|
Author |
Message |
|
TAGS:
|
|
|
Intern
Joined: 16 Aug 2012
Posts: 3
Followers: 0
Kudos [?]:
0
[0], given: 2
|
Working alone at its constant rate, machine K took 3 hours [#permalink]
29 Nov 2012, 22:44
Question Stats:
77% (02:47) correct
22% (01:36) wrong based on 2 sessions
Working alone at its constant rate, machine K took 3 hours to produce 1/4 of the units produced last Friday. Then machine M started working and the two machines, working simultaneously at their respective constant rates, took 6 hours to produce the rest of the units produced last Friday. How many hours would it have taken machine M, working alone at its constant rate, to produce all of the units produced last Friday? A. 8 B. 12 C. 16 D. 24 E. 30
Last edited by Bunuel on 30 Nov 2012, 03:07, edited 1 time in total.
Renamed the topic, edited the question and added the OA.
|
|
|
|
|
|
|
Director
Joined: 02 Jul 2012
Posts: 755
Location: India
Concentration: Strategy
GMAT 1: 740 Q49 V42
GPA: 3.8
WE: Engineering (Energy and Utilities)
Followers: 19
Kudos [?]:
257
[1] , given: 45
|
Re: No hours machine M takes to do last friday's work alone [#permalink]
29 Nov 2012, 23:09
1
This post received KUDOS
Lets assume the work to be something like moving 24 bricks. (Three fourths of 24 gives a multiple of 6 & one fourth of 24 gives a multiple of 3. Hence we are selecting 24 for ease of calculation. This method should work fine for any number) Machine K works at 2 bricks per hour K & M together work at 3 bricks per hour So, M works at 1 brick per hour So, M working alone would have took 24 hours. Answer should be D
_________________
Kudos Please... If my post helped.
Thanks To The Almighty - My GMAT Debrief My Own CR Question 1|My Own CR Question 2|My Own DS Question 1|My Own DS Question 2| My Own PS Question 1
|
|
|
|
|
|
Intern
Joined: 16 Aug 2012
Posts: 3
Followers: 0
Kudos [?]:
0
[0], given: 2
|
Re: No hours machine M takes to do last friday's work alone [#permalink]
30 Nov 2012, 00:21
the explanation sounds logical and the correct answer to this is D.Though,that's the (pick an answer an work upon) approach.how can we approach the same question through the conventional method (conceptual), by taking out the respective rates etc.can any one explain?
|
|
|
|
|
|
Senior Manager
Joined: 22 Dec 2011
Posts: 298
Followers: 2
Kudos [?]:
41
[2] , given: 32
|
Re: No hours machine M takes to do last friday's work alone [#permalink]
30 Nov 2012, 00:32
2
This post received KUDOS
samdarsh88 wrote: the explanation sounds logical and the correct answer to this is D.Though,that's the (pick an answer an work upon) approach.how can we approach the same question through the conventional method (conceptual), by taking out the respective rates etc.can any one explain? 1st 2nd and 3 columns are Rate, Time and Work done. R * 3 = 1/4 so rate of K = 1/12 Now 3/4 of the job is done by both K and M in 6 hrs (1/12 + rate of M ) * 6 = 3/4 solving we get rate of M = 1/24 Finally R * t = W 1/24 * t = 1 there t = 24 hrs HTH. Cheers
|
|
|
|
|
|
Intern
Joined: 16 Aug 2012
Posts: 3
Followers: 0
Kudos [?]:
0
[0], given: 2
|
Re: No hours machine M takes to do last friday's work alone [#permalink]
30 Nov 2012, 00:41
thanks for the explanation jp27.seems ,i was committing a careless mistake before. Hail guys.
|
|
|
|
|
|
Director
Joined: 02 Jul 2012
Posts: 755
Location: India
Concentration: Strategy
GMAT 1: 740 Q49 V42
GPA: 3.8
WE: Engineering (Energy and Utilities)
Followers: 19
Kudos [?]:
257
[0], given: 45
|
Re: No hours machine M takes to do last friday's work alone [#permalink]
30 Nov 2012, 01:31
samdarsh88 wrote: the explanation sounds logical and the correct answer to this is D.Though,that's the (pick an answer an work upon) approach.how can we approach the same question through the conventional method (conceptual), by taking out the respective rates etc.can any one explain? As I mentioned in my previous comment, I was not picking an answer. Rather I was just picking a smart number. In this case both happened to be the same. The same method would work just as well with any other number. Illustration : Lets assume the work to be making 30 bricks : Rate of Machine K = \frac{30}{4*3} = \frac{30}{12}Rate of K & M together = \frac{30*3}{4*6} = \frac{90}{24} = \frac{45}{12}Rate of machine M = \frac{45}{12} - \frac{30}{12} = \frac{15}{12} = \frac{5}{4}Machine M alone = \frac{30}{5/4} = \frac{120}{5} = 24So, we can see that answer is still 24. I had picked 24 only to avoid fractions.
_________________
Kudos Please... If my post helped.
Thanks To The Almighty - My GMAT Debrief My Own CR Question 1|My Own CR Question 2|My Own DS Question 1|My Own DS Question 2| My Own PS Question 1
|
|
|
|
|
|
Manager
Joined: 26 Jul 2011
Posts: 121
Location: India
WE: Marketing (Manufacturing)
Followers: 1
Kudos [?]:
14
[0], given: 15
|
Re: No hours machine M takes to do last friday's work alone [#permalink]
30 Nov 2012, 02:28
rate of machine k = (1/4)/3 (i.e it takes 3 hours to complete 1/4 of the work) ----> 1/12
Now both M and K working together at their respective rate complete 3/4 (the remaining work i.e 1- 1/4) of the work in 6 hours.
1/12 + 1/M = (3/4)/6 ------M = 24
hence the answer is D...
|
|
|
|
|
|
GMAT Club team member
Joined: 02 Sep 2009
Posts: 11534
Followers: 1795
Kudos [?]:
9563
[1] , given: 826
|
Re: Working alone at its constant rate, machine K took 3 hours [#permalink]
30 Nov 2012, 03:18
1
This post received KUDOS
samdarsh88 wrote: Working alone at its constant rate, machine K took 3 hours to produce 1/4 of the units produced last Friday. Then machine M started working and the two machines, working simultaneously at their respective constant rates, took 6 hours to produce the rest of the units produced last Friday. How many hours would it have taken machine M, working alone at its constant rate, to produce all of the units produced last Friday?
A. 8 B. 12 C. 16 D. 24 E. 30 Given that machines M and K, working together, can produce 3/4 of units in 6 hours. Since also given that machine K can produce 1/4 of units in 3 hours, then in 6 hours it can produce 2/4 of units. Which means that when working together, machine M produced 3/4-2/4=1/4 of units in 6 hours, thus it needs 6*4=24 hours to produce all of the units. Answer: D.
_________________
PLEASE READ AND FOLLOW: 11 Rules for Posting!!!
RESOURCES: [GMAT MATH BOOK]; 1. Triangles; 2. Polygons; 3. Coordinate Geometry; 4. Factorials; 5. Circles; 6. Number Theory
COLLECTION OF QUESTIONS: PS: 1. Tough and Tricky questions; 2. Hard questions; 3. Hard questions part 2; 4. Standard deviation; 5. Tough Problem Solving Questions With Solutions; 6. Probability and Combinations Questions With Solutions; 7 Tough and tricky exponents and roots questions; 8 12 Easy Pieces (or not?); 9 Bakers' Dozen; 10 Algebra set. NEW!!!
DS: 1. DS tough questions; 2. DS tough questions part 2; 3. DS tough questions part 3; 4. DS Standard deviation; 5. Inequalities; 6. 700+ GMAT Data Sufficiency Questions With Explanations; 7 Tough and tricky exponents and roots questions; 8 The Discreet Charm of the DS ; 9 Devil's Dozen!!!; 10 Number Properties set. NEW!!!
 What are GMAT Club Tests? 25 extra-hard Quant Tests
Find out what's new at GMAT Club - latest features and updates
|
|
|
|
|
|
|
Re: Working alone at its constant rate, machine K took 3 hours
[#permalink]
30 Nov 2012, 03:18
|
|
|
|
|
|
|
|
|
Similar topics |
Author |
Replies |
Last post |
|
Similar Topics:
|
|
|
|
Working alone at it's own constant rate, a machine seals K
|
ellisje22 |
2 |
03 Jan 2006, 18:45 |
|
1
|
|
Working alone at its constant rate, machine K took 3 hours
|
sset009 |
3 |
26 Jul 2008, 09:32 |
|
|
|
Working alone at its constant rate, machine K took 3 hours
|
Jcpenny |
1 |
05 Nov 2008, 19:50 |
|
|
|
Working alone at its constant rate, machine K took 3 hours
|
caiyun |
1 |
06 Nov 2008, 09:41 |
|
5
|
|
Working alone at its own constant rate, a machine seals k
|
anilnandyala |
7 |
17 Nov 2010, 08:35 |
|
|
|
|
|
|