Last visit was: 23 Apr 2024, 16:45 It is currently 23 Apr 2024, 16:45

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
e-GMAT Representative
Joined: 04 Jan 2015
Posts: 3726
Own Kudos [?]: 16831 [64]
Given Kudos: 165
Send PM
Most Helpful Reply
Senior PS Moderator
Joined: 26 Feb 2016
Posts: 2873
Own Kudos [?]: 5204 [13]
Given Kudos: 47
Location: India
GPA: 3.12
Send PM
General Discussion
Current Student
Joined: 24 Aug 2016
Posts: 733
Own Kudos [?]: 772 [4]
Given Kudos: 97
GMAT 1: 540 Q49 V16
GMAT 2: 680 Q49 V33
Send PM
e-GMAT Representative
Joined: 04 Jan 2015
Posts: 3726
Own Kudos [?]: 16831 [1]
Given Kudos: 165
Send PM
Re: Working at their individual same constant rate, 24 machines can comple [#permalink]
1
Kudos
Expert Reply

Solution



Given:
    • 24 machines can complete a certain production job in 10 hours, all working together
    • All individual machines can work at a same constant rate
    • On a certain day, 8 machines did not work due to minor malfunction, for the first 2 hours

To find:
    • What is the extra time taken, compared to usual days, to complete the job

Approach and Working:
It is given that all machines can work at a same constant rate

Hence, if we assume that each of the machines can complete 1 unit of job every hour, then
    • The total job = 1 * 24 * 10 = 240 units

Now, on that given day, 8 machines did not work for the first 2 hours
    • Therefore, in the first 2 hours only 16 machines were working
    • The job done by the 16 working machines in the first 2 hours = 1 * 16 * 2 units = 32 units

After 2 hours, all the machines were working, hence the time onwards 2 hours will not change the overall time taken

Now, if all machine works, they can complete 24 units work in 1 hour
    • Hence, in 2 hours they would have completed 24 * 2 = 48 units of work

At this rate, to compensate the 32 units of work, the time taken = \(\frac{32}{48}\) hrs = \(\frac{2}{3}\) hrs = 40 minutes

Hence, the correct answer is option C.

Answer: C
Senior Manager
Senior Manager
Joined: 14 Dec 2017
Posts: 426
Own Kudos [?]: 459 [0]
Given Kudos: 173
Location: India
Send PM
Re: Working at their individual same constant rate, 24 machines can comple [#permalink]
EgmatQuantExpert wrote:
3 Deadly Mistakes You Must Avoid in Time and Work Questions – Practice question 1

Working at their individual same constant rate, 24 machines can complete a certain production job in 10 hours when they all work together. On a certain day, due to minor malfunction, 8 of those machines were not operating for the first 2 hours. Compared to normal days, what is the extra time taken to complete the production job on that day?

    A. 20 minutes
    B. 30 minutes
    C. 40 minutes
    D. 1 hour
    E. 1 hour 20 minutes


To solve question 2: Question 2

To read the article: 3 Deadly Mistakes You Must Avoid in Time and Work Questions



Given that 24 machines working together at same constant rate, complete a job in 10 hours.

Hence the job requires a total of 24 * 10 = 240 M/c hrs

Now on a particular day, 8 machines are down for the first 2 hours, hence only 16 machines are operating & they provide 16 * 2 = 32 M/c hrs of work.

Hence the job still requires, 240 - 32 = 208 M/c hrs of work to be done.

Now all 24 machines are working together, to complete the remaining 208 M/c hrs of work.

Hence time taken by the 24 machines to finish the remaining 208 M/c hrs of job = 208/24 = 8.66 hrs.

Hence Total time taken to finish the job (including the 2 hr breakdown of 8 machines) = 2 + 8.66 = 10.66 hrs

Extra time taken = 10.66 - 10 = 0.66 hours = 0.66 * 60 =~ 40 mins

Answer C.

Thanks,
GyM
VP
VP
Joined: 07 Dec 2014
Posts: 1072
Own Kudos [?]: 1560 [1]
Given Kudos: 27
Send PM
Re: Working at their individual same constant rate, 24 machines can comple [#permalink]
1
Kudos
EgmatQuantExpert wrote:
3 Deadly Mistakes You Must Avoid in Time and Work Questions – Practice question 1

Working at their individual same constant rate, 24 machines can complete a certain production job in 10 hours when they all work together. On a certain day, due to minor malfunction, 8 of those machines were not operating for the first 2 hours. Compared to normal days, what is the extra time taken to complete the production job on that day?

    A. 20 minutes
    B. 30 minutes
    C. 40 minutes
    D. 1 hour
    E. 1 hour 20 minutes


rate of 1 machine per 1 hour=1/240
in 2 hours 24 machines complete 48/240=3/15 of job
in 2 hours 16 machines complete 32/240=2/15 of job
24 machines can complete missing 1/15 of job in (1/15)/(24/240)=2/3 extra hour
2/3 hour=40 minutes
C
GMAT Club Legend
GMAT Club Legend
Joined: 19 Dec 2014
Status:GMAT Assassin/Co-Founder
Affiliations: EMPOWERgmat
Posts: 21846
Own Kudos [?]: 11664 [0]
Given Kudos: 450
Location: United States (CA)
GMAT 1: 800 Q51 V49
GRE 1: Q170 V170
Send PM
Re: Working at their individual same constant rate, 24 machines can comple [#permalink]
Expert Reply
Hi All,

We're told that while working at their individual same constant rate, 24 machines can complete a certain production job in 10 hours when they all work together. However, on a certain day, due to minor malfunction, 8 of those machines were not operating for the first 2 hours. We're asked - relative to 'normal' days - what is the EXTRA time taken to complete the production job on that day.

This is an example of a "Work" questions - and it often helps to first determine the total amount of work needed to complete the job. With 24 machines that each work 10 hours at the same rate, the total amount of work needed to complete a job is (24)(10) = 240 machine-hours of work.

Thus, if we had just 1 machine, then it would need to work 240 hours. If we had 2 machines, they would each need to work 120 hours, etc.

We're told that 8 of the machines do NOT work for the first 2 hours, meaning that the remaining 24 - 8 = 16 machines DO work for those first 2 hours....

(16)(2) = 32 machine-hours of work completed. This leaves 240 - 32 = 208 hours of machine work left to complete.

When all 24 machines are working, 24 machine-hours of work are completed each hour....
208/24 = 8 16/24 hours = 8 2/3 hours of time are then needed to complete the job.
Total time = 2 hours + 8 2/3 hours = 10 2/3 hours....
so the extra 2/3 hours = (2/3)(60 minutes) = 40 minutes extra

Final Answer:

GMAT assassins aren't born, they're made,
Rich
Manager
Manager
Joined: 31 Oct 2018
Posts: 65
Own Kudos [?]: 224 [1]
Given Kudos: 173
Location: India
Send PM
Re: Working at their individual same constant rate, 24 machines can comple [#permalink]
1
Kudos
24 Machines do 10% wrk in 1hr
16 machines do (10/24)*16 % wrk in 1 hr
16 machines do (10/24)*16*2 % wrk in first 2 hrs = 13.33%

remaining 100-13.33 = 86.66%
Now all machines work together hence we have to divide 86.66 by 10 i.e (86.66 % work / 10% rate of work) = (time) 8.66 hr

total time = 8.66 + 2 = 10.66 hr

extra = 0.66*60 = 40 min






EgmatQuantExpert wrote:
3 Deadly Mistakes You Must Avoid in Time and Work Questions – Practice question 1





Working at their individual same constant rate, 24 machines can complete a certain production job in 10 hours when they all work together. On a certain day, due to minor malfunction, 8 of those machines were not operating for the first 2 hours. Compared to normal days, what is the extra time taken to complete the production job on that day?

    A. 20 minutes
    B. 30 minutes
    C. 40 minutes
    D. 1 hour
    E. 1 hour 20 minutes


To solve question 2: Question 2

To read the article: 3 Deadly Mistakes You Must Avoid in Time and Work Questions
Intern
Intern
Joined: 13 Nov 2022
Posts: 32
Own Kudos [?]: 27 [0]
Given Kudos: 8
Send PM
Re: Working at their individual same constant rate, 24 machines can comple [#permalink]
Better solution-

24 machines 10 hrs works - total work: 240 units

As per question

16 machine 10 hrs work + 8 Machine 8 hrs work + 24 machine y hrs work = 240

160 + 64 + 24Y = 240x

24y = 240 - 224
y =16/24
Y= 2/3 hrs

Y= 2/3* 60

Y= 40 mins
Senior Manager
Senior Manager
Joined: 29 Oct 2015
Posts: 468
Own Kudos [?]: 255 [0]
Given Kudos: 293
Send PM
Re: Working at their individual same constant rate, 24 machines can comple [#permalink]
egmat , Can you please explain  how you derived 32/48 ? The compensation part is not clear to me . 
EgmatQuantExpert wrote:

Solution



Given:
    • 24 machines can complete a certain production job in 10 hours, all working together
    • All individual machines can work at a same constant rate
    • On a certain day, 8 machines did not work due to minor malfunction, for the first 2 hours

To find:
    • What is the extra time taken, compared to usual days, to complete the job

Approach and Working:
It is given that all machines can work at a same constant rate

Hence, if we assume that each of the machines can complete 1 unit of job every hour, then
    • The total job = 1 * 24 * 10 = 240 units

Now, on that given day, 8 machines did not work for the first 2 hours
    • Therefore, in the first 2 hours only 16 machines were working
    • The job done by the 16 working machines in the first 2 hours = 1 * 16 * 2 units = 32 units

After 2 hours, all the machines were working, hence the time onwards 2 hours will not change the overall time taken

Now, if all machine works, they can complete 24 units work in 1 hour
    • Hence, in 2 hours they would have completed 24 * 2 = 48 units of work

At this rate, to compensate the 32 units of work, the time taken = \(\frac{32}{48}\) hrs = \(\frac{2}{3}\) hrs = 40 minutes

Hence, the correct answer is option C.

Answer: C

­
Senior Manager
Senior Manager
Joined: 29 Oct 2015
Posts: 468
Own Kudos [?]: 255 [0]
Given Kudos: 293
Send PM
Re: Working at their individual same constant rate, 24 machines can comple [#permalink]
egmat , cant I think like this ? 

48 units of work is done  in  2 hours
1 unit of work is done  in 2/48 hours

The remaining (48-32) = 16 units of work (extra) is done in 2/48  * 16 = 2/3 hours extra = 40 mins gmatophobia
sayan640 wrote:
egmat , Can you please explain  how you derived 32/48 ? The compensation part is not clear to me . 
EgmatQuantExpert wrote:

Solution



Given:
    • 24 machines can complete a certain production job in 10 hours, all working together
    • All individual machines can work at a same constant rate
    • On a certain day, 8 machines did not work due to minor malfunction, for the first 2 hours

To find:
    • What is the extra time taken, compared to usual days, to complete the job

Approach and Working:
It is given that all machines can work at a same constant rate

Hence, if we assume that each of the machines can complete 1 unit of job every hour, then
    • The total job = 1 * 24 * 10 = 240 units

Now, on that given day, 8 machines did not work for the first 2 hours
    • Therefore, in the first 2 hours only 16 machines were working
    • The job done by the 16 working machines in the first 2 hours = 1 * 16 * 2 units = 32 units

After 2 hours, all the machines were working, hence the time onwards 2 hours will not change the overall time taken

Now, if all machine works, they can complete 24 units work in 1 hour
    • Hence, in 2 hours they would have completed 24 * 2 = 48 units of work

At this rate, to compensate the 32 units of work, the time taken = \(\frac{32}{48}\) hrs = \(\frac{2}{3}\) hrs = 40 minutes

Hence, the correct answer is option C.

Answer: C

­

­
GMAT Club Bot
Re: Working at their individual same constant rate, 24 machines can comple [#permalink]
Moderators:
Math Expert
92883 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne