Working together, A and B can do a job in 6 days. B and C [#permalink] New post 29 Oct 2005, 10:21
00:00

Question Stats:

0% (00:00) correct 0% (00:00) wrong based on 0 sessions
Working together, A and B can do a job in 6 days. B and C can do the same job in 10 days, while C and A can do it in 7.5 days. How long will it take if all A, B and C work together to complete the job?

(1) 8 days
(2) 5 days
(3) 3 days
(4) 7 days
(5) 6 days


How long will it take for A alone to complete the job?

(1) 8 days
(2) 6 days
(3) 10 days
(4) 20 days
(5) 5 days
Director
Director
User avatar
Joined: 27 Jun 2005
Posts: 518
Location: MS
Followers: 1

Kudos [?]: 3 [0], given: 0

GMAT Tests User
 [#permalink] New post 29 Oct 2005, 10:38
A B and C together will do the Job in 5 days .

A alone in 10 Days......?

what is OA ..?
RK
Manager
Manager
Joined: 01 Aug 2005
Posts: 71
Followers: 1

Kudos [?]: 0 [0], given: 0

 [#permalink] New post 29 Oct 2005, 11:48
I get 5 for number one and 10 for A alone as well, but the calculations took me quite a while, around 3-5 min! Is there some simple way of doing this one? What is OE
SVP
SVP
User avatar
Joined: 24 Sep 2005
Posts: 1913
Followers: 6

Kudos [?]: 55 [0], given: 0

GMAT Tests User
Re: PS Work Ascent 4/02 [#permalink] New post 29 Oct 2005, 19:30
GMATT73 wrote:
Working together, A and B can do a job in 6 days. B and C can do the same job in 10 days, while C and A can do it in 7.5 days. How long will it take if all A, B and C work together to complete the job?

(1) 8 days
(2) 5 days
(3) 3 days
(4) 7 days
(5) 6 days


How long will it take for A alone to complete the job?

(1) 8 days
(2) 6 days
(3) 10 days
(4) 20 days
(5) 5 days


Q.1: Using the productivity to solve:
Let x,y,z be the work A,B and C can do in one day.
We have:
x+y=1/6
y+z=1/10
x+z=1/7.5
---> 2(x+y+z)= 1/6+1/10+1/7.5= 24/60=2/5 ---> x+y+z=1/5 -----> if they work together, they'll finish the work in 5 days

Q.2 (x+y)+(x+z)-(y+z)= 2x= 1/6+1/7.5 -1/10= 12/60=1/5---> x=1/10
----> A alone can finish the work in 10 days.
Senior Manager
Senior Manager
Joined: 11 May 2004
Posts: 462
Location: New York
Followers: 1

Kudos [?]: 3 [0], given: 0

GMAT Tests User
 [#permalink] New post 30 Oct 2005, 17:47
Great explanations laxie...

for the first question, why do u multiply (x+y+z) by 2? Is it because of the double-counting?
GMAT Club Legend
GMAT Club Legend
User avatar
Joined: 07 Jul 2004
Posts: 5134
Location: Singapore
Followers: 9

Kudos [?]: 87 [0], given: 0

GMAT Tests User
 [#permalink] New post 31 Oct 2005, 00:00
Question 1
A and B can do 1/6 job in 1 day
B and C can do 1/10 job in 1 day
C and A can do 2/15 job in 1 day

1/A + 1/B = 1/6 ----(1)
1/B + 1/C = 1/10 ---(2)
1/C + 1/A = 2/15 --(3)

Adding (1), (2) and (3), we get:

2/A + 2/C + 2/B = 2/5
1/A + 1/C + 2/B = 1/5 job in 1 day
So A + B + C willl finishi 1 job in 5 days

Question 2
(1) - (2) --> 1/A - 1/C = 1/15 --(4)
(4) + (3) --> 2/A = 1/5
So A alone finish 1/10 job in 1 day = 10 days for 1 job
Current Student
User avatar
Joined: 29 Jan 2005
Posts: 5289
Followers: 17

Kudos [?]: 91 [0], given: 0

GMAT Tests User Reviews Badge
Re: PS Work Ascent 4/02 [#permalink] New post 01 Nov 2005, 00:35
laxieqv wrote:
GMATT73 wrote:
Working together, A and B can do a job in 6 days. B and C can do the same job in 10 days, while C and A can do it in 7.5 days. How long will it take if all A, B and C work together to complete the job?

(1) 8 days
(2) 5 days
(3) 3 days
(4) 7 days
(5) 6 days


How long will it take for A alone to complete the job?

(1) 8 days
(2) 6 days
(3) 10 days
(4) 20 days
(5) 5 days


Q.1: Using the productivity to solve:
Let x,y,z be the work A,B and C can do in one day.
We have:
x+y=1/6
y+z=1/10
x+z=1/7.5
---> 2(x+y+z)= 1/6+1/10+1/7.5= 24/60=2/5 ---> x+y+z=1/5 -----> if they work together, they'll finish the work in 5 days

Q.2 (x+y)+(x+z)-(y+z)= 2x= 1/6+1/7.5 -1/10= 12/60=1/5---> x=1/10
----> A alone can finish the work in 10 days.


Got it Laxie! Thanx for the explanation. Is there any reason why you are so fond of using the variables x, y, and z?
Re: PS Work Ascent 4/02   [#permalink] 01 Nov 2005, 00:35
    Similar topics Author Replies Last post
Similar
Topics:
New posts Working together A and B can do a job in 6 days. B & C gmacvik 6 26 Sep 2005, 19:36
New posts A, B and C can do a work in 6, 8, 12 days resp. B and C work remgeo 8 04 May 2006, 08:10
New posts A and B together can do a piece of work in 72/5 days ; B and jyotsnasarabu 1 08 Oct 2006, 04:37
Popular new posts A and B together can do a peace of work in 12 days,which B sravan_m444 13 05 Feb 2007, 11:30
Popular new posts 5 EXPERTS_POSTS_IN_THIS_TOPIC A and B working together can finish a job in d days. If A Himalayan 11 14 Jul 2007, 18:58
Display posts from previous: Sort by

Working together, A and B can do a job in 6 days. B and C

  Question banks Downloads My Bookmarks Reviews  


GMAT Club MBA Forum Home| About| Privacy Policy| Terms and Conditions| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group and phpBB SEO

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.