Last visit was: 23 Apr 2024, 12:48 It is currently 23 Apr 2024, 12:48

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
Math Expert
Joined: 02 Sep 2009
Posts: 92881
Own Kudos [?]: 618579 [9]
Given Kudos: 81562
Send PM
GMAT Club Legend
GMAT Club Legend
Joined: 03 Oct 2013
Affiliations: CrackVerbal
Posts: 4946
Own Kudos [?]: 7624 [3]
Given Kudos: 215
Location: India
Send PM
Director
Director
Joined: 21 Jun 2017
Posts: 638
Own Kudos [?]: 530 [1]
Given Kudos: 4092
Location: India
Concentration: Finance, Economics
GMAT 1: 660 Q49 V31
GMAT 2: 620 Q47 V30
GMAT 3: 650 Q48 V31
GPA: 3.1
WE:Corporate Finance (Non-Profit and Government)
Send PM
Director
Director
Joined: 21 Jun 2017
Posts: 638
Own Kudos [?]: 530 [1]
Given Kudos: 4092
Location: India
Concentration: Finance, Economics
GMAT 1: 660 Q49 V31
GMAT 2: 620 Q47 V30
GMAT 3: 650 Q48 V31
GPA: 3.1
WE:Corporate Finance (Non-Profit and Government)
Send PM
Re: A team of workers was employed by a contractor who undertook to finish [#permalink]
1
Kudos
Bunuel wrote:
A team of workers was employed by a contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take?

(A) 8
(B) 9
(C) 10
(D) 12
(E) 13


Hi Bunuel, I feel the question is asking " how many days the work was completed after the rate of output was increased ". Hence, I went with B. Could you please point out the flaw in my approach?
Math Expert
Joined: 02 Sep 2009
Posts: 92881
Own Kudos [?]: 618579 [1]
Given Kudos: 81562
Send PM
Re: A team of workers was employed by a contractor who undertook to finish [#permalink]
1
Kudos
Expert Reply
ShankSouljaBoi wrote:
Bunuel wrote:
A team of workers was employed by a contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take?

(A) 8
(B) 9
(C) 10
(D) 12
(E) 13


Hi Bunuel, I feel the question is asking " how many days the work was completed after the rate of output was increased ". Hence, I went with B. Could you please point out the flaw in my approach?


Agree, the wording could have been better. Edited the question. Hope now it's better.
Current Student
Joined: 15 Aug 2020
Posts: 58
Own Kudos [?]: 76 [1]
Given Kudos: 286
Location: United States (OR)
Concentration: Finance, Organizational Behavior
GMAT 1: 770 Q50 V46
GPA: 3.73
WE:Analyst (Mutual Funds and Brokerage)
Send PM
Re: A team of workers was employed by a contractor who undertook to finish [#permalink]
1
Kudos
This seems like an easy one to do trial and error with the answers:

A) 360/8 = 45 units per day
B) 360/9 = 40 units per day
C) 360/10 = 36 units per day
D) 360/12 = 30 units per day
E) 360/13 = 27ish or 28ish units per day

Notice the difference between B & C is 4 units per day, hence B must be the +4 unit rate and C must be the original rate, hence C is the answer. Good strategy for plugging answers is to start with C, so if you were lucky enough to start with C and go up this took very little math.
User avatar
Non-Human User
Joined: 09 Sep 2013
Posts: 32626
Own Kudos [?]: 821 [0]
Given Kudos: 0
Send PM
Re: A team of workers was employed by a contractor who undertook to finish [#permalink]
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
GMAT Club Bot
Re: A team of workers was employed by a contractor who undertook to finish [#permalink]