Last visit was: 24 Apr 2024, 05:59 It is currently 24 Apr 2024, 05:59

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Manager
Manager
Joined: 14 Dec 2004
Posts: 68
Own Kudos [?]: 520 [0]
Given Kudos: 0
Send PM
User avatar
Director
Director
Joined: 25 Nov 2004
Posts: 707
Own Kudos [?]: 448 [0]
Given Kudos: 0
Send PM
avatar
Intern
Intern
Joined: 04 Feb 2005
Posts: 7
Own Kudos [?]: 47 [0]
Given Kudos: 0
Send PM
User avatar
Current Student
Joined: 13 Jun 2004
Posts: 583
Own Kudos [?]: 132 [0]
Given Kudos: 0
Location: London, UK
Schools:Tuck'08
Send PM
Re: David completes 60% of an assigned task in 8 days and [#permalink]
jma123,

16/3 is the remaining work

3/3 is the working rate of David
we know that Ron is 1/3d as efficient as David : 1/3
so they work at a rate of 4/3 days

(16/3) / (4/3)
User avatar
Director
Director
Joined: 25 Nov 2004
Posts: 707
Own Kudos [?]: 448 [0]
Given Kudos: 0
Send PM
Re: David completes 60% of an assigned task in 8 days and [#permalink]
jma123 wrote:
Please explain how you got the last part "days david and ron worked together"thanks.


total days req= 8/0.6=40/3
remaining days, d= (8/0.6)-8=16/3
days david and ron worked togather = (16/3)/4/3=4 days

if he works alone, david takes 16/3 days to work at his current speed.
if he works togather with ron, whose speed is 1/3 of david's, it takes (16/3)/(4/3) days to finish the job. their combined speed =1+1/3=4/3. explain more, if any.
User avatar
Manager
Manager
Joined: 25 Oct 2004
Posts: 142
Own Kudos [?]: 285 [0]
Given Kudos: 0
Send PM
Re: David completes 60% of an assigned task in 8 days and [#permalink]
4 days

In 8 days David finishes 60% of the job. So to complete the job he takes 40/3 days. So each day he finishes 3/40th of the job.

Ron is 1/3rd as efficient So he finishes 3/40*1/3 =1/40th of the job each day.

When both work together they finish 3/40+1/40= 4/40 each day

David had already finished 60% of the job . for the bal 40% he and Ron work together. So no of days both work together= 40/100* 40/4=4 days
User avatar
Director
Director
Joined: 30 Sep 2004
Posts: 687
Own Kudos [?]: 1448 [0]
Given Kudos: 0
Location: Germany
Send PM
Re: David completes 60% of an assigned task in 8 days and [#permalink]
in 1 day david completes 1/(80/6) and in 8 days 8/(80/6)

ron is 1/3 as efficient and in 1 day he does 1/40

a complete job is equal to the sum of the fractional parts or is equal to one => 8/(80/6) + x/(80/6) + x/(40)=1 => solve for x

a little bit too long but i just want to show the formulas:

1/x + 1/x = 1/x => where x is the total time in hours and 1/x is the fractional part of job done in 1 hour

or

x/5 + x/8 = 1 => where x is the fractional part each does in x days; 5 and 8 are their rates
User avatar
Intern
Intern
Joined: 11 Jan 2005
Posts: 29
Own Kudos [?]: 4 [0]
Given Kudos: 0
Location: Mexico City
Send PM
Re: David completes 60% of an assigned task in 8 days and [#permalink]
it works quite easily if you take the total job as 100

say that in 8 days 60 has been done which equals 7.5 per day.

add in the bro at 1/3 of 7.5= 2.5 so now we are doing 10 per day look at the remaining 40 to be done and it is clearly 4 days.
User avatar
Intern
Intern
Joined: 28 Jan 2005
Posts: 9
Own Kudos [?]: 4 [0]
Given Kudos: 0
Send PM
Re: David completes 60% of an assigned task in 8 days and [#permalink]
In 8 days 60/100 i.e. 3/5 work has been done.

If efficiency of David=1
efficiency of Ron=1/3

acording to formulae:

[man(d)*efficiency(d)*days worked(d)]/part of work done=(man(ron+david)*daysworked)/part of work done

(1*1*8)/(3/5)=(4x/3)/(2/5)
=>x=4 days
User avatar
Manager
Manager
Joined: 15 Feb 2005
Posts: 116
Own Kudos [?]: 13 [0]
Given Kudos: 0
Location: Rockville
Send PM
Re: David completes 60% of an assigned task in 8 days and [#permalink]
christoph wrote:
in 1 day david completes 1/(80/6) and in 8 days 8/(80/6)

where does the 80 come from?

i did it a little differently
if 60% is done in 8 days 7.5% is done in 1 day
Ron is 1/3 as efficient so in 1 day he does 2.5% of the task
WHAT IS LEFT:
40%=7.5X+2.5X
X is time they both finish 40% in
4 days
(note: you can do this since all the numbers are in %, i guess it is the same as taking total of the job as 100
avatar
Intern
Intern
Joined: 17 Feb 2005
Posts: 6
Own Kudos [?]: 62 [0]
Given Kudos: 0
Location: SE Michigan
Send PM
Re: David completes 60% of an assigned task in 8 days and [#permalink]
a. 4

60% in 8 days
=> 100% in 40/3 days
& 40% in 16/3 days

1/3 efficient => 100% in 40 days => 40% in 16 days

together 1/t = 1/16 + 3/16
=> t = 4
User avatar
Intern
Intern
Joined: 20 Dec 2004
Posts: 9
Own Kudos [?]: [0]
Given Kudos: 0
Send PM
Re: David completes 60% of an assigned task in 8 days and [#permalink]
4 days seems right to me
User avatar
Intern
Intern
Joined: 17 Dec 2004
Posts: 26
Own Kudos [?]: 36 [0]
Given Kudos: 0
Send PM
Re: David completes 60% of an assigned task in 8 days and [#permalink]
[quote="Caspace"]it works quite easily if you take the total job as 100

say that in 8 days 60 has been done which equals 7.5 per day.

add in the bro at 1/3 of 7.5= 2.5 so now we are doing 10 per day look at the remaining 40 to be done and it is clearly 4 days.[/quote]

This is essentially how I did it as well:

David completed 60% of the assignment in 8 days, which means that he completed 7.5% each day. His brother, Ron, completed 1/3 of that (or 2.5% each day). Together, they can complete 10% of the assignment each day. With 40% to complete, they worked together for 4 days to complete it.
avatar
Director
Director
Joined: 03 Jan 2005
Posts: 971
Own Kudos [?]: 769 [1]
Given Kudos: 0
Send PM
Re: David completes 60% of an assigned task in 8 days and [#permalink]
1
Kudos
If you want easy arithmatic here's how:

8 days D can finish 60%, therefore every four days he finishes 30%. His brother's speed is 1/3 of his. So every four days he finishes 10%. When they work together every four days they finish 30+10=40%, which is exactly what they needed.
User avatar
Director
Director
Joined: 30 Sep 2004
Posts: 687
Own Kudos [?]: 1448 [0]
Given Kudos: 0
Location: Germany
Send PM
Re: David completes 60% of an assigned task in 8 days and [#permalink]
Rupstar wrote:
christoph wrote:
in 1 day david completes 1/(80/6) and in 8 days 8/(80/6)

where does the 80 come from?

i did it a little differently
if 60% is done in 8 days 7.5% is done in 1 day
Ron is 1/3 as efficient so in 1 day he does 2.5% of the task
WHAT IS LEFT:
40%=7.5X+2.5X
X is time they both finish 40% in
4 days
(note: you can do this since all the numbers are in %, i guess it is the same as taking total of the job as 100


i calculated his rate. in 8 days he does 60% and in 80/6 he does 100%.
User avatar
Director
Director
Joined: 18 Nov 2004
Posts: 679
Own Kudos [?]: 198 [0]
Given Kudos: 0
Send PM
Re: David completes 60% of an assigned task in 8 days and [#permalink]
HongHu wrote:
If you want easy arithmatic here's how:

8 days D can finish 60%, therefore every four days he finishes 30%. His brother's speed is 1/3 of his. So every four days he finishes 10%. When they work together every four days they finish 30+10=40%, which is exactly what they needed.


I like ur ways to handle word problems, seems to be much faster if one can get a hang of it e.g. how did u know to think abt the amt of work in four days interval only, is it becose 40% work is left, is there any rule of thumb in this ?
avatar
Director
Director
Joined: 03 Jan 2005
Posts: 971
Own Kudos [?]: 769 [1]
Given Kudos: 0
Send PM
Re: David completes 60% of an assigned task in 8 days and [#permalink]
1
Kudos
Normally I'd do it to the smallest integer, and take it from there. This may not work every time though, but it's still good to save you a bit time if it works, and if it doesn't you simply have to go one step further.

For example in one of the other posts, we have
4m=6s or something like that
I'd simplify it to
2m=3s
instead of m=1.5s
Then when I want to know 16m it's easier to multiple 3 with 8, compare to 1.5 with 16.

Same thing with this one. We have 8 vs 60. It's easier to simplify it to 4 vs 30 than to simplify it to 1 vs 7.5. The 30 is also easier to handle when we want to multiply it by 1/3. Lots of GMAT math problems have nice numbers like this that would save you time if you know the trick.
User avatar
Senior Manager
Senior Manager
Joined: 18 Feb 2005
Posts: 360
Own Kudos [?]: 20 [0]
Given Kudos: 0
Send PM
Re: David completes 60% of an assigned task in 8 days and [#permalink]
60% done in 8 days

Another person B joins A and is 1/3 efficient of A....

So man power is 4/3 times A .So work can be done in 3/4 time

So 60% can be done in (3/4)*8 = 6 days

So remaining 40% can be done in 4 days !!!
avatar
Intern
Intern
Joined: 29 Mar 2005
Posts: 34
Own Kudos [?]: 10 [0]
Given Kudos: 0
Send PM
Re: David completes 60% of an assigned task in 8 days and [#permalink]
cloaked_vessel wrote:
David completes 60% of an assigned task in 8 days and realizes that he will be behind schedule at the present rate. He takes the assistance of his younger brother Ron who is one-third as efficient as David is and completes the assigned task on schedule. How many days did David and Ron work together?

a. 4
b. 6
c. 8
d. 12
e. 14


Sometimes it helps to look at the answer list for clues... in this case, you're given that he's completed 60% in 8 days, so at the current rate he'd be complete in ~14 days. Cancel out c/d/e right away, as it won't take him longer with additional help. 6 days would be close without his brother, but it has to be less leaving you 4



Archived Topic
Hi there,
This topic has been closed and archived due to inactivity or violation of community quality standards. No more replies are possible here.
Where to now? Join ongoing discussions on thousands of quality questions in our Quantitative Questions Forum
Still interested in this question? Check out the "Best Topics" block above for a better discussion on this exact question, as well as several more related questions.
Thank you for understanding, and happy exploring!
GMAT Club Bot
Re: David completes 60% of an assigned task in 8 days and [#permalink]
Moderator:
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne