Last visit was: 19 Nov 2025, 01:16 It is currently 19 Nov 2025, 01:16
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
guddo
Joined: 25 May 2021
Last visit: 30 Oct 2025
Posts: 360
Own Kudos:
8,662
 [41]
Given Kudos: 19
Posts: 360
Kudos: 8,662
 [41]
6
Kudos
Add Kudos
35
Bookmarks
Bookmark this Post
User avatar
Apeksha2101
Joined: 31 May 2018
Last visit: 06 Jun 2025
Posts: 43
Own Kudos:
9
 [3]
Given Kudos: 28
Posts: 43
Kudos: 9
 [3]
3
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Anooj1705
Joined: 10 Jan 2022
Last visit: 18 Nov 2025
Posts: 2
Own Kudos:
4
 [4]
Given Kudos: 26
Posts: 2
Kudos: 4
 [4]
4
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
kop18
Joined: 30 Sep 2020
Last visit: 09 Jan 2025
Posts: 90
Own Kudos:
21
 [1]
Given Kudos: 98
GMAT 1: 610 Q40 V35
GMAT 1: 610 Q40 V35
Posts: 90
Kudos: 21
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Please can someone explain the 3rd question?

KarishmaB Sajjad1994 GMATNinja
User avatar
ShilpiAgnihotrii
Joined: 27 Dec 2022
Last visit: 19 Nov 2025
Posts: 84
Own Kudos:
68
 [3]
Given Kudos: 359
Location: India
Schools: ESSEC Kellogg IIM
Schools: ESSEC Kellogg IIM
Posts: 84
Kudos: 68
 [3]
3
Kudos
Add Kudos
Bookmarks
Bookmark this Post
kop18
Please can someone explain the 3rd question?

KarishmaB Sajjad1994 GMATNinja
­Its simple when you read what Anooj1705 above has mentioned, you just have to see the last column of the table, which shows the CURRENT data(currently means data of the present day). So the last day has A, B, C, D and F which represent Initial and Intermediate cluster. The Final cluster letters G and H are missing. 

So the Answer is Yes Yes and No.
User avatar
KarishmaB
Joined: 16 Oct 2010
Last visit: 18 Nov 2025
Posts: 16,267
Own Kudos:
76,986
 [4]
Given Kudos: 482
Location: Pune, India
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 16,267
Kudos: 76,986
 [4]
4
Kudos
Add Kudos
Bookmarks
Bookmark this Post
 
kop18
Please can someone explain the 3rd question?

KarishmaB Sajjad1994 GMATNinja
­Initial Cluster - Stages A and B
Intermediate cluster - Stages C, D E, F
Final Cluster - Stages G, H

Today is the 5th day of week 7. So we only have to look at week 7. Look at the report generated.

Last 4 projects are all in A or B so they are in Initial Cluster. 
Initial Cluster - Select YES

Rest all 6 projects today are in C or D or F. They all belong to Intermediate cluster.
Intermediate cluster - Select YES

No other project is active today. 
Final Cluster - Select NO
User avatar
Varshakash
Joined: 28 Jun 2024
Last visit: 06 Apr 2025
Posts: 15
Own Kudos:
Given Kudos: 64
Location: India
Posts: 15
Kudos: 4
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Can someone lease help in explaining 3rd question in terms of respective tabs?
User avatar
sayan640
Joined: 29 Oct 2015
Last visit: 10 Nov 2025
Posts: 1,179
Own Kudos:
Given Kudos: 783
GMAT 1: 570 Q42 V28
Products:
GMAT 1: 570 Q42 V28
Posts: 1,179
Kudos: 813
Kudos
Add Kudos
Bookmarks
Bookmark this Post
KarishmaB The project 74154 can also be considered an active one. Why can't its current status be 'H' ? 
KarishmaB

kop18
Please can someone explain the 3rd question?

KarishmaB Sajjad1994 GMATNinja
­Initial Cluster - Stages A and B
Intermediate cluster - Stages C, D E, F
Final Cluster - Stages G, H

Today is the 5th day of week 7. So we only have to look at week 7. Look at the report generated.

Last 4 projects are all in A or B so they are in Initial Cluster. 
Initial Cluster - Select YES

Rest all 6 projects today are in C or D or F. They all belong to Intermediate cluster.
Intermediate cluster - Select YES

No other project is active today. 
Final Cluster - Select NO
­
User avatar
KarishmaB
Joined: 16 Oct 2010
Last visit: 18 Nov 2025
Posts: 16,267
Own Kudos:
Given Kudos: 482
Location: Pune, India
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 16,267
Kudos: 76,986
Kudos
Add Kudos
Bookmarks
Bookmark this Post
sayan640
KarishmaB The project 74154 can also be considered an active one. Why can't its current status be 'H' ? 
KarishmaB

kop18
Please can someone explain the 3rd question?

KarishmaB Sajjad1994 GMATNinja
­Initial Cluster - Stages A and B
Intermediate cluster - Stages C, D E, F
Final Cluster - Stages G, H

Today is the 5th day of week 7. So we only have to look at week 7. Look at the report generated.

Last 4 projects are all in A or B so they are in Initial Cluster. 
Initial Cluster - Select YES

Rest all 6 projects today are in C or D or F. They all belong to Intermediate cluster.
Intermediate cluster - Select YES

No other project is active today. 
Final Cluster - Select NO
­
­
If that were the case then previous days including today would have an H against it. But there isn't. This shows that the project is already complete. 
User avatar
Elite097
Joined: 20 Apr 2022
Last visit: 08 Oct 2025
Posts: 771
Own Kudos:
Given Kudos: 346
Location: India
GPA: 3.64
Posts: 771
Kudos: 553
Kudos
Add Kudos
Bookmarks
Bookmark this Post
KarishmaB MartyMurray egmat pls explain Q2 and Q1 too­.

Pls tell the significance of % asssigned to clusters to indicate a % of project lifetime spent in one cluster. For ex a delay would occur even if the stage was supposed to be there for 2 days but got completed in >2 days but how do we find these cases. We coincidentally got this answer correct by seeing which stage exceeeded 3 days instead but the delay need not be due to exceeding 3 days
User avatar
MishalSen1
Joined: 01 Mar 2022
Last visit: 27 Aug 2024
Posts: 12
Own Kudos:
Given Kudos: 21
Location: India
Posts: 12
Kudos: 2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
why is answer to 74154 "delayed" in the second question?
User avatar
nawal_slg
Joined: 04 Aug 2023
Last visit: 18 Nov 2025
Posts: 6
Given Kudos: 103
Location: India
Products:
Posts: 6
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
In quest 2 how can 74584 be delayed?
User avatar
ShilpiAgnihotrii
Joined: 27 Dec 2022
Last visit: 19 Nov 2025
Posts: 84
Own Kudos:
68
 [2]
Given Kudos: 359
Location: India
Schools: ESSEC Kellogg IIM
Schools: ESSEC Kellogg IIM
Posts: 84
Kudos: 68
 [2]
1
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
nawal_slg
In quest 2 how can 74584 be delayed?
­Read the 1st passage "none requires more than 3 days of work. A project is said to be delayed if it spends more time at a stage than is required to complete the work."
User avatar
BongBideshini
Joined: 25 May 2021
Last visit: 16 Nov 2025
Posts: 46
Own Kudos:
39
 [3]
Given Kudos: 58
Location: India
Concentration: Entrepreneurship, Leadership
GPA: 3.8
WE:Engineering (Aerospace and Defense)
Posts: 46
Kudos: 39
 [3]
3
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Official Answer: Q1

The report on the Status History Reports tab lists seven projects that had reached Stage H before they were successfully completed. None of these projects spent more than one day in Stage H. This information supports the statement that Stage H typically lasts 1 day.
The diagram on the Stages and Clusters tab provides evidence against both the statement that the first stage of each project is handled by an individual from the administration department and the statement that final stage of each project is handled by an individual from the development department. It shows that Stage A, the first stage, is the responsibility of one or more individuals in the development department, and that Stage H, the final stage, is the responsibility of one or more individuals in the administration department.
The report on the Status History Reports tab provides evidence against the statement that Stage F typically lasts 4–6 days. Each of the projects shown to have reached Stage F was in the stage for either 1 or 2 days. Furthermore, the Projects tab states that no stage requires more than 3 days of work.
The report on the Status History Reports tab provides evidence against the statement that Stage X typically comes immediately after Stage C. For each of the three projects that had reached Stage X, Stage X appears immediately following Stage E.
The correct answer is, Stage H typically lasts 1 day.

Official Answer: Q2

The passage on the Projects tab states that no stage requires more than 3 days of work and that a project is said to be delayed if it spends more time at a stage than is required to complete the work. The information provided in the stimuli does not indicate the required amount of time to complete any specific stage, but it can be inferred that any project that spent more than 3 days in any one stage must have experienced a delay at that stage. The report on the Status History Reports tab indicates that Project 74154 spent 4 days at each of Stages C and D. Therefore, Project 74154 must have experienced a delay at one or more stages.
The correct answer is Delayed.
B.
As discussed above, a project that spent more than 3 days at any one stage must have experienced a delay at that stage. The report on the Status History Report tab indicates that Project 74854 spent 5 days at Stage A and 6 days at Stage C. Therefore, Project 74854 must have experienced a delay at one or more stages.
The correct answer is Delayed.
C.
As discussed above, the information provided in the tabs does not indicate the required amount of time to complete any specific stage other than that no stage requires more than 3 days of work. Given this and the fact that the report on the Status History Reports tab indicates that the first stage (Stage A) of Project 75745 began on the day on the report was generated, it cannot be inferred whether Project 75745 spent more time at that stage than was required to complete the work.
The correct answer is Not necessarily delayed.


Official Answer: Q3

A.
The diagram on the Stages and Clusters tab shows that Stage A and Stage B together constitute the Initial cluster of stages. According to the report on the Status History Reports tab, which its title indicates was generated today, exactly four projects (75351, 75353, 75489, and 75745) are currently in either Stage A or Stage B. Therefore, at least two active projects are currently in a stage within the initial cluster.
The correct answer is Yes.
B.
The diagram on the Stages and Clusters tab shows that Stage C, Stage D, Stage E, and Stage F together constitute the Intermediate cluster of stages. According to the report on the Status History Reports tab, which its title indicates was generated today, exactly six projects (74545, 74803, 74854, 74870, 75038, and 75039) are currently in Stage C, Stage D, or Stage F. Therefore, at least two active projects are currently in a stage within the intermediate cluster.
The correct answer is Yes.
C.
The diagram on the Stages and Clusters tab shows that Stage G and Stage H together constitute the Final cluster of stages. According to the report on the Status History Reports tab, which its title indicates was generated today, no projects are currently at either Stage G or Stage H. Therefore, there are not at least two active projects currently in a stage within the final cluster.
The correct answer is No.
User avatar
samarpan.g28
Joined: 08 Dec 2023
Last visit: 19 Nov 2025
Posts: 324
Own Kudos:
Given Kudos: 1,236
Location: India
Concentration: General Management, Human Resources
GPA: 8.88
WE:Engineering (Technology)
Kudos
Add Kudos
Bookmarks
Bookmark this Post
In this project, A took 5 days and C took 6 days.
In tab 1, it was mentioned that " Some stages require as little as 1 day of work, and none requires more than 3 days of work. A project is said to be delayed if it spends more time at a stage than is required to complete the work." Thus, it is delayed.
nawal_slg
In quest 2 how can 74584 be delayed?