GMAT Question of the Day (Jan 19): Work Problem and Critical Reasoning

dzyubam 0

Math (PS)

A contractor estimated that his 10-men crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, after 5 days of rain, on the 61-st day, he hired 6 more people to finish the project early. If the job was done in 100 days, on how many days after day 60 was it raining?

(A) 4
(B) 5
(C) 6
(D) 7
(E) 8

OA and Explanation

Like these questions? Get the GMAT Club question collection: online at GMAT Club OR on your Kindle OR on your iPhone/iPad

Verbal (CR)

Monarch butterflies, whose average life span is nine months, migrate from the midwestern United States to selected forests outside Mexico City. It takes at least three generations of monarchs to make the journey, so the great-great-grandchildren who finally arrive in the Mexican forests have never been there before. Yet they return to the same trees their forebears left. Scientists theorize that monarchs, like homing pigeons, map their routes according to the earth’s electromagnetic fields. As a first step in testing this theory, lepidopterists plan to install a low-voltage transmitter inside one grove of “butterfly trees” in the Mexican forests. If the butterflies are either especially attracted to the grove with the transmitter or especially repelled by it, lepidopterists will have evidence that______

(A) monarch butterflies have brains, however minuscule
(B) monarch butterflies are sensitive to electricity
(C) low-voltage electricity can affect butterflies, whether positively or adversely
(D) monarchs map their routes according to the earth’s electromagnetic fields
(E) monarchs communicate in intergenerationally via electromagnetic fields

OA and Explanation