Find all School-related info fast with the new School-Specific MBA Forum

It is currently 22 Oct 2014, 00:07

Close

GMAT Club Daily Prep

Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Events & Promotions

Events & Promotions in June
Open Detailed Calendar

Working together, Jose and Jane can complete an assigned

  Question banks Downloads My Bookmarks Reviews Important topics  
Author Message
TAGS:
Manager
Manager
avatar
Joined: 11 Mar 2007
Posts: 154
Followers: 1

Kudos [?]: 4 [0], given: 0

Working together, Jose and Jane can complete an assigned [#permalink] New post 19 Aug 2007, 21:15
Working together, Jose and Jane can complete an assigned task in 20 days. However, if Jose worked alone and complete half the work and then Jane takes over the task and completes the second half of the task, the task will be completed in 45 days. How long will Jose take to complete the task if he worked alone? Assume that Jane is more efficient than Jose.

A. 25 days
B. 30 days
C. 60 days
D. 65 days
E. 36 days
GMAT Club Legend
GMAT Club Legend
User avatar
Joined: 07 Jul 2004
Posts: 5095
Location: Singapore
Followers: 19

Kudos [?]: 155 [0], given: 0

 [#permalink] New post 19 Aug 2007, 21:32
Jose -> 1 job in x days -> 1/x job in 1 day
Jane -> 1 job in y days -> 1/y job in 1 day

Together, 1/x + 1/y = 1/20
x+y/xy = 1/20
20x+20y = xy

Jose takes x/2 days to finish 1/2 a job. Jane takes y/2 days to finish 1/2 a job. Together, x/2 + y/2 = 45 --> x+y = 90

So

20(x+y) = xy
20(90) = x(90-x)
1800 = 90x - x^2
x^2 - 90x + 1800 = 0
x = 60 days or 30 days. But we are told Jane is more efficient, so x = 60 days.
  [#permalink] 19 Aug 2007, 21:32
    Similar topics Author Replies Last post
Similar
Topics:
8 John can complete a given task in 20 days. Jane will take arjtryarjtry 7 20 Jul 2008, 04:23
working together at their constant rates , A and B can fill arjtryarjtry 6 18 Jul 2008, 05:08
Experts publish their posts in the topic Working together, Jose and Jane can complete an assigned Ravshonbek 8 17 Nov 2007, 12:34
Working together, Jose and Jane can complete an assigned ggarr 5 09 Apr 2007, 19:23
If A and B work together, they will complete a job in 7.5 GMATT73 10 29 Oct 2005, 09:19
Display posts from previous: Sort by

Working together, Jose and Jane can complete an assigned

  Question banks Downloads My Bookmarks Reviews Important topics  


GMAT Club MBA Forum Home| About| Privacy Policy| Terms and Conditions| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group and phpBB SEO

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.