Last visit was: 08 May 2024, 19:10 It is currently 08 May 2024, 19:10

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
User avatar
Intern
Intern
Joined: 24 May 2014
Posts: 13
Own Kudos [?]: 659 [100]
Given Kudos: 6
Location: Brazil
Send PM
Most Helpful Reply
Math Expert
Joined: 02 Sep 2009
Posts: 93096
Own Kudos [?]: 622264 [28]
Given Kudos: 81800
Send PM
General Discussion
Director
Director
Joined: 22 Mar 2013
Status:Everyone is a leader. Just stop listening to others.
Posts: 611
Own Kudos [?]: 4602 [4]
Given Kudos: 235
Location: India
GPA: 3.51
WE:Information Technology (Computer Software)
Send PM
avatar
Intern
Intern
Joined: 15 Sep 2013
Posts: 1
Own Kudos [?]: [0]
Given Kudos: 4
Send PM
Re: Machine M and Machine N working alone at their constant rate [#permalink]
Hi Bunuel,

Why are we rounding off the number of hours here?
Am i missing something in the question, why arent we considering minutes, for which im getting the first statement as being sufficient.
Thanks
Math Expert
Joined: 02 Sep 2009
Posts: 93096
Own Kudos [?]: 622264 [0]
Given Kudos: 81800
Send PM
Re: Machine M and Machine N working alone at their constant rate [#permalink]
Expert Reply
shishir16 wrote:
Hi Bunuel,

Why are we rounding off the number of hours here?
Am i missing something in the question, why arent we considering minutes, for which im getting the first statement as being sufficient.
Thanks


Cannot follow what you mean...

Where do we round the number of hours? Also, in my solution for (1) there are an example given which gives two different answers to the question, which means that this statement is not sufficient.
User avatar
Manager
Manager
Joined: 06 Mar 2014
Posts: 166
Own Kudos [?]: 477 [0]
Given Kudos: 84
Location: India
GMAT Date: 04-30-2015
Send PM
Re: Machine M and Machine N working alone at their constant rate [#permalink]
Bunuel wrote:
Machine M and Machine N working alone at their constant rates, non stop, produced 6000 and 8000 nails respectively. Did machine M work longer than machine N?

(1) Machine N produces 2000 more nails than machine M in one hour when each machine work at its constant rate.

If the rate of M is 2,000 nails per hour and the rate of N is 4,000 nails per hour, then to produce 6,000 nails, M needs 3 hours and to produce 8,000 nails N, needs 2 hours. In this case M worked longer than N.

If the rate of M is 6,000 nails per hour and the rate of N is 8,000 nails per hour, then to produce 6,000 nails, M needs 1 hours and to produce 8,000 nails N, needs 1 hour. In this case M did not work longer than N.

Not sufficient.

(2) Machine N produces twice as much as machine M in one hour when each machine work at its constant rate. In the time M needs to produce 6,000 nails, N can produce 12,000 nails, thus it can produce 8,000 nails in less time than M can produce 6,000 nails. Sufficient.

Answer: B.



The highlighted part: If the question is to produce 6000 nails then definitely M needs 1 hour but N with a rate of 8000 nails per hour would need less than an hour right?

Please clarify if possible.
Thank you.
Math Expert
Joined: 02 Sep 2009
Posts: 93096
Own Kudos [?]: 622264 [0]
Given Kudos: 81800
Send PM
Re: Machine M and Machine N working alone at their constant rate [#permalink]
Expert Reply
earnit wrote:
Bunuel wrote:
Machine M and Machine N working alone at their constant rates, non stop, produced 6000 and 8000 nails respectively. Did machine M work longer than machine N?

(1) Machine N produces 2000 more nails than machine M in one hour when each machine work at its constant rate.

If the rate of M is 2,000 nails per hour and the rate of N is 4,000 nails per hour, then to produce 6,000 nails, M needs 3 hours and to produce 8,000 nails N, needs 2 hours. In this case M worked longer than N.

If the rate of M is 6,000 nails per hour and the rate of N is 8,000 nails per hour, then to produce 6,000 nails, M needs 1 hours and to produce 8,000 nails N, needs 1 hour. In this case M did not work longer than N.

Not sufficient.

