Last visit was: 26 Apr 2024, 20:35 It is currently 26 Apr 2024, 20:35

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Kudos
Tags:
Show Tags
Hide Tags
User avatar
Current Student
Joined: 11 May 2008
Posts: 377
Own Kudos [?]: 1029 [43]
Given Kudos: 0
Concentration: General
 Q50  V34
Send PM
Most Helpful Reply
Tutor
Joined: 16 Oct 2010
Posts: 14831
Own Kudos [?]: 64941 [24]
Given Kudos: 427
Location: Pune, India
Send PM
User avatar
Director
Director
Joined: 03 Aug 2012
Posts: 587
Own Kudos [?]: 3156 [9]
Given Kudos: 322
Concentration: General Management, General Management
GMAT 1: 630 Q47 V29
GMAT 2: 680 Q50 V32
GPA: 3.7
WE:Information Technology (Investment Banking)
Send PM
General Discussion
User avatar
Intern
Intern
Joined: 29 Jun 2008
Posts: 25
Own Kudos [?]: 51 [6]
Given Kudos: 0
Send PM
Re: John can complete a given task in 20 days. Jane will take [#permalink]
1
Kudos
5
Bookmarks
R * T = 1

John's rate = 1/20
Jane's rate = 1/12

(1/20)T + (1/12)(T-4) = 1
T/20 + (T-4)/12 = 1
(12T + 20T - 80)/240 = 1
32T = 320
T=10
User avatar
Manager
Manager
Joined: 27 May 2008
Posts: 231
Own Kudos [?]: 622 [5]
Given Kudos: 0
Send PM
Re: John can complete a given task in 20 days. Jane will take [#permalink]
3
Kudos
2
Bookmarks
john's rate = 1/20
jane's rate = 1/12
combined rate = 1/20+1/12 = 2/15

let the work finished in x days
both woked for (x-4) days amd John alone worked for 4 days

(x-4)*2/15 + 4*1/20 = 1
2x - 8 + 3 = 15
x= 10 answer .............
User avatar
Manager
Manager
Joined: 16 Aug 2004
Posts: 191
Own Kudos [?]: 143 [4]
Given Kudos: 0
Location: India
Send PM
Re: John can complete a given task in 20 days. Jane will take [#permalink]
4
Kudos
10 days. Here is the explanation
for 4 days Jane didn't work, hence john would complete (4/20=1/5 of the work). Therefore Jane and John together will complete 4/5 of the work.
Now John and Jane together would complete the work in (1/20+1/12=15/2 days).
Therefore they would take 6 days to complete 4/5 of the work, after which John worked for another 4 days. Hence in total they took 6+4=10 days to complete.
User avatar
Intern
Intern
Joined: 16 Jul 2008
Posts: 3
Own Kudos [?]: 2 [2]
Given Kudos: 0
Send PM
Re: John can complete a given task in 20 days. Jane will take [#permalink]
1
Kudos
1
Bookmarks
I have a different point of view, solution can be too long, however, it is easy to think and solve with this method.

We know that John completes the task in 20 days, Jane completes the task in 12 days.
We can assume that total of this work is 60 units (which is the least common multiply)

From here; John finishes 3 units of the task in a day (60/20=3)
Jane finishes 5 units of the task in a day (60/12=5)

First 4 days, john complete 4*3=12 units of the task. Remaining part is 48 units (60-12=48)
Both of them complete 3+5=8 units of the task in a day. Accrodingly, they can complete 48 units of tasks in 6 days.

Then, the answer is 4+6=10...
Manager
Manager
Joined: 22 Nov 2016
Posts: 205
Own Kudos [?]: 267 [2]
Given Kudos: 50
Concentration: Leadership, Strategy
Send PM
Re: John can complete a given task in 20 days. Jane will take [#permalink]
2
Kudos
The combined rate of John and Jane is \(\frac{1}{20} + \frac{1}{12} = \frac{2}{15}\)

Let the number of days required to complete the work be = x

For x-4 days, both Jane and John work together. Hence the work done = \(\frac{2}{15}*(x-4)\)

After x-4 days, Jane is gone and John works alone at his constant rate of 1/20 for 4 days. Hence the work done = = \(\frac{1}{20}*4\) =\(\frac{1}{5}\)

Total work done must = 1.

\(\frac{2}{15}*(x-4)\) + \(\frac{1}{5}\) = 1

On solving, x = 10 days.
avatar
Intern
Intern
Joined: 11 Dec 2013
Posts: 7
Own Kudos [?]: 4 [1]
Given Kudos: 3
Send PM
Re: John can complete a given task in 20 days. Jane will take [#permalink]
1
Kudos
My approach is slightly different:
John+Jane can complete the work in 7.5 days (20*12)/(20+12).
Jane left 4 days before the work got completed...that means they together worked for 3.5 days.
Now with rate of 1/20 and 1/12 per day..combined...they can do...2/15 work in 1 day. That means in 3.5 days, then can do -->7/15 of work.
So left over work is 8/15 and needs to be be done by John alone.
which would take him...(1/20)/(8/15)--->32/3 days...
This is taking me nowhere..Can anyone suggest what is wrong in this logic??
Senior Manager
Senior Manager
Joined: 28 Jun 2015
Posts: 250
Own Kudos [?]: 294 [1]
Given Kudos: 47
Concentration: Finance
GPA: 3.5
Send PM
Re: John can complete a given task in 20 days. Jane will take [#permalink]
1
Bookmarks
John's 1 day's work = 1/20.
Jane's 1 day's work = 1/12.

If John had worked for x days, Jane had worked for (x-4) days.

So, x/20 + (x-4)/12 = 1
12x + 20x - 80 = 240
32x = 320
x = 10 days. Ans (B).
Board of Directors
Joined: 11 Jun 2011
Status:QA & VA Forum Moderator
Posts: 6072
Own Kudos [?]: 4690 [1]
Given Kudos: 463
Location: India
GPA: 3.5
WE:Business Development (Commercial Banking)
Send PM
Re: John can complete a given task in 20 days. Jane will take [#permalink]
1
Kudos
arjtryarjtry wrote:
John can complete a given task in 20 days. Jane will take only 12 days to complete the same task. John and Jane set out to complete the task by beginning to work together. However, Jane was indisposed 4 days before the work got over. In how many days did the work get over from the time John and Jane started to work on it together?

A. 6
B. 10
C. 8
D. 7.5
E. 3.5


Let the total task be 60 units

John can complete 3 units of work per day
Jane can complete 5 units of work per day

Togather Jane and John can complete 8 units of work per day

Let John and Jane togather worked for " d " days , so work completed by them is 8d units

Then John completes the remaining work in 4 more days , so work done by John in 4 days is ( 4*3) 12 units

Now , we have Total Work = Work completed by John and Jane ( in "d " days ) and work done by John in 4 days

60 = 8d + 12
48 = 8d

or, d =6

So, John and John worked for 6 days and then John worked for 4 days , so they took 10 days to complete the work.
avatar
Intern
Intern
Joined: 30 May 2012
Posts: 2
Own Kudos [?]: [0]
Given Kudos: 9
Send PM
Re: John can complete a given task in 20 days. Jane will take [#permalink]
john takes 20d to complete the work so number of units each day =3
jane takes 12d to complete the work so number of units each day =5
since jane didnt work for last 4 days it means number of units done in last 4 days are =3*4=12
so john and jane work together for (60-12)/3+5 = 6days
thus total days = 6+4 =10days
Intern
Intern
Joined: 17 Jun 2015
Posts: 1
Own Kudos [?]: [0]
Given Kudos: 15
Location: Argentina
Schools: Judge'17 (M)
GMAT 1: 690 Q47 V38
GPA: 3.83
Re: John can complete a given task in 20 days. Jane will take [#permalink]
narmit wrote:
My approach is slightly different:
John+Jane can complete the work in 7.5 days (20*12)/(20+12).
Jane left 4 days before the work got completed...that means they together worked for 3.5 days.
Now with rate of 1/20 and 1/12 per day..combined...they can do...2/15 work in 1 day. That means in 3.5 days, then can do -->7/15 of work.
So left over work is 8/15 and needs to be be done by John alone.
which would take him...(1/20)/(8/15)--->32/3 days...
This is taking me nowhere..Can anyone suggest what is wrong in this logic??



i did exactly the same and got stucked too... (just note the following in your last calc. -> (1/20)/(8/15) = 36/3 = 12 days
not sure what is wrong, i learned this approach from manhattan and usually works fine
User avatar
Manager
Manager
Joined: 23 Sep 2015
Posts: 68
Own Kudos [?]: 50 [0]
Given Kudos: 213
Concentration: General Management, Finance
GMAT 1: 680 Q46 V38
GMAT 2: 690 Q47 V38
GPA: 3.5
Send PM
Re: John can complete a given task in 20 days. Jane will take [#permalink]
elch4ngo wrote:
narmit wrote:
My approach is slightly different:
John+Jane can complete the work in 7.5 days (20*12)/(20+12).
Jane left 4 days before the work got completed...that means they together worked for 3.5 days.
Now with rate of 1/20 and 1/12 per day..combined...they can do...2/15 work in 1 day. That means in 3.5 days, then can do -->7/15 of work.
So left over work is 8/15 and needs to be be done by John alone.
which would take him...(1/20)/(8/15)--->32/3 days...
This is taking me nowhere..Can anyone suggest what is wrong in this logic??



i did exactly the same and got stucked too... (just note the following in your last calc. -> (1/20)/(8/15) = 36/3 = 12 days
not sure what is wrong, i learned this approach from manhattan and usually works fine



Having the same issue as both of these people with this method.

I think this method, because it seems straight forward in my brain, but this is the second time ive been hung up on a question. And got the answer by choosing the closest answer. But something is off logic wise.

Can Bunuel or Engr2012 help if possible :) ?
User avatar
Manager
Manager
Joined: 23 Sep 2015
Posts: 68
Own Kudos [?]: 50 [0]
Given Kudos: 213
Concentration: General Management, Finance
GMAT 1: 680 Q46 V38
GMAT 2: 690 Q47 V38
GPA: 3.5
Send PM
Re: John can complete a given task in 20 days. Jane will take [#permalink]
VeritasPrepKarishma wrote:
There is a problem in this logic.

"Jane was indisposed 4 days before the work got over." - implies that Jane left 4 days before the work actually got over. So perhaps only 1 day work was left but Jane left and John alone completed the work in 4 days. After Jane left, the work continued for 4 days.
In your logic, John and Jane would have taken total 7.5 days and Jane left after 3.5 days. But then, the leftover work would have been completed in more than 4 days because John was working alone.

In such questions, you need to start from the end. Last 4 days John works alone and completes 4 * (1/20) = 1/5 of the work.
So 4/5 of the work should have been completed by the two of them together before Jane left.
Their combined rate of work is 1/20 + 1/12 = 8/60
Time taken to complete 4/5 of the work = (4/5)/(8/60) = 6 days.

So total number of days taken to complete the work = 6 + 4 = 10 days.



Makes more sense now, thanks for the reply!
Current Student
Joined: 10 Mar 2013
Posts: 360
Own Kudos [?]: 2698 [0]
Given Kudos: 200
Location: Germany
Concentration: Finance, Entrepreneurship
GMAT 1: 580 Q46 V24
GPA: 3.7
WE:Marketing (Telecommunications)
Send PM
Re: John can complete a given task in 20 days. Jane will take [#permalink]
Hi guys, I used the same logic but using smart numbers (let's say entire work=120)
John 6*20=120
Jane 10*12=120
In 4 days working alone John did: 4 Days * Rate = 4*6=24, so working together they did 120-24=96 --> Rate(A+B)*t=96 -> 16*t=96, t=6. hence the answer is B (John worked 4 days + 6 days they worked together = 10 days)
avatar
Intern
Intern
Joined: 28 Dec 2015
Posts: 27
Own Kudos [?]: 13 [0]
Given Kudos: 62
Send PM
Re: John can complete a given task in 20 days. Jane will take [#permalink]
R(john)=1/20
R(Jane)=1/12

Since,jane left the work 4 days before,it means the remaining 4 days john had to work alone.
So using work time equation: Work=Rate *time=R(john)*4=1/20*4=1/5 th of work was done by john in the last 4 days.
So,4/5th work has to be done when jane and john were working together.
4/5=(1/20+1/12)*T
T=10 days. :-D
Manager
Manager
Joined: 24 Mar 2015
Status:love the club...
Posts: 220
Own Kudos [?]: 112 [0]
Given Kudos: 527
Send PM
Re: John can complete a given task in 20 days. Jane will take [#permalink]
arjtryarjtry wrote:
John can complete a given task in 20 days. Jane will take only 12 days to complete the same task. John and Jane set out to complete the task by beginning to work together. However, Jane was indisposed 4 days before the work got over. In how many days did the work get over from the time John and Jane started to work on it together?

A. 6
B. 10
C. 8
D. 7.5
E. 3.5


hi

since Jane was indisposed 4 days before the work got over, john had to work alone on those bad days
in 4 days john accomplished (1/20) * 4 = 1/5 of the task
so it is very natural to assume that 4/5 part of the task was done by john and jane working together


so, their combined rate of work is (1/20 + 1/12) = 2/15 per day
now, as rate and time have a reciprocal relationship, they need 15/2 days to do the whole job

so, 4/5 of the work was done by john + jane in (15/2) * (4/5) = 6 days

total time required is (6 + 4) = 10 days

cheers through the kudos button if it's clear to you
thanks
:cool:
Intern
Intern
Joined: 22 Jan 2018
Posts: 1
Own Kudos [?]: 0 [0]
Given Kudos: 0
Send PM
John can complete a given task in 20 days. Jane will take [#permalink]
hello folks
i totaly agree that the total number spend on this work is 10 days. but i have a question regarding the way the question is ask. it is asking 'In how many days did the work get over from the time John and Jane started to work on it together?'. i feel like from the time they start work together it is 6 not 10 cuz john start alone. please can you explain me why it is 10. please somebody to respond to me
VP
VP
Joined: 07 Dec 2014
Posts: 1072
Own Kudos [?]: 1562 [0]
Given Kudos: 27
Send PM
John can complete a given task in 20 days. Jane will take [#permalink]
arjtryarjtry wrote:
John can complete a given task in 20 days. Jane will take only 12 days to complete the same task. John and Jane set out to complete the task by beginning to work together. However, Jane was indisposed 4 days before the work got over. In how many days did the work get over from the time John and Jane started to work on it together?

A. 6
B. 10
C. 8
D. 7.5
E. 3.5


let d=total days
2d/15-4/12=1
d=10 days
B
GMAT Club Bot
John can complete a given task in 20 days. Jane will take [#permalink]
 1   2   
Moderators:
Math Expert
92948 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne