Last visit was: 25 Apr 2024, 09:23 It is currently 25 Apr 2024, 09:23

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
Math Expert
Joined: 02 Sep 2009
Posts: 92914
Own Kudos [?]: 618961 [12]
Given Kudos: 81595
Send PM
Retired Moderator
Joined: 25 Feb 2013
Posts: 895
Own Kudos [?]: 1527 [4]
Given Kudos: 54
Location: India
GPA: 3.82
Send PM
Senior PS Moderator
Joined: 26 Feb 2016
Posts: 2873
Own Kudos [?]: 5205 [1]
Given Kudos: 47
Location: India
GPA: 3.12
Send PM
Manager
Manager
Joined: 22 Nov 2016
Posts: 205
Own Kudos [?]: 267 [3]
Given Kudos: 50
Concentration: Leadership, Strategy
Send PM
A and B together complete a piece of job in 10 days, B and C together [#permalink]
1
Kudos
2
Bookmarks
When we are given AB, BC and CA rates, there is a quicker method. Eventually we have to add the rates, hence, the shortcut is

2*(combined rate) = Sum of rates of AB + BC + CA

\(2*x= \frac{1}{8}+\frac{1}{10}+\frac{1}{15}\)

\(x=\frac{7}{48}\)

Flip the rate to get the time.

Answer is \(\frac{48}{7}\)
Target Test Prep Representative
Joined: 04 Mar 2011
Status:Head GMAT Instructor
Affiliations: Target Test Prep
Posts: 3043
Own Kudos [?]: 6273 [2]
Given Kudos: 1646
Send PM
Re: A and B together complete a piece of job in 10 days, B and C together [#permalink]
2
Bookmarks
Expert Reply
Bunuel wrote:
A and B together complete a piece of job in 10 days, B and C together complete the same piece of job in 15 days, whereas A and C together complete it in 8 days. How many days will it take to complete the job if all of them work together?


A. \(3 \frac{3}{7}\)

B. \(6 \frac{6}{7}\)

C. \(7\)

D. \(7 \frac{23}{35}\)

E. \(7 \frac{6}{7}\)


We can let a = the number of days A will complete the job alone, b = the number of days B will complete the job alone and c = the number of days C will complete the job alone. We can now create the following combined rate equations:

1/a + 1/b = 1/10

and

1/b + 1/c = 1/15

and

1/a + 1/c = 1/8

Adding the equations together, we have:

2/a + 2/b + 2/c = 1/10 + 1/15 + 1/8

2/a + 2/b + 2/c = 12/120 + 8/120 + 15/120

2/a + 2/b + 2/c = 35/120= 7/24

Thus, 1/a + 1/b + 1/c = 7/24 x 1/2 = 7/48.

So, the time it would take the machines to work together is 1/(7/48) = 48/7 = 6 6/7.

Answer: B
Board of Directors
Joined: 11 Jun 2011
Status:QA & VA Forum Moderator
Posts: 6072
Own Kudos [?]: 4689 [0]
Given Kudos: 463
Location: India
GPA: 3.5
WE:Business Development (Commercial Banking)
Send PM
Re: A and B together complete a piece of job in 10 days, B and C together [#permalink]
Bunuel wrote:
A and B together complete a piece of job in 10 days, B and C together complete the same piece of job in 15 days, whereas A and C together complete it in 8 days. How many days will it take to complete the job if all of them work together?


A. \(3 \frac{3}{7}\)

B. \(6 \frac{6}{7}\)

C. \(7\)

D. \(7 \frac{23}{35}\)

E. \(7 \frac{6}{7}\)

Let the total work be 120 units

So, Efficiency of A and B together is 12
Efficiency of B and C together is 8
Efficiency of A and C together is 15

Combined efficiency is \(\frac{12+8+15}{2} = \frac{35}{2}\)

Time required to complete the work is \(120*\frac{2}{35}\) = \(6 \frac{6}{7}\)

Answer will be (B) \(6 \frac{6}{7}\)
Manager
Manager
Joined: 20 Feb 2017
Posts: 154
Own Kudos [?]: 438 [0]
Given Kudos: 489
Location: India
Concentration: Operations, Strategy
WE:Engineering (Other)
Send PM
A and B together complete a piece of job in 10 days, B and C together [#permalink]
Lets solve this using LCM method
A+B = 10 days
B+C = 15 days
C+D = 8 days
LCM of 10,15 and 8 is 120.
so 120 units of work done (Assume)
therefore rate of work
A+B = 120/10 = 12 units per day
B+C = 120/15 = 8 units per day
C+D = 120/8 = 15 units per day.
So if all of them work together i.e A+B+C = 35/ 2units ((12+8+15)/2)(we are dividing by 2 because each rate gets repeated
twice)
hence number of days = 120/ (35/2) = 48/7 (answer B)
Intern
Intern
Joined: 26 Sep 2016
Posts: 6
Own Kudos [?]: [0]
Given Kudos: 14
Send PM
Re: A and B together complete a piece of job in 10 days, B and C together [#permalink]
sasyaharry wrote:
When we are given AB, BC and CA rates, there is a quicker method. Eventually we have to add the rates, hence, the shortcut is

2*(combined rate) = Sum of rates of AB + BC + CA

\(2*x= \frac{1}{8}+\frac{1}{10}+\frac{1}{15}\)

\(x=\frac{7}{48}\)

Flip the rate to get the time.

Answer is \(\frac{48}{7}\)


what is combined rate?
Senior PS Moderator
Joined: 26 Feb 2016
Posts: 2873
Own Kudos [?]: 5205 [0]
Given Kudos: 47
Location: India
GPA: 3.12
Send PM
Re: A and B together complete a piece of job in 10 days, B and C together [#permalink]
Combined rate here will refer to the rate at which the three of them(A,B, and C) do the work.

I have used a different method to solve this problem. Check if that method is clear
User avatar
Non-Human User
Joined: 09 Sep 2013
Posts: 32675
Own Kudos [?]: 821 [0]
Given Kudos: 0
Send PM
Re: A and B together complete a piece of job in 10 days, B and C together [#permalink]
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
GMAT Club Bot
Re: A and B together complete a piece of job in 10 days, B and C together [#permalink]
Moderators:
Math Expert
92914 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne