Last visit was: 26 Apr 2024, 08:10 It is currently 26 Apr 2024, 08:10

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Math Expert
Joined: 02 Sep 2009
Posts: 92940
Own Kudos [?]: 619180 [34]
Given Kudos: 81609
Send PM
Most Helpful Reply
Math Expert
Joined: 02 Sep 2009
Posts: 92940
Own Kudos [?]: 619180 [17]
Given Kudos: 81609
Send PM
General Discussion
User avatar
Manager
Manager
Joined: 11 Oct 2013
Posts: 70
Own Kudos [?]: 286 [25]
Given Kudos: 137
Concentration: Marketing, General Management
GMAT 1: 600 Q41 V31
Send PM
avatar
Intern
Intern
Joined: 29 Nov 2015
Posts: 4
Own Kudos [?]: 5 [0]
Given Kudos: 42
Send PM
Re: D01-30 [#permalink]
I think this is a high-quality question and I agree with explanation.
Intern
Intern
Joined: 23 Apr 2014
Posts: 45
Own Kudos [?]: 24 [0]
Given Kudos: 82
Location: United States
GMAT 1: 680 Q50 V31
GPA: 2.75
Send PM
Re: D01-30 [#permalink]
I think this is a high-quality question and I agree with explanation.
avatar
Manager
Manager
Joined: 03 Dec 2013
Posts: 50
Own Kudos [?]: 53 [0]
Given Kudos: 11
Location: United States (HI)
GMAT 1: 660 Q49 V30
GPA: 3.56
Send PM
Re: D01-30 [#permalink]
I think this is a high-quality question and I agree with explanation. Great question. I freaked out when I first faced it but was able to solve it within 2 mins! Thanks
Intern
Intern
Joined: 30 Mar 2016
Status:Preparation
Posts: 12
Own Kudos [?]: 12 [2]
Given Kudos: 28
Location: India
Concentration: General Management, Technology
GPA: 4
Send PM
Re: D01-30 [#permalink]
2
Kudos
I will go with this approach,

rate of A= 1/20 job per day
rate of B = 1/30 job per day

when they work together the no of days required to complete the task = 1/20 + 1/30 = 3+2/60 = 5/60 = 1/12

when A and B were working together let us assume that after X days A left the working while ,
so the work completed in X days by both of them = x * 1/12= x/12

so the work remaining = 1-x/12 = 12-x/12

Now B worked for 5 days , so total work done by B in 5 days = 5*1/30 = 1/6

now the total work remaining = total work remaining after x days - work done alone by B in 5 days
= 12-x/12 - 1/6
= 10-x/12

now A rejoined the work and they both completed the remaining work in 4 days
remaining work = 4 days of work for A and B
10-x/12 = 4/12
10-x = 4
x= 6

so the no of days after which A left working together is 6
Intern
Intern
Joined: 13 Mar 2016
Posts: 44
Own Kudos [?]: 82 [2]
Given Kudos: 89
Location: India
Concentration: General Management, Entrepreneurship
WE:General Management (Energy and Utilities)
Send PM
Re: D01-30 [#permalink]
2
Kudos
let for x days A worked with B before he left
Now
A worked for X+ 4 days
B worked for X+4+5 ie. X+9 days.

(X+4)/20 + (x+9)/30 =1
solve this you will get X=6
RSM Erasmus Moderator
Joined: 26 Mar 2013
Posts: 2461
Own Kudos [?]: 1360 [4]
Given Kudos: 641
Concentration: Operations, Strategy
Schools: Erasmus (II)
Send PM
Re: D01-30 [#permalink]
2
Kudos
2
Bookmarks
Bunuel wrote:
Painters A and B can paint a house working alone in 20 and 30 days respectively. They started painting a house together but then A left after a number of days but then rejoined B before the job was completed. If B worked alone for 5 days and then A and B together completed the work in 4 days, after how many days of working together, did A leave B?

