Summer is Coming! Join the Game of Timers Competition to Win Epic Prizes. Registration is Open. Game starts Mon July 1st.

It is currently 18 Jul 2019, 21:02

Close

GMAT Club Daily Prep

Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Close

Request Expert Reply

Confirm Cancel

A can complete a certain job in 12 days. B is 60%

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  
Author Message
TAGS:

Hide Tags

Find Similar Topics 
Manager
Manager
User avatar
Joined: 25 Sep 2012
Posts: 237
Location: India
Concentration: Strategy, Marketing
GMAT 1: 660 Q49 V31
GMAT 2: 680 Q48 V34
GMAT ToolKit User Reviews Badge
A can complete a certain job in 12 days. B is 60%  [#permalink]

Show Tags

New post 02 Jun 2014, 07:09
4
8
00:00
A
B
C
D
E

Difficulty:

  45% (medium)

Question Stats:

65% (01:27) correct 35% (01:26) wrong based on 297 sessions

HideShow timer Statistics


A can complete a certain job in 12 days. B is 60% more efficient than A. In how many days can B complete the same job?

(A) 6
(B) 6.25
(C) 7
(D) 7.5
(E) 4.8

Kudos if you like the question..

Little awkward explanation.60% more efficient means B can do 160% of work in same no. of days as A takes to do 100% of work.
160% work in 12 days
100% work in x days
x = \(\frac{(12*100)}{160}\)
Most Helpful Expert Reply
CEO
CEO
User avatar
D
Status: GMATINSIGHT Tutor
Joined: 08 Jul 2010
Posts: 2959
Location: India
GMAT: INSIGHT
Schools: Darden '21
WE: Education (Education)
Reviews Badge
Re: A can complete a certain job in 12 days. B is 60%  [#permalink]

Show Tags

New post 12 Jul 2015, 06:05
3
5
b2bt wrote:
A can complete a certain job in 12 days. B is 60% more efficient than A. In how many days can B complete the same job?

(A) 6
(B) 6.25
(C) 7
(D) 7.5
(E) 4.8


Alternate Method

Let, Total Work Unit = 120 Units

A can finish in 12 days = 120 unit work
i.e. A can finish in 1 days = 10 unit work
i.e. B can finish in 1 days = 10+(60/100)*10 = 16 unit work

Days in which B will complete the work alone = 120/16 = 30/4 = 7.5 days

Answer: Option D
_________________
Prosper!!!
GMATinsight
Bhoopendra Singh and Dr.Sushma Jha
e-mail: info@GMATinsight.com I Call us : +91-9999687183 / 9891333772
Online One-on-One Skype based classes and Classroom Coaching in South and West Delhi
http://www.GMATinsight.com/testimonials.html

ACCESS FREE GMAT TESTS HERE:22 ONLINE FREE (FULL LENGTH) GMAT CAT (PRACTICE TESTS) LINK COLLECTION
General Discussion
Math Expert
User avatar
V
Joined: 02 Sep 2009
Posts: 56257
Re: A can complete a certain job in 12 days. B is 60%  [#permalink]

Show Tags

New post 02 Jun 2014, 07:29
b2bt wrote:
A can complete a certain job in 12 days. B is 60% more efficient than A. In how many days can B complete the same job?

(A) 6
(B) 6.25
(C) 7
(D) 7.5
(E) 4.8

Kudos if you like the question..

Little awkward explanation.60% more efficient means B can do 160% of work in same no. of days as A takes to do 100% of work.
160% work in 12 days
100% work in x days
x = \(\frac{(12*100)}{160}\)


B is 60% more efficient than A, means that the rate of B is 1.6 times as greater as that of A.

So, if A can complete the job in 12 days, then B complete the same job in 12/1.6 = 12/(8/5) = 15/2 = 7.5 days.

Answer D.

P.S. Not exactly a GMAT wording.
_________________
Retired Moderator
avatar
Joined: 29 Apr 2015
Posts: 830
Location: Switzerland
Concentration: Economics, Finance
Schools: LBS MIF '19
WE: Asset Management (Investment Banking)
GMAT ToolKit User
Re: A can complete a certain job in 12 days. B is 60%  [#permalink]

Show Tags

New post 12 Jul 2015, 03:52
b2bt wrote:
A can complete a certain job in 12 days. B is 60% more efficient than A. In how many days can B complete the same job?

(A) 6
(B) 6.25
(C) 7
(D) 7.5
(E) 4.8

Kudos if you like the question..

Little awkward explanation.60% more efficient means B can do 160% of work in same no. of days as A takes to do 100% of work.
160% work in 12 days
100% work in x days
x = \(\frac{(12*100)}{160}\)


Set up a Rate Time Work Table and plug in the values:

Rate / Time / Work for A:
12 / 12 / 144

Rate / Time / Work for B:
19.2 / 7.5 / 144

Do not fall into the trap by just working with the time, i.e. taking 60% off from 12 days and subtracting it from 12. Trap Answer E.
_________________
Saving was yesterday, heat up the gmatclub.forum's sentiment by spending KUDOS!

PS Please send me PM if I do not respond to your question within 24 hours.
Senior Manager
Senior Manager
User avatar
B
Joined: 28 Jun 2015
Posts: 286
Concentration: Finance
GPA: 3.5
Re: A can complete a certain job in 12 days. B is 60%  [#permalink]

Show Tags

New post 12 Jul 2015, 10:18
Let the number of units of work done by A in one day = 10, so B does 16 units of work per day.

Total units of work done by A = 12*10 = 120 units.

No. of days taken by B to do 120 units of work = 120/16 = 7.5. Ans (D).
_________________
I used to think the brain was the most important organ. Then I thought, look what’s telling me that.
Manager
Manager
avatar
B
Joined: 06 Dec 2016
Posts: 243
Re: A can complete a certain job in 12 days. B is 60%  [#permalink]

Show Tags

New post 18 Apr 2017, 10:37
You could even do process elimination

let's start with C

7 x 1 3/5
56/5 or 11 1/5 Not the answer. Let's use a big number

D - 7 1/2 x 1 3/5
15/2 x 8/5
12

The answer is D
Target Test Prep Representative
User avatar
G
Status: Head GMAT Instructor
Affiliations: Target Test Prep
Joined: 04 Mar 2011
Posts: 2823
Re: A can complete a certain job in 12 days. B is 60%  [#permalink]

Show Tags

New post 08 Mar 2018, 17:44
1
b2bt wrote:
A can complete a certain job in 12 days. B is 60% more efficient than A. In how many days can B complete the same job?

(A) 6
(B) 6.25
(C) 7
(D) 7.5
(E) 4.8


The rate of A is 1/12.

Since B is 60% more efficient the rate of B is 1.6 x 1/12 = 1.6/12 = 16/120 = 2/15.

Since time is inverse of rate, B can complete the job in 15/2 = 7.5 days.

Answer: D
_________________

Jeffrey Miller

Head of GMAT Instruction

Jeff@TargetTestPrep.com
TTP - Target Test Prep Logo
122 Reviews

5-star rated online GMAT quant
self study course

See why Target Test Prep is the top rated GMAT quant course on GMAT Club. Read Our Reviews

If you find one of my posts helpful, please take a moment to click on the "Kudos" button.

Non-Human User
User avatar
Joined: 09 Sep 2013
Posts: 11702
Re: A can complete a certain job in 12 days. B is 60%  [#permalink]

Show Tags

New post 12 Mar 2019, 00:15
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
_________________
GMAT Club Bot
Re: A can complete a certain job in 12 days. B is 60%   [#permalink] 12 Mar 2019, 00:15
Display posts from previous: Sort by