(2) Machine N produces twice as much as machine M in one hour when each machine work at its constant rate. In the time M needs to produce 6,000 nails, N can produce 12,000 nails, thus it can produce 8,000 nails in less time than M can produce 6,000 nails. Sufficient.

Answer: B.



The highlighted part: If the question is to produce 6000 nails then definitely M needs 1 hour but N with a rate of 8000 nails per hour would need less than an hour right?

Please clarify if possible.
Thank you.


How does N, at the rate of 8,000 nails per hour, need more than an hour to produce 8000 nails? It will need exactly 1 hour.

Again, the question asks: did machine M (which produced 6000 nails) work longer than machine N (which produced 8000 nails)?

If the rate of M is 6,000 nails per hour and the rate of N is 8,000 nails per hour, then to produce 6,000 nails, M needs 1 hours and to produce 8,000 nails N, needs 1 hour. In this case M did not work longer than N.
User avatar
Manager
Manager
Joined: 06 Mar 2014
Posts: 166
Own Kudos [?]: 477 [0]
Given Kudos: 84
Location: India
GMAT Date: 04-30-2015
Send PM
Re: Machine M and Machine N working alone at their constant rate [#permalink]
Bunuel wrote:
earnit wrote:
Bunuel wrote:
Machine M and Machine N working alone at their constant rates, non stop, produced 6000 and 8000 nails respectively. Did machine M work longer than machine N?

(1) Machine N produces 2000 more nails than machine M in one hour when each machine work at its constant rate.

If the rate of M is 2,000 nails per hour and the rate of N is 4,000 nails per hour, then to produce 6,000 nails, M needs 3 hours and to produce 8,000 nails N, needs 2 hours. In this case M worked longer than N.

If the rate of M is 6,000 nails per hour and the rate of N is 8,000 nails per hour, then to produce 6,000 nails, M needs 1 hours and to produce 8,000 nails N, needs 1 hour. In this case M did not work longer than N.

Not sufficient.

(2) Machine N produces twice as much as machine M in one hour when each machine work at its constant rate. In the time M needs to produce 6,000 nails, N can produce 12,000 nails, thus it can produce 8,000 nails in less time than M can produce 6,000 nails. Sufficient.

Answer: B.



The highlighted part: If the question is to produce 6000 nails then definitely M needs 1 hour but N with a rate of 8000 nails per hour would need less than an hour right?

Please clarify if possible.
Thank you.


How does N, at the rate of 8,000 nails per hour, need more than an hour to produce 8000 nails? It will need exactly 1 hour.

Again, the question asks: did machine M (which produced 6000 nails) work longer than machine N (which produced 8000 nails)?

If the rate of M is 6,000 nails per hour and the rate of N is 8,000 nails per hour, then to produce 6,000 nails, M needs 1 hours and to produce 8,000 nails N, needs 1 hour. In this case M did not work longer than N.



Got it.
Its not the common number that the machines are expected to produce.
That part slipped out when exploring the options.

Key take away: if there is a common number required to produce then even (1) would be sufficient. But not in the above case.
Math Revolution GMAT Instructor
Joined: 16 Aug 2015
Posts: 10156
Own Kudos [?]: 16659 [3]
Given Kudos: 4
GMAT 1: 760 Q51 V42
GPA: 3.82
Send PM
Machine M and Machine N working alone at their constant rate [#permalink]
2
Kudos
1
Bookmarks
Expert Reply
Forget conventional ways of solving math questions. In DS, Variable approach is the easiest and quickest way to find the answer without actually solving the problem. Remember equal number of variables and equations ensures a solution.


Machine M and Machine N working alone at their constant rates, non stop, produced 6000 and 8000 nails respectively. Did machine M work longer than machine N?

(1) Machine N produces 2000 more nails than machine M in one hour when each machine work at its constant rate

(2) Machine N produces twice as much as machine M in one hour when each machine work at its constant rate

In the original condition, r1*t1=6000, r2*t2=8000 and throw some transformation we have t1=6000/r1, t2=8000/r2 and 6000/r1>8000/r2, 3r2>4r1?, therefore the question is all about comparing r1 and r2.
We have 4 variables (r1,r2,t1,t2), 2 equations (r1*t1=6000, r2*t2=8000) therefore we need 2 more equations and therefore C is likely the answer. Using both 1) & 2) together, r2=r1+2000, r2=2r1 gives us r1=2000, r2=4000 and thus C is the answer. But such trivial conditions are rarely the answer, so we might try it separately again.

Using 1), 2)separately, (from Common mistake type 4(A), in case of 2) substituting r2=2r1 to 3r2>4r1? gives us 3*2r1>4r1?, 6>4. Therefore the answer is yes, and the condition is sufficient. Therefore the answer is B. (when looking at conditions 1), 2) if one is given by value and the other is given by ratio, the one with ratio is usually the answer. That's why we just calculated using con 1) here. )
Intern
Intern
Joined: 30 Aug 2016
Posts: 3
Own Kudos [?]: 8 [2]
Given Kudos: 92
Location: Italy
GMAT 1: 700 Q47 V41
GPA: 3.83
Send PM
Re: Machine M and Machine N working alone at their constant rate [#permalink]
2
Kudos
Here is my approach

Is 6000/(rate of m = rm) > 8000 / (rate of n = rn) ? <--> Is 6/rm > 8/rn? <--> Is 6 rn > 8 rm ?

St. 1: rn = rm + 2000 --> Is 6 rm + 12000 > 8 rm ? Here we get a condition, i.e. rm < 6000 that is not verified a priori --> NOT SUFF

St. 2: rn = 2 rm --> Is 12 rm > 8 rm ? Yes because rm >0 --> SUFF

B
Director
Director
Joined: 29 Oct 2015
Posts: 588
Own Kudos [?]: 306 [0]
Given Kudos: 389
Send PM
Re: Machine M and Machine N working alone at their constant rate [#permalink]
Reni wrote:
Machine M and Machine N working alone at their constant rates, non stop, produced 6000 and 8000 nails respectively. Did machine M work longer than machine N?

(1) Machine N produces 2000 more nails than machine M in one hour when each machine work at its constant rate

(2) Machine N produces twice as much as machine M in one hour when each machine work at its constant rate


Statement 1 :-
Say , Machine M produces x nails / hour and machine N produces (x +2000 ) nails / hour.
Machine M worked for = 6000/x hours.
Machine N worked for = 8000 / (x + 2000) hours.
The denominator is not same . We cant tell whether 6000/x > 8000/(x+2000)
It depends on the value of x.

Statement 2:-
Say , Machine M produces x nails / hour and machine N produces 2*x nails / hour.
So, Machine M worked for = 6000/x hours.
Machine N worked for = 8000 /2*x hours = 4000/x hours

Since the denominator is fixed , we can say YES , machine M work longer than machine N.

Take a fixed denominator for example , x = 2
6000 / 2 = 3000
4000/2 = 2000
3000 > 2000

Please give me kudo s if you liked my explanation.
Intern
Intern
Joined: 21 Oct 2018
Posts: 43
Own Kudos [?]: 10 [0]
Given Kudos: 604
Location: India
Schools: ISB '21
Send PM
Re: Machine M and Machine N working alone at their constant rate [#permalink]
Very well curated question from GMAT !!

Option 2 is easily sufficient , and coming option 1 is trap as we don't consider below scenario or hardly skip this part.

If the rate of M is 6,000 nails per hour and the rate of N is 8,000 nails per hour, then to produce 6,000 nails, M needs 1 hours and to produce 8,000 nails N, needs 1 hour. In this case M did not work longer than N.
Manager
Manager
Joined: 23 May 2023
Posts: 62
Own Kudos [?]: 31 [0]
Given Kudos: 305
Location: India
Concentration: Real Estate, Sustainability
GPA: 3.7
WE:Other (Other)
Send PM
Machine M and Machine N working alone at their constant rate [#permalink]
Machine M :
Work = 6000 nails
Let time = m
Rate = \(\frac{6000}{m}\)


Machine N :
Work = 8000 nails
Let time = n
Rate = \(\frac{8000}{n}\)

Question: Is m>n?

1:

\((\frac{8000}{n}) * 1 - (\frac{6000}{m}) * 1 = 2000\\
4m-3n = mn \)

Not sufficient


2:

\(\frac{8000}{n} = 2* (\frac{6000}{m})\\
m=\frac{3n}{2}\\
m>n\)

Sufficient.
GMAT Club Bot
Machine M and Machine N working alone at their constant rate [#permalink]
Moderator:
Math Expert
93096 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne