Working together, Jose and Jane can complete an assigned

  Question banks Downloads My Bookmarks Reviews  
Author Message
TAGS:
Manager
Manager
Joined: 11 Mar 2007
Posts: 154
Followers: 1

Kudos [?]: 3 [0], given: 0

Working together, Jose and Jane can complete an assigned [#permalink] New post 19 Aug 2007, 22:15
Working together, Jose and Jane can complete an assigned task in 20 days. However, if Jose worked alone and complete half the work and then Jane takes over the task and completes the second half of the task, the task will be completed in 45 days. How long will Jose take to complete the task if he worked alone? Assume that Jane is more efficient than Jose.

A. 25 days
B. 30 days
C. 60 days
D. 65 days
E. 36 days
GMAT Club Legend
GMAT Club Legend
User avatar
Joined: 07 Jul 2004
Posts: 5134
Location: Singapore
Followers: 9

Kudos [?]: 87 [0], given: 0

GMAT Tests User
 [#permalink] New post 19 Aug 2007, 22:32
Jose -> 1 job in x days -> 1/x job in 1 day
Jane -> 1 job in y days -> 1/y job in 1 day

Together, 1/x + 1/y = 1/20
x+y/xy = 1/20
20x+20y = xy

Jose takes x/2 days to finish 1/2 a job. Jane takes y/2 days to finish 1/2 a job. Together, x/2 + y/2 = 45 --> x+y = 90

So

20(x+y) = xy
20(90) = x(90-x)
1800 = 90x - x^2
x^2 - 90x + 1800 = 0
x = 60 days or 30 days. But we are told Jane is more efficient, so x = 60 days.
  [#permalink] 19 Aug 2007, 22:32
    Similar topics Author Replies Last post
Similar
Topics:
Popular new posts If A and B work together, they will complete a job in 7.5 GMATT73 10 29 Oct 2005, 10:19
New posts Working together, Jose and Jane can complete an assigned ggarr 5 09 Apr 2007, 20:23
New posts EXPERTS_POSTS_IN_THIS_TOPIC Working together, Jose and Jane can complete an assigned Ravshonbek 8 17 Nov 2007, 13:34
New posts working together at their constant rates , A and B can fill arjtryarjtry 6 18 Jul 2008, 06:08
New posts 1 John can complete a given task in 20 days. Jane will take arjtryarjtry 5 20 Jul 2008, 05:23
Display posts from previous: Sort by

Working together, Jose and Jane can complete an assigned

  Question banks Downloads My Bookmarks Reviews  


GMAT Club MBA Forum Home| About| Privacy Policy| Terms and Conditions| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group and phpBB SEO

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.