Six machines each working at the same

  Question banks Downloads My Bookmarks Reviews  
Author Message
TAGS:
VP
VP
User avatar
Joined: 18 May 2008
Posts: 1304
Followers: 9

Kudos [?]: 58 [0], given: 0

GMAT Tests User
Six machines each working at the same [#permalink] New post 13 Nov 2008, 03:46
Help
Attachments

machines.JPG
machines.JPG [ 53.72 KiB | Viewed 597 times ]

Manager
Manager
Joined: 08 Aug 2008
Posts: 235
Followers: 1

Kudos [?]: 13 [0], given: 0

GMAT Tests User
Re: GMATCLUB- machines [#permalink] New post 13 Nov 2008, 07:29
more workers, lesser days....(inverse ratio since rates are same..)
6/x=8/12==> x=9

so 9-6 =3 additional workers reqd.
Manager
Manager
Joined: 23 Jul 2008
Posts: 207
Followers: 1

Kudos [?]: 18 [0], given: 0

GMAT Tests User
Re: GMATCLUB- machines [#permalink] New post 13 Nov 2008, 12:19
using unitary method
six m/cs------12 days
one m/cs------72 days
nine m/cs------8 days
=> additional machines= 9-6=3
Director
Director
Joined: 14 Aug 2007
Posts: 745
Followers: 7

Kudos [?]: 66 [0], given: 0

GMAT Tests User
Re: GMATCLUB- machines [#permalink] New post 13 Nov 2008, 20:07
6 machines * Rate of individual machine (R) * 12 days = 1 work

Therefore R = 1/72

Let X be the total number of machines reqd to complete work in 8 days

we have,

X * 1/72 * 8 = 1

X =9

we need to know how many "additional" machines are reqd = 9 -6 = 3
VP
VP
User avatar
Joined: 18 May 2008
Posts: 1304
Followers: 9

Kudos [?]: 58 [0], given: 0

GMAT Tests User
Re: GMATCLUB- machines [#permalink] New post 13 Nov 2008, 21:30
Ohhhhhhhhhhhh. I didnt notice the word "additional" in the question and got 6 as the final answer. :x
This shows we shld read wht exactly is required in the question
Director
Director
Joined: 14 Aug 2007
Posts: 745
Followers: 7

Kudos [?]: 66 [0], given: 0

GMAT Tests User
Re: GMATCLUB- machines [#permalink] New post 13 Nov 2008, 21:47
ritula wrote:
Ohhhhhhhhhhhh. I didnt notice the word "additional" in the question and got 6 as the final answer. :x
This shows we shld read wht exactly is required in the question


But then you should get 9 as answer right :)
or was it an upside down problem (9 6) :wink: :-D
Re: GMATCLUB- machines   [#permalink] 13 Nov 2008, 21:47
    Similar topics Author Replies Last post
Similar
Topics:
Popular new posts Six machines, each working at the same constant rate, Matador 10 06 Apr 2006, 15:24
New posts Six machines, each working at the same constant rate, x242222 3 21 May 2006, 14:51
New posts Six machines, each working at the same constant rate, uphillclimb 6 21 Oct 2006, 10:45
New posts Six machines, each working at the same constant rate, jayy178 4 19 Nov 2006, 23:09
New posts Six machines, each working at the same constant rate, above720 1 09 Feb 2007, 21:43
Display posts from previous: Sort by

Six machines each working at the same

  Question banks Downloads My Bookmarks Reviews  


GMAT Club MBA Forum Home| About| Privacy Policy| Terms and Conditions| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group and phpBB SEO

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.