A. 4
B. 5
C. 6
D. 7
E. 8



Given from the prompt:

A & B worked together + B worked alone + A& B joined again to complete work

Combined rate = 1/20+ 1/30 = (3+2)/60=5/60= 1/12 job/day

Let T= time for both A & B together before A leaving B

To solve the question:

Use the standard formula

Work = rate * time

Following the sequence stated by prompt

T *1/12 + 5 *1/30 + 4 *1/12 = 1 .............( the work here is one house)

T /12 + 1/6 + 1/3 = 1

T /12 + 3/6= 1

T /12 = 1/2 .......T=6

Answer: C
Intern
Intern
Joined: 20 Apr 2017
Posts: 2
Own Kudos [?]: 0 [0]
Given Kudos: 36
Location: Bangladesh
Schools: Goodman "22
GMAT 1: 670 Q46 V36
GPA: 2.79
Send PM
Re: D01-30 [#permalink]
I think this is a high-quality question.
Intern
Intern
Joined: 22 May 2017
Posts: 1
Own Kudos [?]: 5 [0]
Given Kudos: 24
Location: United States (TX)
Concentration: General Management, Strategy
GMAT 1: 680 Q50 V32
GPA: 3.24
WE:Supply Chain Management (Energy and Utilities)
Send PM
Re: D01-30 [#permalink]
I think this is a high-quality question and I agree with explanation.
Intern
Intern
Joined: 12 Sep 2016
Posts: 20
Own Kudos [?]: 10 [1]
Given Kudos: 32
Location: India
GMAT 1: 730 Q47 V42
WE:Accounting (Consulting)
Send PM
Re: D01-30 [#permalink]
1
Bookmarks
Let's pick up a Number which is the LCM of both of A and B's rates, for eg. 60.
Here, let 60 be the total units of work to be done.

So, if A takes 20 days to finish 60 units, it means he accomplishes 60/20= 3 units per day.
Similarly, if B takes 30 days to finish 60 units, he accomplishes 60/30= 2 units per day

Now, the total work done by them in 1 day= 3+2= 5 units.

For the 5 days B worked by himself, he gets 5*2 units= 10 units done.
The 4 days A and B work together in the end, they get 4* 5 units= 20 units done.
Total work done= 30 units.
Leftover work= 60-30 units= 30 units. This is the work that A and B must have done together, before A left.

So, given the combined rate, A and B together must have done 30 units in 30/5= 6 days!
Math Expert
Joined: 02 Sep 2009
Posts: 92940
Own Kudos [?]: 619180 [0]
Given Kudos: 81609
Send PM
Re: D01-30 [#permalink]
Expert Reply
I have edited the question and the solution by adding more details to enhance its clarity. I hope it is now easier to understand.
Intern
Intern
Joined: 08 Aug 2022
Posts: 1
Own Kudos [?]: 0 [0]
Given Kudos: 16
Send PM
Re D01-30 [#permalink]
I think this is a high-quality question and I agree with explanation. I agree with the explanation just I want to point out that the work done in second stage, can you explain why you considered 5*1/30= 2/12
Math Expert
Joined: 02 Sep 2009
Posts: 92940
Own Kudos [?]: 619180 [0]
Given Kudos: 81609
Send PM
Re: D01-30 [#permalink]
Expert Reply
aviral12567 wrote:
I think this is a high-quality question and I agree with explanation. I agree with the explanation just I want to point out that the work done in second stage, can you explain why you considered 5*1/30= 2/12


In the second stage, B worked alone for 5 days at the rate of \(\frac{1}{30}\) job/day, hence completed \(5*\frac{1}{30}=\frac{2}{12}\) of the job.
DI Forum Moderator
Joined: 05 May 2019
Status:GMAT Club Team member
Affiliations: GMAT Club
Posts: 1030
Own Kudos [?]: 638 [0]
Given Kudos: 1003
Location: India
GMAT Focus 1:
645 Q82 V81 DI82
GMAT 1: 430 Q31 V19
GMAT 2: 570 Q44 V25
GMAT 3: 660 Q48 V33
GPA: 3.26
WE:Engineering (Manufacturing)
Send PM
Re D01-30 [#permalink]
I think this is a high-quality question and I agree with explanation.
GMAT Club Bot
Re D01-30 [#permalink]
Moderator:
Math Expert
92940 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne