Find all School-related info fast with the new School-Specific MBA Forum

It is currently 16 Apr 2014, 23:25

Close

GMAT Club Daily Prep

Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Events & Promotions

Events & Promotions in June
Open Detailed Calendar

Six Machines Working Together GMAT Prep

  Question banks Downloads My Bookmarks Reviews Important topics  
Author Message
TAGS:
1 KUDOS received
Director
Director
Joined: 12 Jun 2006
Posts: 539
Followers: 1

Kudos [?]: 7 [1] , given: 1

GMAT Tests User
Six Machines Working Together GMAT Prep [#permalink] New post 27 Nov 2006, 02:04
1
This post received
KUDOS
00:00
A
B
C
D
E

Difficulty:

  5% (low)

Question Stats:

100% (03:02) correct 0% (00:00) wrong based on 2 sessions
each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines each working at the same constant rate, will be needed to complete the job in 8 days?

I believe this was answered before. I searched the forum cursorily and came up empty. In any case, if it was answered please let me know and I'll give a more thorough look. If not, please show all work. Thanks!
Director
Director
User avatar
Joined: 05 Feb 2006
Posts: 905
Followers: 1

Kudos [?]: 22 [0], given: 0

GMAT Tests User
 [#permalink] New post 27 Nov 2006, 02:15
1/x+1/x+1/x+1/x+1/x+1/x=1/12
6/x=1/12
x=72

So.

x/72=1/8
8x=72
x=9

9-6=3
Senior Manager
Senior Manager
User avatar
Joined: 01 Sep 2006
Posts: 302
Location: Phoenix, AZ, USA
Followers: 1

Kudos [?]: 9 [0], given: 0

GMAT Tests User
Re: Six Machines, [#permalink] New post 27 Nov 2006, 08:28
each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines each working at the same constant rate, will be needed to complete the job in 8 days?


Assume N machines are needed and each machine does M amount of work

6/M=1/12==> M =72

N*(1/72)=1/8

N*(1/72)=1/8
N=72/8=9

Additional machines =9-6=3
Senior Manager
Senior Manager
Joined: 13 Sep 2006
Posts: 282
Location: New York
Followers: 1

Kudos [?]: 3 [0], given: 0

GMAT Tests User
 [#permalink] New post 27 Nov 2006, 15:50
6:12
x:8

flip one ratio

6:8
x:12

multiply 6*12 = 72 so 8*x=72 ...x=9

3 more machines needed
_________________

"Never let the fear of striking out get in your wayâ€

Manager
Manager
Joined: 01 Apr 2006
Posts: 98
Followers: 2

Kudos [?]: 5 [0], given: 0

GMAT Tests User
 [#permalink] New post 02 Dec 2006, 18:57
Just had this, here is my take:

I used the work formula (like the RT=D) Time*Rate= Work

T*R=W

12*6=72

8*(6+x) = 72

48+8x=72

8x=24
x=3

Seemed to work out for me.
Intern
Intern
Joined: 19 Jan 2009
Posts: 23
Followers: 0

Kudos [?]: 0 [0], given: 0

PS machines working together [#permalink] New post 05 Feb 2009, 04:27
Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each woring at the same constant rate, will be needed to complete the job in 8 days?

A) 2

B) 3

C) 4

D) 6

E) 8
1 KUDOS received
VP
VP
User avatar
Joined: 18 May 2008
Posts: 1302
Followers: 10

Kudos [?]: 78 [1] , given: 0

GMAT Tests User
Re: PS machines working together [#permalink] New post 05 Feb 2009, 06:42
1
This post received
KUDOS
Let R be the rate of working of each machine
6/R=1/12
hence, R=72
Let X be the total no of machines which can complete work in 8 days
X/R=1/8
Put value of R=72
Solving X=9
Hence additional no of machines required =9-6=3 Hence B
jairus wrote:
Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each woring at the same constant rate, will be needed to complete the job in 8 days?

A) 2

B) 3

C) 4

D) 6

E) 8
SVP
SVP
User avatar
Joined: 07 Nov 2007
Posts: 1833
Location: New York
Followers: 23

Kudos [?]: 390 [0], given: 5

GMAT Tests User
Re: PS machines working together [#permalink] New post 05 Feb 2009, 19:31
jairus wrote:
Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each woring at the same constant rate, will be needed to complete the job in 8 days?

A) 2

B) 3

C) 4

D) 6

E) 8



Work Rate = 1/Time taken

Work Rate for 6 machines = 1/12
Work Rate for 1 machine = 1/12*6 = 1/72

Wor Rate for X machines = x/72 = 1/8 --> x=9

Answ = 9-6=3

B
_________________

Your attitude determines your altitude
Smiling wins more friends than frowning

Manager
Manager
Joined: 14 Jun 2009
Posts: 98
Followers: 1

Kudos [?]: 1 [0], given: 9

machines? [#permalink] New post 09 Aug 2009, 05:13
got this question on gmatprep...i know its an easy question but dunno why today i jus wasnt able to come 2 eqtns>>

Q> 6 machines at the same constant rate can do a work in 12 days,if the work has to be done in 8 days, how many machines which work at the same constant rate, need to be added.???
1 KUDOS received
Manager
Manager
Joined: 10 Jul 2009
Posts: 172
Followers: 1

Kudos [?]: 24 [1] , given: 8

GMAT Tests User
Re: machines? [#permalink] New post 09 Aug 2009, 05:47
1
This post received
KUDOS
For work related problems, number of person days or machine days is always constant
Let x be the number of machines that were used to complete the work in 8 days.
So, 6*12 = 8*x
x = 9
Number of machines to be added = 9-6 = 3
1 KUDOS received
Manager
Manager
Joined: 09 Aug 2009
Posts: 57
Followers: 1

Kudos [?]: 4 [1] , given: 1

Re: machines? [#permalink] New post 09 Aug 2009, 06:14
1
This post received
KUDOS
Here number of machines and days are inversely proportional.
6 machine can complete the work in 12 days, so in 1 day all together can complete 1/12 part of work.
Now to complete 1/8 part of work,
6 -- 1/12
x -- 1/8
x =6/8*12
x=9
Number of machines to be added = 9-6 = 3

/Prabu
1 KUDOS received
Manager
Manager
User avatar
Joined: 13 Aug 2009
Posts: 204
Schools: Sloan '14 (S)
Followers: 3

Kudos [?]: 70 [1] , given: 16

GMAT Tests User
Re: PS machines working together [#permalink] New post 16 Aug 2009, 10:55
1
This post received
KUDOS
Here is how I solved the problem:

6 machines each working at the same constant rate together can complete a job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days?

I think I saw this one in the first PowerPrep Test:

This is a simple two equation problem:

let x = the number of additional machines needed to complete the job in 8 days
let y = the rate for one machine to complete the job

Equation 1:

Rate * Time = Work
6*y*12 = 1 job

Equation 2:

(6+x)*y*8 = 1 job

so...
y = 1/(6*12)
(6+x)*(1/(6*12))*8 = 1
x = 3
Senior Manager
Senior Manager
User avatar
Joined: 21 Jul 2009
Posts: 368
Schools: LBS, INSEAD, IMD, ISB - Anything with just 1 yr program.
Followers: 14

Kudos [?]: 92 [0], given: 22

GMAT Tests User
Re: PS machines working together [#permalink] New post 17 Aug 2009, 09:27
This solution is much faster and doesn't require you to calculate the rate of each of the machines -

6 machines ---> 12 days
? machines ---> 8 days.

the trick is to consider proportions since all machines are running at constant rate. so the number of machines is inversely proportional to number of days taken to complete the job. More number of machines to finish in lesser number of days - plain logic.

Under such situations, the blind approach is to multiply 6 with 12 and divide by 8, gives total number of machines to finish in 8 days, additional machines would be to just subtract with original number of machines. 9 - 6 = 3.

If the proportion was straight and not inverse, we would have multiplied 6 with 8 and divided with 12, but in inverse proportions, same line elements are multiplied.
_________________

I am AWESOME and it's gonna be LEGENDARY!!!

Manager
Manager
User avatar
Joined: 13 Aug 2009
Posts: 204
Schools: Sloan '14 (S)
Followers: 3

Kudos [?]: 70 [0], given: 16

GMAT Tests User
Re: Six Machines, [#permalink] New post 17 Aug 2009, 11:42
18.Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days?

A) 2
B) 3
C) 4
D) 6
E) 8

Rate of one machine = 1 job / (12*6) days

let X = number of machines needed to complete the job in 8 days

1/(6*12) * 8 * X = 1 job

X = 9

9-6 = 3

ANSWER: B. 3
Manager
Manager
User avatar
Joined: 13 Aug 2009
Posts: 204
Schools: Sloan '14 (S)
Followers: 3

Kudos [?]: 70 [0], given: 16

GMAT Tests User
Re: machines? [#permalink] New post 17 Aug 2009, 11:43
18.Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days?

A) 2
B) 3
C) 4
D) 6
E) 8

Rate of one machine = 1 job / (12*6) days

let X = number of machines needed to complete the job in 8 days

1/(6*12) * 8 * X = 1 job

X = 9

9-6 = 3

ANSWER: B. 3
Suspended Member
User avatar
Joined: 23 Jul 2009
Posts: 60
Followers: 7

Kudos [?]: 50 [0], given: 10

Re: machines? [#permalink] New post 17 Aug 2009, 12:52
let the rate of machines be x

then 6 machines * 12 days * x = n machines * 8 days * x

--> 9 machines, thus 3 more are required
Senior Manager
Senior Manager
Joined: 17 Mar 2009
Posts: 311
Followers: 6

Kudos [?]: 221 [0], given: 22

GMAT Tests User
Re: machines? [#permalink] New post 17 Aug 2009, 18:10
arvs212 wrote:
got this question on gmatprep...i know its an easy question but dunno why today i jus wasnt able to come 2 eqtns>>

Q> 6 machines at the same constant rate can do a work in 12 days,if the work has to be done in 8 days, how many machines which work at the same constant rate, need to be added.???


Follow this formula, it will be always easy..
* Different number of machines (or men) , change the number of days(hours) , but the product of the number of machines and number of days remain the same

M1 * D1 = M2 * D2
M= number of machines
D= number of days
6 * 12 = M2 * 8
M2 = 9, so 3 more

* another formula when amount of work is different from the original, will be useful in some problems.
(M1 * D1) / W1 = (M2 * D2)/W2
W = amount of work
Manager
Manager
Joined: 09 Aug 2009
Posts: 57
Followers: 1

Kudos [?]: 4 [0], given: 1

Re: machines? [#permalink] New post 17 Aug 2009, 22:30
crejoc wrote:
arvs212 wrote:
got this question on gmatprep...i know its an easy question but dunno why today i jus wasnt able to come 2 eqtns>>

Q> 6 machines at the same constant rate can do a work in 12 days,if the work has to be done in 8 days, how many machines which work at the same constant rate, need to be added.???


Follow this formula, it will be always easy..
* Different number of machines (or men) , change the number of days(hours) , but the product of the number of machines and number of days remain the same

M1 * D1 = M2 * D2
M= number of machines
D= number of days
6 * 12 = M2 * 8
M2 = 9, so 3 more

* another formula when amount of work is different from the original, will be useful in some problems.
(M1 * D1) / W1 = (M2 * D2)/W2
W = amount of work


Yes, another good way to go about it.
Re: machines?   [#permalink] 17 Aug 2009, 22:30
    Similar topics Author Replies Last post
Similar
Topics:
New posts 10 machines work at constant rate and working together, they bh10503 5 04 Mar 2006, 13:10
Popular new posts Six machines, each working at the same constant rate, Matador 10 06 Apr 2006, 14:24
New posts Working together at their respective rates, machine A, B, arjtryarjtry 3 22 Jul 2008, 10:46
New posts Six machines each working at the same ritula 5 13 Nov 2008, 02:46
Popular new posts 20 Experts publish their posts in the topic Machines A and B, working together, take t minutes to comple skamal7 12 23 Feb 2013, 00:44
Display posts from previous: Sort by

Six Machines Working Together GMAT Prep

  Question banks Downloads My Bookmarks Reviews Important topics  


GMAT Club MBA Forum Home| About| Privacy Policy| Terms and Conditions| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group and phpBB SEO

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.