VeritasPrepKarishma wrote:
rtaha2412 wrote:
A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?
4
5
6
7
8
You can visualize it in another way:
10 man crew needs 110 days means the total work = 10*110 = 1100 man-days
(man-days means the amount of work 1 man does in 1 day)
In 60 days, it rained for 5 days and the crew worked for 55 days and completed 10*55 = 550 man-days work and left over work is 1100 - 550 = 550 man-days
From 61st day on, there are 16 people working and will need 550/16 = 34.4 days to complete the remaining work. So out of 40 days (from 61st to 100th day), 35 days were used (though the 100th day wasn't completely utilized) and it must have rained on 5 days.
Following your approach, I did this, but the answer came out wrong.
after 60 days have passed, the 16 member crew is able to do 550 mandays of work in 40 days.
What would've happened if it worked for the 40 days? they would have done 640 mandys of work.
But they did only 550 mandays of work. so they did not work for the number of days it would have taken them to do 640-550 = 90 mandays of work
90/16 = 5.625 rounding off gives 6!