12 <= 1
n* ((3+2)/24) <= 1
n <= 24/5
n <= 4.8 days
This means that Ram and Syam will have to work at least 4 days each before the job can be done.
Work from Ram = 4 * 1/8 = 1/2
Work from Syam = 4 * 1/12 = 1/3
Total = 1/2 + 1/3 = 5/6
On 8th day, the job remain 1 - 5/6 = 1/6 work
On 9th day, Ram will work on this day and the job remain = 1/6 - 1/8 = 1/24.
On the 10th day, Syam will do the rest and the job is done.

Therefore, it will take 10 days to finish the job.
Senior Manager
Senior Manager
User avatar
Joined: 04 Jan 2006
Posts: 282
Followers: 1

Kudos [?]: 14 [0], given: 0

GMAT Tests User
 [#permalink] New post 05 Feb 2007, 14:04
Here is another approach for this question.

R = 1/8 (work/day)
S = 1/12 (work/day)

If they work together, their work rate = (1/8 + 1/12) = 5/24 (work/day)

They will need 24/5 (day/work) = 4.8 days to finish one work.

But since Ram and Syam will work on alternate day they will need total of 4.8 x 2 = 9.6 days = 10 days to finish the work.
Director
Director
Joined: 12 Jun 2006
Posts: 544
Followers: 1

Kudos [?]: 6 [0], given: 1

GMAT Tests User
 [#permalink] New post 05 Feb 2007, 14:11
Quote:
Ram can do a piece of work in 8 days which syam can finsih in 12 days.If they work at it on alternate days,with Ram begining,in how many days,the work will be finished?
Ram
rt = w
r(8) = 1
r= 1/8

Syam
rt = w
r(12) = 1
r=1/2

1/8 + 1/12 = 5/24

5/24(x) = 1
****remember, 5/24 is really 1/8 + 1/12, in other words, 2 days****
x = 4.8
4.8*2 = 9.6 = 10 days
Manager
Manager
Joined: 10 Dec 2005
Posts: 114
Followers: 1

Kudos [?]: 2 [0], given: 0

 [#permalink] New post 05 Feb 2007, 14:40
R can do 1/8 of the job in 1 day
S can do 1/12 off the job in 1 day

If R and S both worked together for a day they can finish (1/8 + 1/12) of the job

meaning 5/24 of the job can be done in 1 day
Therefore to do 1 jobit will take 24/5 days = 4.8 days

Since both are working alternate days it will take twice as long, meaning 2(4.8) days = 9.6 = 10 days.
_________________

"Live as if you were to die tomorrow. Learn as if you were to live forever." - Mahatma Gandhi

Manager
Manager
Joined: 12 Feb 2006
Posts: 119
Followers: 1

Kudos [?]: 0 [0], given: 0

GMAT Tests User
 [#permalink] New post 05 Feb 2007, 21:52
We know that it will take more than 8 days because that is how long R alone can do the job. So R 5d ays and S 4 days = 5/8 + 1/3 = 23/24.

Therefore we need one more day or 10.

This isn't has fast as the other guys, but if you are math moron like me it gets the job done.
  [#permalink] 05 Feb 2007, 21:52
    Similar topics Author Replies Last post
Similar
Topics:
New posts If 12 men and 16 women can do a piece of work in 5 days and smcgrath12 4 17 Aug 2004, 15:19
New posts A and B together can do a piece of work in 72/5 days ; B and jyotsnasarabu 1 08 Oct 2006, 04:37
Popular new posts A and B together can do a peace of work in 12 days,which B sravan_m444 13 05 Feb 2007, 11:30
Popular new posts 2 EXPERTS_POSTS_IN_THIS_TOPIC Matt and Peter can do together a piece of work in 20 days prasannar 12 11 Mar 2008, 03:56
New posts 2 Micheal and Adam can do together a piece of work in 20 days. prasannar 3 11 Mar 2008, 04:47
Display posts from previous: Sort by

Ram can do a piece of work in 8 days which syam can finsih

  Question banks Downloads My Bookmarks Reviews  


GMAT Club MBA Forum Home| About| Privacy Policy| Terms and Conditions| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group and phpBB SEO

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.