Find all School-related info fast with the new School-Specific MBA Forum

It is currently 22 Aug 2014, 13:45

Close

GMAT Club Daily Prep

Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Events & Promotions

Events & Promotions in June
Open Detailed Calendar

Which of the following best completes the passage below?

  Question banks Downloads My Bookmarks Reviews Important topics  
Author Message
TAGS:
Director
Director
User avatar
Joined: 25 Oct 2006
Posts: 652
Followers: 7

Kudos [?]: 187 [0], given: 6

GMAT Tests User
Which of the following best completes the passage below? [#permalink] New post 18 Jan 2009, 21:23
00:00
A
B
C
D
E

Difficulty:

(N/A)

Question Stats:

0% (00:00) correct 0% (00:00) wrong based on 0 sessions
Which of the following best completes the passage below?
When a project is failing and should be terminated, plan to bring in a new manager. New managers are more likely to terminate the project than are the original managers because______

(A) the project may have failed for reasons that the original manager could not have foreseen
(B) organizations tend to reward managers who can overcome problems
(C) managerial decisions to terminate a project should depend on the likelihood of the project’s eventual success
(D) the original managers were not necessarily able to overcome problems caused by external events over which they had no control
(E) the new managers have no need to justify the earlier decision to maintain the project
PLease give reasons for choosing your answer
_________________

If You're Not Living On The Edge, You're Taking Up Too Much Space

Director
Director
avatar
Joined: 12 Oct 2008
Posts: 558
Followers: 2

Kudos [?]: 56 [0], given: 2

GMAT Tests User
Re: CR - Terminate Project [#permalink] New post 18 Jan 2009, 21:36
IMO D....Keep all things constant....now new manager will try to overcome all the possible problems those which are in his hands....however if some external factor is causing project to terminate and nobody from the organization have a control on that....then project has to be terminated....

therefore IMO D.
Director
Director
avatar
Joined: 14 Aug 2007
Posts: 735
Followers: 7

Kudos [?]: 99 [0], given: 0

GMAT Tests User
Re: CR - Terminate Project [#permalink] New post 18 Jan 2009, 21:39
E it is!

priyankur_saha@ml.com wrote:
Which of the following best completes the passage below?
When a project is failing and should be terminated, plan to bring in a new manager. New managers are more likely to terminate the project than are the original managers because______

(A) the project may have failed for reasons that the original manager could not have foreseen
if this is the case, the new manager should not terminate project, instead as he knows the reasons he will probably work on it
(B) organizations tend to reward managers who can overcome problems.
The old manager too can do it if he is getting reward.
(C) managerial decisions to terminate a project should depend on the likelihood of the project’s eventual success
again if this is the case the old manager too can terminate the project
(D) the original managers were not necessarily able to overcome problems caused by external events over which they had no control .
this can happen with new manager as well.
(E) the new managers have no need to justify the earlier decision to maintain the project
this is something old manager can not do. and new manager can easily do.
PLease give reasons for choosing your answer
VP
VP
User avatar
Joined: 18 May 2008
Posts: 1300
Followers: 12

Kudos [?]: 106 [0], given: 0

GMAT Tests User
Re: CR - Terminate Project [#permalink] New post 18 Jan 2009, 23:02
It should be E. The question asks for a valid reason for the new manager terminating the project. E says that old manager had justifications to mainatain the project which is a hurdle in the termination process. but new managers have no such reason so they can easily terminate it. E is the clear winner
priyankur_saha@ml.com wrote:
Which of the following best completes the passage below?
When a project is failing and should be terminated, plan to bring in a new manager. New managers are more likely to terminate the project than are the original managers because______

(A) the project may have failed for reasons that the original manager could not have foreseen
(B) organizations tend to reward managers who can overcome problems
(C) managerial decisions to terminate a project should depend on the likelihood of the project’s eventual success
(D) the original managers were not necessarily able to overcome problems caused by external events over which they had no control
(E) the new managers have no need to justify the earlier decision to maintain the project
PLease give reasons for choosing your answer
VP
VP
User avatar
Joined: 05 Jul 2008
Posts: 1436
Followers: 33

Kudos [?]: 214 [0], given: 1

GMAT Tests User
Re: CR - Terminate Project [#permalink] New post 19 Jan 2009, 17:33
Got an E as well.
Director
Director
User avatar
Joined: 25 Oct 2006
Posts: 652
Followers: 7

Kudos [?]: 187 [0], given: 6

GMAT Tests User
Re: CR - Terminate Project [#permalink] New post 19 Jan 2009, 18:34
Thanks for explanations. OA is E indeed.

I ignored the fact "new manager" and reinforced more on "project termination" so got answer C.
_________________

If You're Not Living On The Edge, You're Taking Up Too Much Space

Director
Director
avatar
Joined: 12 Oct 2008
Posts: 558
Followers: 2

Kudos [?]: 56 [0], given: 2

GMAT Tests User
Re: CR - Terminate Project [#permalink] New post 19 Jan 2009, 20:01
can somebody explain more on this?
VP
VP
User avatar
Joined: 05 Jul 2008
Posts: 1436
Followers: 33

Kudos [?]: 214 [0], given: 1

GMAT Tests User
Re: CR - Terminate Project [#permalink] New post 21 Jan 2009, 09:25
reply2spg wrote:
can somebody explain more on this?


Just read the stimulus with out looking at answer choices and think for a sec on possible reasons

When a project is failing and should be terminated, plan to bring in a new manager. New managers are more likely to terminate the project than are the original managers because______

So old managers are not terminating failing projects but new M's will do possibly because

old M's have reputation at stake, getting kick backs from vendors, have their job at stake if the project fails and wants to make it a success from the doors of failure.

The commonality in all the reasons I said above is summed up in E.

the new managers have no need to justify the earlier decision to maintain the project

HTH
Senior Manager
Senior Manager
avatar
Joined: 02 Nov 2008
Posts: 283
Followers: 1

Kudos [?]: 30 [0], given: 2

GMAT Tests User
Re: CR - Terminate Project [#permalink] New post 21 Jan 2009, 14:23
alpha_plus_gamma wrote:
E it is!

priyankur_saha@ml.com wrote:
Which of the following best completes the passage below?
When a project is failing and should be terminated, plan to bring in a new manager. New managers are more likely to terminate the project than are the original managers because______

(A) the project may have failed for reasons that the original manager could not have foreseen
if this is the case, the new manager should not terminate project, instead as he knows the reasons he will probably work on it
(B) organizations tend to reward managers who can overcome problems.
The old manager too can do it if he is getting reward.
(C) managerial decisions to terminate a project should depend on the likelihood of the project’s eventual success
again if this is the case the old manager too can terminate the project
(D) the original managers were not necessarily able to overcome problems caused by external events over which they had no control .
this can happen with new manager as well.
(E) the new managers have no need to justify the earlier decision to maintain the project
this is something old manager can not do. and new manager can easily do.
PLease give reasons for choosing your answer


I don't like this question but the above analysis is a good explanation.
Director
Director
avatar
Joined: 29 Aug 2005
Posts: 881
Followers: 7

Kudos [?]: 149 [0], given: 7

GMAT Tests User
Re: CR - Terminate Project [#permalink] New post 21 Jan 2009, 14:50
priyankur_saha@ml.com wrote:
Which of the following best completes the passage below?
When a project is failing and should be terminated, plan to bring in a new manager. New managers are more likely to terminate the project than are the original managers because______

(A) the project may have failed for reasons that the original manager could not have foreseen
(B) organizations tend to reward managers who can overcome problems
(C) managerial decisions to terminate a project should depend on the likelihood of the project’s eventual success
(D) the original managers were not necessarily able to overcome problems caused by external events over which they had no control
(E) the new managers have no need to justify the earlier decision to maintain the project
PLease give reasons for choosing your answer

The argument needs to be strengthened and E does so.
It gives a reason why one should appoint a new manager to terminate the failing project.
Senior Manager
Senior Manager
avatar
Joined: 02 Nov 2008
Posts: 283
Followers: 1

Kudos [?]: 30 [0], given: 2

GMAT Tests User
Re: CR - Terminate Project [#permalink] New post 21 Jan 2009, 15:09
botirvoy wrote:
priyankur_saha@ml.com wrote:
Which of the following best completes the passage below?
When a project is failing and should be terminated, plan to bring in a new manager. New managers are more likely to terminate the project than are the original managers because______

(A) the project may have failed for reasons that the original manager could not have foreseen
(B) organizations tend to reward managers who can overcome problems
(C) managerial decisions to terminate a project should depend on the likelihood of the project’s eventual success
(D) the original managers were not necessarily able to overcome problems caused by external events over which they had no control
(E) the new managers have no need to justify the earlier decision to maintain the project
PLease give reasons for choosing your answer

The argument needs to be strengthened and E does so.
It gives a reason why one should appoint a new manager to terminate the failing project.


The argument does not need to be strengthened (that's not what the question is asking)
Director
Director
avatar
Joined: 29 Aug 2005
Posts: 881
Followers: 7

Kudos [?]: 149 [0], given: 7

GMAT Tests User
Re: CR - Terminate Project [#permalink] New post 21 Jan 2009, 15:36
chicagocubsrule wrote:
botirvoy wrote:
priyankur_saha@ml.com wrote:
Which of the following best completes the passage below?
When a project is failing and should be terminated, plan to bring in a new manager. New managers are more likely to terminate the project than are the original managers because______

(A) the project may have failed for reasons that the original manager could not have foreseen
(B) organizations tend to reward managers who can overcome problems
(C) managerial decisions to terminate a project should depend on the likelihood of the project’s eventual success
(D) the original managers were not necessarily able to overcome problems caused by external events over which they had no control
(E) the new managers have no need to justify the earlier decision to maintain the project
PLease give reasons for choosing your answer

The argument needs to be strengthened and E does so.
It gives a reason why one should appoint a new manager to terminate the failing project.


The argument does not need to be strengthened (that's not what the question is asking)

I see it as a "strengthen" question in disguise. The argument says "bring a new manager". E says why. Let us know if your thinking differs.
Senior Manager
Senior Manager
User avatar
Joined: 19 Nov 2007
Posts: 477
Followers: 3

Kudos [?]: 49 [0], given: 4

GMAT ToolKit User GMAT Tests User
Re: CR - Terminate Project [#permalink] New post 21 Jan 2009, 19:26
priyankur_saha@ml.com wrote:
Which of the following best completes the passage below?
When a project is failing and should be terminated, plan to bring in a new manager. New managers are more likely to terminate the project than are the original managers because______

(A) the project may have failed for reasons that the original manager could not have foreseen
(B) organizations tend to reward managers who can overcome problems
(C) managerial decisions to terminate a project should depend on the likelihood of the project’s eventual success
(D) the original managers were not necessarily able to overcome problems caused by external events over which they had no control
(E) the new managers have no need to justify the earlier decision to maintain the project
PLease give reasons for choosing your answer

The argument needs to be strengthened and E does so.
It gives a reason why one should appoint a new manager to terminate the failing project.[/quote]

The argument does not need to be strengthened (that's not what the question is asking)[/quote]
I see it as a "strengthen" question in disguise. The argument says "bring a new manager". E says why. Let us know if your thinking differs.[/quote]

Botir,

Thats a good way of looking at it.
_________________

-Underline your question. It takes only a few seconds!
-Search before you post.

Senior Manager
Senior Manager
avatar
Joined: 02 Nov 2008
Posts: 283
Followers: 1

Kudos [?]: 30 [0], given: 2

GMAT Tests User
Re: CR - Terminate Project [#permalink] New post 21 Jan 2009, 22:04
I still don't agree that this is a strengthen question. Nothing in the question stem indicates that it is a str. q.
SVP
SVP
avatar
Joined: 17 Jun 2008
Posts: 1580
Followers: 12

Kudos [?]: 180 [0], given: 0

GMAT Tests User
Re: CR - Terminate Project [#permalink] New post 21 Jan 2009, 22:16
Agree with E.

Why is new manager required to terminate the project? This is because the current manager has to justify the continuity of the project. New manager does not have any such thing in the background.
Senior Manager
Senior Manager
avatar
Joined: 23 May 2008
Posts: 428
Followers: 4

Kudos [?]: 68 [0], given: 14

GMAT Tests User
Re: CR - Terminate Project [#permalink] New post 21 Jan 2009, 23:01
reply2spg wrote:
IMO D....Keep all things constant....now new manager will try to overcome all the possible problems those which are in his hands....however if some external factor is causing project to terminate and nobody from the organization have a control on that....then project has to be terminated....

therefore IMO D.


reply2msg if the old managers have no control over the external factors and the project needs to be terminated then there would be no use to bring in a new manager.....so the option D holds invalid.....

and the only option that seems logical is that the new manager doesn't need to give any justification to terminate that project.......

IMO E.......
Re: CR - Terminate Project   [#permalink] 21 Jan 2009, 23:01
    Similar topics Author Replies Last post
Similar
Topics:
Which of the following best completes the passage below? A puma 3 24 Mar 2008, 10:34
Which of the following best completes the passage below? One suntaurian 16 30 Jan 2008, 09:33
Experts publish their posts in the topic Which of the following best completes the passage below? A marcodonzelli 5 29 Jan 2008, 05:26
Which of the following best completes the passage below? In JCLEONES 5 07 Jan 2008, 15:52
Which of the following best completes the passage below? sidbidus 6 11 Jul 2007, 10:53
Display posts from previous: Sort by

Which of the following best completes the passage below?

  Question banks Downloads My Bookmarks Reviews Important topics  


GMAT Club MBA Forum Home| About| Privacy Policy| Terms and Conditions| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group and phpBB SEO

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.