Last visit was: 26 Apr 2024, 05:25 It is currently 26 Apr 2024, 05:25

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Kudos
Tags:
Show Tags
Hide Tags
Math Expert
Joined: 02 Sep 2009
Posts: 92931
Own Kudos [?]: 619154 [13]
Given Kudos: 81609
Send PM
Retired Moderator
Joined: 19 Oct 2018
Posts: 1878
Own Kudos [?]: 6296 [2]
Given Kudos: 704
Location: India
Send PM
Target Test Prep Representative
Joined: 14 Oct 2015
Status:Founder & CEO
Affiliations: Target Test Prep
Posts: 18761
Own Kudos [?]: 22055 [2]
Given Kudos: 283
Location: United States (CA)
Send PM
GMAT Club Legend
GMAT Club Legend
Joined: 18 Aug 2017
Status:You learn more from failure than from success.
Posts: 8020
Own Kudos [?]: 4098 [1]
Given Kudos: 242
Location: India
Concentration: Sustainability, Marketing
GMAT Focus 1:
545 Q79 V79 DI73
GPA: 4
WE:Marketing (Energy and Utilities)
Send PM
Re: 10 men take 30 minutes to wrap 100 articles. How long will it take 40 [#permalink]
1
Bookmarks
Method 1;

time per article ; 100/30 ; 3.33
time per men ; 3.33/10 ; .33
effici

.33*40 = 13.33
given efficiency is half ; 13.33/2
200*2 /13.3 = 30
IMO C

Method 2
m1*t1/w1= m2*t2/w2

10*30/100 = 1/2 * 40*t2/200
t2 = 30 mins
IMO C



Bunuel wrote:
10 men take 30 minutes to wrap 100 articles. How long will it take 40 men to wrap 200 articles if the new team is half as efficient?

A. 7.5 minutes
B. 15 minutes
C. 30 minutes
D. 60 minutes
E. 120 minutes


Are You Up For the Challenge: 700 Level Questions
Intern
Intern
Joined: 12 Mar 2017
Posts: 7
Own Kudos [?]: 9 [0]
Given Kudos: 3
Location: India
Anup: Patel
Concentration: Strategy, Economics
GPA: 3
WE:Education (Education)
Send PM
Re: 10 men take 30 minutes to wrap 100 articles. How long will it take 40 [#permalink]
we can use the general equation : n*R*t = W
where n - no. of units/ men/ women/ machine etc
R - rate of the work
t - time required for work (note units of time should be consistent)
W - total work completed (usually taken as 1) - in this it is given as 100 & 200

setting up the equation
nRT = W
10R*30 = 100
R = 1/3
So,
40* 1/3 * t = 200
t = 15 min
Manager
Manager
Joined: 10 Dec 2017
Posts: 235
Own Kudos [?]: 207 [0]
Given Kudos: 135
Location: India
Send PM
Re: 10 men take 30 minutes to wrap 100 articles. How long will it take 40 [#permalink]
Bunuel wrote:
10 men take 30 minutes to wrap 100 articles. How long will it take 40 men to wrap 200 articles if the new team is half as efficient?

A. 7.5 minutes
B. 15 minutes
C. 30 minutes
D. 60 minutes
E. 120 minutes


Are You Up For the Challenge: 700 Level Questions

40*1/2*(100/300)*t=200
t=30 minutes
C:)
Intern
Intern
Joined: 05 Oct 2019
Posts: 36
Own Kudos [?]: 7 [0]
Given Kudos: 91
Location: Georgia
Concentration: Marketing, General Management
GMAT 1: 540 Q37 V27
GPA: 2.88
Send PM
Re: 10 men take 30 minutes to wrap 100 articles. How long will it take 40 [#permalink]
10 men - 30 minutes - 100 articles - 30/100=3/10 Rate
1 man from the old team - (3/10)/10= 1/3 Rate
1 man from the new team with half the effi. = (1/3)/2 = 1/6
40 men from the new team with new rate = 40/6 = 20/3
The whole new team's timing: 200/(20/3) = 30 minutes - C.
Board of Directors
Joined: 11 Jun 2011
Status:QA & VA Forum Moderator
Posts: 6072
Own Kudos [?]: 4690 [0]
Given Kudos: 463
Location: India
GPA: 3.5
WE:Business Development (Commercial Banking)
Send PM
Re: 10 men take 30 minutes to wrap 100 articles. How long will it take 40 [#permalink]
Bunuel wrote:
10 men take 30 minutes to wrap 100 articles. How long will it take 40 men to wrap 200 articles if the new team is half as efficient?

A. 7.5 minutes
B. 15 minutes
C. 30 minutes
D. 60 minutes
E. 120 minutes


Are You Up For the Challenge: 700 Level Questions


\(M_1T_1W_2 = M_2T_2W_1\)

\(10*30*200 = 40*T_2*100\)

Or, \(T_2 = 15\), Answer must be (B)
Intern
Intern
Joined: 19 Mar 2022
Posts: 6
Own Kudos [?]: 0 [0]
Given Kudos: 116
Location: Poland
GMAT 1: 670 Q44 V38
Send PM
Re: 10 men take 30 minutes to wrap 100 articles. How long will it take 40 [#permalink]
IF THE TEAM IS HALF AS EFFICIENT :/
Intern
Intern
Joined: 11 Jan 2021
Posts: 15
Own Kudos [?]: 1 [0]
Given Kudos: 19
Send PM
10 men take 30 minutes to wrap 100 articles. How long will it take 40 [#permalink]
W1/M1D1=W2/M2D2
So, 100/(10*30)= 200/(40*t)
So, t= 15
But as the new team is half efficient, so t=30 mins (Option C)

Note: Time is inversely proportional to Efficiency
Senior Manager
Senior Manager
Joined: 21 Nov 2021
Posts: 437
Own Kudos [?]: 211 [0]
Given Kudos: 345
Send PM
Re: 10 men take 30 minutes to wrap 100 articles. How long will it take 40 [#permalink]
When the numbers are simple as these are, should be able to do in your head.

Twice as many articles, twice the time.

But, 4x as many workers, 1/4 the time.

Half as efficient, twice the time.

2*1/4*2 = 1. Same time.

Posted from my mobile device
GMAT Club Bot
Re: 10 men take 30 minutes to wrap 100 articles. How long will it take 40 [#permalink]