Last visit was: 25 Apr 2024, 16:43 It is currently 25 Apr 2024, 16:43

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
avatar
Intern
Intern
Joined: 02 Jun 2013
Posts: 15
Own Kudos [?]: 107 [15]
Given Kudos: 74
Send PM
avatar
Intern
Intern
Joined: 01 Aug 2013
Posts: 9
Own Kudos [?]: 9 [1]
Given Kudos: 0
Location: United States
Concentration: Operations, International Business
GMAT 1: 710 Q47 V41
GPA: 3.65
Send PM
Intern
Intern
Joined: 10 Jun 2019
Posts: 7
Own Kudos [?]: 3 [3]
Given Kudos: 7
Send PM
Current Student
Joined: 30 May 2019
Posts: 126
Own Kudos [?]: 252 [0]
Given Kudos: 1696
Location: Tajikistan
Concentration: Finance, General Management
Schools: Simon '24 (A)
GMAT 1: 610 Q46 V28
GMAT 2: 730 Q49 V40 (Online)
GPA: 3.37
WE:Analyst (Consulting)
Send PM
Re: P,Q and R can do a piece of work in 4,6 and 12 days working [#permalink]
sharankotagiri wrote:
P takes 4 days working 12 hrs/day to complete the job i.e. he takes 48 man-hours to complete the job.
Q takes 6 days working 12 hrs/day to complete the job i.e. he takes 72 man-hours to complete the job.
R takes 12 days working 12 hrs/day to complete the job i.e. he takes 144 man-hours to complete the job.

Taking the LCM of the total man-hours, let us say that the total work was 144 units.

If P completes 144 units in 48 hours, then P completes 24 units in 8 hours (by unitary method).
If Q completes 144 units in 72 hours, then Q completes 16 units in 8 hours (by unitary method).
If R completes 144 units in 144 hours, then R completes 8 units in 8 hours (by unitary method).

So on days 1 and 2, we have
First 8 hours (P) - 24 units
Next 8 hours (Q) - 16 units
Last 8 hours (R) - 8 units
Total - 48 units per day, so 96 units completed in 2 days.

Now, P leaves after day 2 while Q and R continue working alternatively. So on day 3, we have
First 8 hours (Q) - 16 units
Next 8 hours (R) - 8 units
Last 8 hours (Q) - 16 units
Total - 40 units per day

So, we have 136 units completed in 3 complete days and require 8 more hours to complete the task.

On day 4, resuming from who did the work last, we have
First 8 hours (R) - 8 units

So we have completed the task and taken 3 complete days and 8/24 => 1/3rd of the 4th day.

So total days taken => 3 + 1/3 = 10/3 days. Hence, Option A is the right choice.



Hello,

Could you please help me out here. The question says max number of working hours in any day is 12h, but you are taking all 24h. Why so?
Bunuel, could you please shed some light here?
Thank you
Intern
Intern
Joined: 09 Oct 2019
Posts: 8
Own Kudos [?]: 3 [0]
Given Kudos: 2
Send PM
Re: P,Q and R can do a piece of work in 4,6 and 12 days working [#permalink]
sharankotagiri wrote:
P takes 4 days working 12 hrs/day to complete the job i.e. he takes 48 man-hours to complete the job.
Q takes 6 days working 12 hrs/day to complete the job i.e. he takes 72 man-hours to complete the job.
R takes 12 days working 12 hrs/day to complete the job i.e. he takes 144 man-hours to complete the job.

Taking the LCM of the total man-hours, let us say that the total work was 144 units.

If P completes 144 units in 48 hours, then P completes 24 units in 8 hours (by unitary method).
If Q completes 144 units in 72 hours, then Q completes 16 units in 8 hours (by unitary method).
If R completes 144 units in 144 hours, then R completes 8 units in 8 hours (by unitary method).

So on days 1 and 2, we have
First 8 hours (P) - 24 units
Next 8 hours (Q) - 16 units
Last 8 hours (R) - 8 units
Total - 48 units per day, so 96 units completed in 2 days.

Now, P leaves after day 2 while Q and R continue working alternatively. So on day 3, we have
First 8 hours (Q) - 16 units
Next 8 hours (R) - 8 units
Last 8 hours (Q) - 16 units
Total - 40 units per day

So, we have 136 units completed in 3 complete days and require 8 more hours to complete the task.

On day 4, resuming from who did the work last, we have
First 8 hours (R) - 8 units

So we have completed the task and taken 3 complete days and 8/24 => 1/3rd of the 4th day.

So total days taken => 3 + 1/3 = 10/3 days. Hence, Option A is the right choice.



it's ok until the one highlighted
why 40 units per day for the sum of 24 hrs if the question says 12 hrs working a day ?

I got 2/3 : 5/18 * 2 = 2/3 * 18/5 * 2 = 24/5
Total days taken = 2 + 24/5 day

please help
Intern
Intern
Joined: 26 Sep 2019
Posts: 10
Own Kudos [?]: 20 [0]
Given Kudos: 15
GMAT 1: 620 Q49 V26 (Online)
GMAT 2: 740 Q51 V39 (Online)
Send PM
Re: P,Q and R can do a piece of work in 4,6 and 12 days working [#permalink]
The question does not limit the daily working hour capabilities of machines, saying "working 12 hours a day". It mentions 12 hours only to give information about the capacities of machines. What it says if machine p would work 12 hours a day, it would complete the job in 4 days, alternatively it could say if machine p works 24 hours a day, it would complete the job in 2 days and nothing would change in the question.
GMAT Club Bot
Re: P,Q and R can do a piece of work in 4,6 and 12 days working [#permalink]
Moderators:
Math Expert
92915 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne