Last visit was: 25 Apr 2024, 13:01 It is currently 25 Apr 2024, 13:01

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
e-GMAT Representative
Joined: 04 Jan 2015
Posts: 3726
Own Kudos [?]: 16841 [42]
Given Kudos: 165
Send PM
Most Helpful Reply
Manager
Manager
Joined: 17 May 2015
Posts: 200
Own Kudos [?]: 3019 [8]
Given Kudos: 85
Send PM
General Discussion
Manager
Manager
Joined: 14 Jun 2018
Posts: 171
Own Kudos [?]: 257 [1]
Given Kudos: 176
Send PM
Intern
Intern
Joined: 30 Sep 2018
Posts: 14
Own Kudos [?]: 16 [2]
Given Kudos: 7
Send PM
Re: Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
2
Kudos
I've solved this differently.

40 workers, 20 days, 1/4
40 workers, 10 days, 1/2 * 1/4 = 1/8

Amount of work incomplete - 3/4

Therefore, if 40 workers complete 1/8th of the work in 10 days, we should have 240 (40*6) workers to complete 6*(1/8) work in 10 days.

Additional workers = 240 - the 40 who are already working = 200 I.e. (C)

Hope this helps.

Posted from my mobile device
Intern
Intern
Joined: 18 Oct 2017
Posts: 2
Own Kudos [?]: 0 [0]
Given Kudos: 9
Send PM
Re: Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
Hey Nikhilaery, can you explain how did you arrive at
Quote:
Therefore, if 40 workers complete 1/8th of the work in 10 days, we should have 240 (40*6) workers to complete 6*(1/8) work in 10 days.
Intern
Intern
Joined: 30 Sep 2018
Posts: 14
Own Kudos [?]: 16 [4]
Given Kudos: 7
Send PM
Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
2
Kudos
2
Bookmarks
Hi Harsh,

Firstly, the key is "all the workers work at a constant rate".

I hope you understand how I arrived at 40 workers complete 1/8th piece of work in 10 days.

So knowing that 1/4th of work is already completed, we can infer that 3/4th is still pending. If I could arrive at an equation which could tell me how many workers and days will be required to finish 3/4th of pending work, that would suffice my requirement.

40 workers in 10 days complete 1/8th piece of work.

So, let's say, if in the same period I have to double the work being done in 10 days or same time, I'll simply double the number of workers working at a constant rate.

I'll thus say
40 workers x 2 in 10 days will do double the work they do I.e. 2 x 1/8th piece of work

Now, we know that what's pending is 3/4th. And 6 x (1/8) will give us (3/4)

So, if you want to finish the pending work in 10 days, you'll have to increase the workers.

Hence, 40 workers x 6 in 10 days will complete 3/4th of pending work.

Hope this helps.

Posted from my mobile device
Intern
Intern
Joined: 18 Oct 2017
Posts: 2
Own Kudos [?]: 0 [0]
Given Kudos: 9
Send PM
Re: Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
Hi Nikhilaery

Thanks this helps

Quote:
Hi Harsh,

Firstly, the key is "all the workers work at a constant rate".

I hope you understand how I arrived at 40 workers complete 1/8th piece of work in 10 days.

So knowing that 1/4th of work is already completed, we can infer that 3/4th is still pending. If I could arrive at an equation which could tell me how many workers and days will be required to finish 3/4th of pending work, that would suffice my requirement.

40 workers in 10 days complete 1/8th piece of work.

So, let's say, if in the same period I have to double the work being done in 10 days or same time, I'll simply double the number of workers working at a constant rate.

I'll thus say
40 workers x 2 in 10 days will do double the work they do I.e. 2 x 1/8th piece of work

Now, we know that what's pending is 3/4th. And 6 x (1/8) will give us (3/4)

So, if you want to finish the pending work in 10 days, you'll have to increase the workers.

Hence, 40 workers x 6 in 10 days will complete 3/4th of pending work.

Hope this helps.
e-GMAT Representative
Joined: 04 Jan 2015
Posts: 3726
Own Kudos [?]: 16841 [4]
Given Kudos: 165
Send PM
Re: Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
4
Bookmarks
Expert Reply
Given:
    • Initial number of workers = 40
    • The work must be completed in 30 days
    • After, 20 days, only \(\frac{1}{4}^{th}\) of the work was completed
    • All the workers work at a constant rate

To find:
    • The number of new workers to be recruited, so that the work gets completed on time

Approach and Working:
    • If 40 workers can complete \(\frac{1}{4}^{th}\) of the work in 20 days, they can finish the work in 20 * 4 = 80 days.
      o Implies, total work = 40 * 80 ………… (1)

    • Now, let us assume that the number of new workers = x
    • Thus, 40 + x workers must finish the rest \(\frac{3}{4}^{th}\) of the work in remaining 10 days
      o Implies, total work = \((40 + x) * 10 * \frac{4}{3}\) …………. (2)

    Equating (1) and (2), we get,
    • \(40 * 80 = (\frac{40}{3}) * (40 + x)\)
    • Thus, x = 240 – 40 = 200

Hence the correct answer is Option C.

Answer: C
GMAT Club Legend
GMAT Club Legend
Joined: 03 Jun 2019
Posts: 5344
Own Kudos [?]: 3964 [1]
Given Kudos: 160
Location: India
GMAT 1: 690 Q50 V34
WE:Engineering (Transportation)
Send PM
Re: Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
1
Kudos
EgmatQuantExpert wrote:
e-GMAT Question of the Week #21

A group of 40 workers working together have to complete a piece of work in 30 days. If all the workers work at a constant rate and after 20 days, it was found that only \(\frac{1}{4}^{th}\) of the work was completed, then how many more workers should be recruited so that the work gets completed on time?

    A. 32
    B. 100
    C. 200
    D. 240
    E. 280



Given:
1. A group of 40 workers working together have to complete a piece of work in 30 days.
2. All the workers work at a constant rate and after 20 days, it was found that only \(\frac{1}{4}^{th}\) of the work was completed

Asked: How many more workers should be recruited so that the work gets completed on time?

40 * 20 man-days could complete = 1/4 work
800 man-days are required to complete 1/4 work
3200 man-days will be required to complete the work.

800 man-days were already consumed.
2400 man-days were required in 10 days.
240 men will be needed for 10 days
200 men will be required to be recruited.

IMO C
GMAT Club Legend
GMAT Club Legend
Joined: 18 Aug 2017
Status:You learn more from failure than from success.
Posts: 8019
Own Kudos [?]: 4097 [0]
Given Kudos: 242
Location: India
Concentration: Sustainability, Marketing
GMAT Focus 1:
545 Q79 V79 DI73
GPA: 4
WE:Marketing (Energy and Utilities)
Send PM
Re: Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
let total work = 120
so work done by 40 workers in 20 days is ; 1/4*120 ; 30
for 30 units work done the rate per worker per day was ; 30* 1/20*1/40 ; 3/80
with the same rate per day per worker we now have to complete 3/4 of pending work ; viz 90 units which is to be done in 10 days
so we have 90=3/80 * 10*x
x=240 workers
we already have 40 workers so extra workers required ; 240-40 ; 200
IMO C




EgmatQuantExpert wrote:
e-GMAT Question of the Week #21

A group of 40 workers working together have to complete a piece of work in 30 days. If all the workers work at a constant rate and after 20 days, it was found that only \(\frac{1}{4}^{th}\) of the work was completed, then how many more workers should be recruited so that the work gets completed on time?

    A. 32
    B. 100
    C. 200
    D. 240
    E. 280

Intern
Intern
Joined: 24 Aug 2017
Posts: 7
Own Kudos [?]: 0 [0]
Given Kudos: 11
Send PM
Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
Days | work | worker
20 | 1/4 | 40
1 | 1/4 | 40*20
1 | 1 | 40*20*4
10 | 1 | 3200÷10
10 | 3/4 | (320*3)/4
=240
Additional worker needed = 240-40
= 200(ans)

Posted from my mobile device
Tutor
Joined: 04 Aug 2010
Posts: 1315
Own Kudos [?]: 3136 [1]
Given Kudos: 9
Schools:Dartmouth College
Send PM
Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
1
Bookmarks
Expert Reply
EgmatQuantExpert wrote:
[A group of 40 workers working together have to complete a piece of work in 30 days. If all the workers work at a constant rate and after 20 days, it was found that only \(\frac{1}{4}^{th}\) of the work was completed, then how many more workers should be recruited so that the work gets completed on time?

    A. 32
    B. 100
    C. 200
    D. 240
    E. 280


Let the daily rate per worker = 1 widget per day, implying that the daily rate for 40 workers = 40 widgets per day.
In 20 days, the number of widgets produced by 40 workers = (daily rate for 40 workers)(number of days) = 40*20 = 800 widgets.

Since these 800 widgets constitute 1/4 of the total job, we get:
\(800 = \frac{1}{4}j\)
\(j = 3200\)

Remaining work = (total job) - (widgets produced in the first 20 days) = 3200 - 800 = 2400.
For 2400 widgets to be produced in the remaining 10 days, the required rate \(= \frac{work}{time} = \frac{2400}{10} = 240\) widgets per day.
Since the daily rate must increase from 40 widgets per day to 240 widgets per day, the number of additional workers that must be recruited = 200.


Originally posted by GMATGuruNY on 20 Sep 2019, 19:02.
Last edited by GMATGuruNY on 21 Sep 2019, 03:06, edited 1 time in total.
VP
VP
Joined: 12 Feb 2015
Posts: 1065
Own Kudos [?]: 2103 [0]
Given Kudos: 77
Send PM
Re: Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
You may do everything correctly in this question and still get the question wrong if you don't read the question carefully. While answering GMAT questions always check whether or not you are answering the right question or not?
Senior Manager
Senior Manager
Joined: 21 Nov 2021
Posts: 437
Own Kudos [?]: 210 [0]
Given Kudos: 345
Send PM
Re: Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
EgmatQuantExpert wrote:
e-GMAT Question of the Week #21

A group of 40 workers working together have to complete a piece of work in 30 days. If all the workers work at a constant rate and after 20 days, it was found that only \(\frac{1}{4}^{th}\) of the work was completed, then how many more workers should be recruited so that the work gets completed on time?

    A. 32
    B. 100
    C. 200
    D. 240
    E. 280



Can use ratios

3x as much work needs to be done than has been done.

That would suggest 3x as many workers if they were able to work for the same 20 days.

Since they have only half as much time left, 10 days, that would suggest 2*3 = 6x as many workers are necessary.

Since the original number is 40 and 6*40 = 240, 200 more workers are required

Posted from my mobile device
Tutor
Joined: 11 May 2022
Posts: 1092
Own Kudos [?]: 697 [0]
Given Kudos: 81
Send PM
Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
Expert Reply
EgmatQuantExpert wrote:
e-GMAT Question of the Week #21

A group of 40 workers working together have to complete a piece of work in 30 days. If all the workers work at a constant rate and after 20 days, it was found that only \(\frac{1}{4}^{th}\) of the work was completed, then how many more workers should be recruited so that the work gets completed on time?

    A. 32
    B. 100
    C. 200
    D. 240
    E. 280



This is a Hidden Plug In: there's no variable listed, but there is some piece of information that we can make up to make our lives easier. Let's make something up to define how much each worker does each day.

Each worker solves one GMAT question per day. In 20 days, 40 workers solve 800 GMAT questions. That's 1/4 of the number of GMAT questions that need to be solved, so the total job is 3200 GMAT questions. 800 are solved already, so we still need to solve 2400. We have 10 days, so we need 240 per day. We already have enough workers to solve 40 per day, so we need to hire 200 additional workers.

Answer choice C.


ThatDudeKnowsHiddenPlugIn

Originally posted by ThatDudeKnows on 03 Jul 2022, 12:03.
Last edited by ThatDudeKnows on 03 Jul 2022, 14:42, edited 1 time in total.
Intern
Intern
Joined: 09 Apr 2017
Posts: 31
Own Kudos [?]: 12 [0]
Given Kudos: 48
Location: India
Schools: HBS '26
Send PM
Re: Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
EgmatQuantExpert wrote:
Question of the Week #21

A group of 40 workers working together have to complete a piece of work in 30 days. If all the workers work at a constant rate and after 20 days, it was found that only \(\frac{1}{4}^{th}\) of the work was completed, then how many more workers should be recruited so that the work gets completed on time?

    A. 32
    B. 100
    C. 200
    D. 240
    E. 280




Here is my approach:

Target : 40 workers * 30 days = x (let's assume, required work to be done = x)
Status : 40 workers * 20 days = x/4 --------(1)
Requirement : (p+40) (let's assume total p workers are required to meet new deadline) workers * 10 days = (x-x/4) = 3x/4

work done by 40 workers in next 10 days = x/8
work to be done by p workers in next 10 days = 3x/4 - x/8 = 5x/8

p workers * 10 days = 5x/8

Multiplying each side by 2/5 -

p workers * 10 days * 2/5 = 5x/8 * 2/5
p workers * 10 day * 2/5 = x/4 = 40 workers * 20 days ------(from 1)

p workers = (40*20*5)/(10*2) = 200

Therefore, answer is 200 workers (C)
avatar
Intern
Intern
Joined: 29 Jan 2021
Posts: 5
Own Kudos [?]: 0 [0]
Given Kudos: 10
Send PM
Re: Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
I solved it this way, please advise if it works...

20 days worked is 2/3 of the 30 days in which the project is due.

1/4 of the work was done in that time

So if 1/4 of work done in 2/3 of time then x is the amount that would be done in all (3/3 or 1) of the time at the rate the 40 people work.

1/4 ÷ 2/3 = ×/1
Cross multiply and you get 2/3x=1/4*1

Solving you have x=1/4*3/2 = 3/8 of the work being done in 30 days at the rate these people work.

To get all the work done at this rate, you need 30 ÷ 3/8, or 30*8/3 people, to get it done on schedule. (30*8)/3 = 80

So if it take 80 people at this rate over a 30 day period, then during the remaining 10 days (or 1/3 of the time) you would need to have 3x as many, which is 240.

However, since you already have 40 people, you'd subtract that from the 240 needed for a total of 200.

Not sure if I just got lucky so please let me know if my logic is correct.

Thank you...

Posted from my mobile device
Intern
Intern
Joined: 24 May 2022
Posts: 19
Own Kudos [?]: 6 [0]
Given Kudos: 38
Location: India
Send PM
Re: Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
EgmatQuantExpert wrote:
e-GMAT Question of the Week #21

A group of 40 workers working together have to complete a piece of work in 30 days. If all the workers work at a constant rate and after 20 days, it was found that only \(\frac{1}{4}^{th}\) of the work was completed, then how many more workers should be recruited so that the work gets completed on time?

    A. 32
    B. 100
    C. 200
    D. 240
    E. 280




So I solved it like this,
40 workers, worked --> 20 days, completed -->\(\frac{1}{4}\)th of the total work
So, 1 worker would take --> 20 x 40 = 800 days to complete \(\frac{1}{4}\)th of the total work
Or,
1 worker would, in a day, complete --> \(\frac{1}{4*800 }\)th of the total work
and, we know that, 1- \(\frac{1}{4}\) = \(\frac{3}{4}\)th work is left for the workers to do in 30-20 = 10 days,
using the basic formula, Work = Rate*Time ,
and taking \(x\) as the total number of workers it would take to complete the work in 10 days,
we can write, \(x(\frac{1}{4*800})10 = \frac{3}{4}\),
which gives us \(x\) = 240
so 240 is the total number of workers required to complete the rest of the work in 10 days,
so, additional workers required = 240 - 40 = 200
So C
User avatar
Non-Human User
Joined: 09 Sep 2013
Posts: 32678
Own Kudos [?]: 822 [0]
Given Kudos: 0
Send PM
Re: Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
GMAT Club Bot
Re: Question of the Week- 21 (A group of 30 men and 10 women working ....) [#permalink]
Moderators:
Math Expert
92914 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne