Last visit was: 26 Apr 2024, 08:28 It is currently 26 Apr 2024, 08:28

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
User avatar
Intern
Intern
Joined: 19 Dec 2009
Posts: 17
Own Kudos [?]: 465 [34]
Given Kudos: 9
Send PM
Most Helpful Reply
Tutor
Joined: 16 Oct 2010
Posts: 14830
Own Kudos [?]: 64934 [11]
Given Kudos: 427
Location: Pune, India
Send PM
Math Expert
Joined: 02 Sep 2009
Posts: 92945
Own Kudos [?]: 619183 [10]
Given Kudos: 81609
Send PM
General Discussion
Math Expert
Joined: 02 Sep 2009
Posts: 92945
Own Kudos [?]: 619183 [7]
Given Kudos: 81609
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
3
Kudos
4
Bookmarks
Expert Reply
rtaha2412 wrote:
A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?

4
5
6
7
8


Given: 10-man crew needs 110 days to complete the construction.

"On the 61-st day, after 5 days of rain ..." --> as it was raining for 5 days then they must have bee working for 55 days thus completed 1/2 of the job, 1/2 is left (55 days of work for 10 men).

Then contractor "hired 6 more people" --> speed of construction increased 1.6 times, so the new 16-man crew needed 55/1.6=~34.4 days to complete the construction, but after they were hired job was done in 100-60=40 days --> so 5 days rained. (They needed MORE than 34 days to finish the job, so if it rained for 6 days they wouldn't be able to finish the job in 100(40) days.)

Answer: B.
Tutor
Joined: 16 Oct 2010
Posts: 14830
Own Kudos [?]: 64934 [4]
Given Kudos: 427
Location: Pune, India
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
2
Kudos
2
Bookmarks
Expert Reply
rtaha2412 wrote:
A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?

4
5
6
7
8


You can visualize it in another way:
10 man crew needs 110 days means the total work = 10*110 = 1100 man-days
(man-days means the amount of work 1 man does in 1 day)

In 60 days, it rained for 5 days and the crew worked for 55 days and completed 10*55 = 550 man-days work and left over work is 1100 - 550 = 550 man-days

From 61st day on, there are 16 people working and will need 550/16 = 34.4 days to complete the remaining work. So out of 40 days (from 61st to 100th day), 35 days were used (though the 100th day wasn't completely utilized) and it must have rained on 5 days.
User avatar
Manager
Manager
Joined: 07 Jan 2010
Posts: 80
Own Kudos [?]: 297 [0]
Given Kudos: 57
Location: So. CA
Concentration: General
WE 1: 2 IT
WE 2: 4 Software Analyst
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
VeritasPrepKarishma wrote:


From 61st day on, there are 16 people working and will need 550/16 = 34.4 days to complete the remaining work. So out of 40 days (from 61st to 100th day), 35 days were used (though the 100th day wasn't completely utilized) and it must have rained on 5 days.


your method makes sense, but i got kind of lost at the end.
so if it takes 34.4 days, wouldn't it be 61+34=95 days, so it rained for 5 days?
thanks.
Math Expert
Joined: 02 Sep 2009
Posts: 92945
Own Kudos [?]: 619183 [1]
Given Kudos: 81609
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
1
Kudos
Expert Reply
gtr022001 wrote:
VeritasPrepKarishma wrote:


From 61st day on, there are 16 people working and will need 550/16 = 34.4 days to complete the remaining work. So out of 40 days (from 61st to 100th day), 35 days were used (though the 100th day wasn't completely utilized) and it must have rained on 5 days.


your method makes sense, but i got kind of lost at the end.
so if it takes 34.4 days, wouldn't it be 61+34=95 days, so it rained for 5 days?
thanks.


Yes it rained on 5 days but the job took 34.4 days, so more than 34 (full 34 days and the part of 35th day). Next, you should count from 61st day (61st day is the first day when 16 men crew started to work) so 60+35=95 (not 61+...) --> 100-95=5.
Tutor
Joined: 16 Oct 2010
Posts: 14830
Own Kudos [?]: 64934 [0]
Given Kudos: 427
Location: Pune, India
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
Expert Reply
gtr022001 wrote:
VeritasPrepKarishma wrote:


From 61st day on, there are 16 people working and will need 550/16 = 34.4 days to complete the remaining work. So out of 40 days (from 61st to 100th day), 35 days were used (though the 100th day wasn't completely utilized) and it must have rained on 5 days.


your method makes sense, but i got kind of lost at the end.
so if it takes 34.4 days, wouldn't it be 61+34=95 days, so it rained for 5 days?
thanks.


As bunuel pointed out above, it rained for 5days in the first 60 days. Thereafter, in the remaining 100 - 60 = 40 days, they worked for 34.4 days ie 35 days (the 35th day, they worked partly). The rest of the 5 days, it rained. Snce the work was not over in 34 days, they needed the 35th day. You cannot round it off to 34.
avatar
Manager
Manager
Joined: 12 Jun 2010
Status:MBA Aspirant
Posts: 79
Own Kudos [?]: 247 [0]
Given Kudos: 1
Location: India
Concentration: Finance, International Business
WE:Information Technology (Investment Banking)
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
Bunnel - Could you please explain the step
"Then contractor "hired 6 more people" --> speed of construction increased 1.6 times, so the new 16-man crew needed 55/1.6=~34.4 days"
Math Expert
Joined: 02 Sep 2009
Posts: 92945
Own Kudos [?]: 619183 [4]
Given Kudos: 81609
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
3
Kudos
1
Bookmarks
Expert Reply
subhajeet wrote:
Bunnel - Could you please explain the step
"Then contractor "hired 6 more people" --> speed of construction increased 1.6 times, so the new 16-man crew needed 55/1.6=~34.4 days"


10 men need 55 days to complete a job. How many days does 20 men need to complete the same job? In 55/2 days (the rate of 20 men group is twice the rate of 10 men group).

Similarly, if 10 men need 55 days to complete a job, 16 men (10*1.6) will need 55/1.6 days to complete the job (the rate of 16 men group is 1.6 times greater than the rate of 10 men group).

Or: there was 10*55=550 man-days of work left which can be done by 16 men in 550/16=~34.4 days.
Refer to two-consultants-can-type-up-a-report-126155.html for theory on work problems and practice questions.

Hope it helps.
avatar
Intern
Intern
Joined: 21 Sep 2010
Posts: 4
Own Kudos [?]: 14 [0]
Given Kudos: 9
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
I thought of the problem in units of work. The total project needed 1100 units of work. 550 of these units were completed by the 55th day (10 x 55). It rained on the 56th, 57th, 58th, 59th, and 60th day. On the 61st day, the contractor hired 6 more laborers thus bringing the total laborer population to 16. With 550 units of work left, these 16 laborers should have completed the remaining work in 34.375 days.

Here's where I went wrong. I added 34.375 to 61 to bring total days needed (assuming no rain after the 60th) to 95.375 (essentially 96 days of work). However, this would imply only 4 days of rain since the project actually took 100 days to complete. I believe I went wrong in adding the 34.375 to 61 instead of 60 since by doing the former I didn't credit them for one day of work. Could someone confirm this?

Thank you.
User avatar
Director
Director
Joined: 22 Mar 2011
Posts: 520
Own Kudos [?]: 2136 [0]
Given Kudos: 43
WE:Science (Education)
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
Club909 wrote:
I thought of the problem in units of work. The total project needed 1100 units of work. 550 of these units were completed by the 55th day (10 x 55). It rained on the 56th, 57th, 58th, 59th, and 60th day. On the 61st day, the contractor hired 6 more laborers thus bringing the total laborer population to 16. With 550 units of work left, these 16 laborers should have completed the remaining work in 34.375 days.

Here's where I went wrong. I added 34.375 to 61 to bring total days needed (assuming no rain after the 60th) to 95.375 (essentially 96 days of work). However, this would imply only 4 days of rain since the project actually took 100 days to complete. I believe I went wrong in adding the 34.375 to 61 instead of 60 since by doing the former I didn't credit them for one day of work. Could someone confirm this?

Thank you.


You are right. You simply took away one work day. The 61st day of the project was a work day, in fact the first day when the extended team of 16 took over the job.
Tutor
Joined: 16 Oct 2010
Posts: 14830
Own Kudos [?]: 64934 [0]
Given Kudos: 427
Location: Pune, India
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
Expert Reply
Club909 wrote:
I thought of the problem in units of work. The total project needed 1100 units of work. 550 of these units were completed by the 55th day (10 x 55). It rained on the 56th, 57th, 58th, 59th, and 60th day. On the 61st day, the contractor hired 6 more laborers thus bringing the total laborer population to 16. With 550 units of work left, these 16 laborers should have completed the remaining work in 34.375 days.

Here's where I went wrong. I added 34.375 to 61 to bring total days needed (assuming no rain after the 60th) to 95.375 (essentially 96 days of work). However, this would imply only 4 days of rain since the project actually took 100 days to complete. I believe I went wrong in adding the 34.375 to 61 instead of 60 since by doing the former I didn't credit them for one day of work. Could someone confirm this?

Thank you.


Think of it this way: 60 days are accounted for. From the 61st day to the 100th day, there are 40 days. You need 35 of these to complete the work so you are left with 5 days.
When you add 35 to 61, you are saying that 61 days are accounted for but that is not the case.
avatar
Intern
Intern
Joined: 01 Oct 2012
Posts: 12
Own Kudos [?]: 15 [0]
Given Kudos: 9
Location: United States
Concentration: Entrepreneurship, Marketing
WE:Research (Energy and Utilities)
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
Bunuel wrote:
manalq8 wrote:
A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?

A. 4
B. 5
C. 6
D. 7
E. 8


Given: 10-man crew needs 110 days to complete the construction.

"On the 61-st day, after 5 days of rain ..." --> as it was raining for 5 days then they must have bee working for 55 days thus completed 1/2 of the job, 1/2 is left (55 days of work for 10 men).

Then contractor "hired 6 more people" --> speed of construction increased 1.6 times, so the new 16-man crew needed 55/1.6=~34.4 days to complete the construction, but after they were hired job was done in 100-60=40 days --> so 5 days rained. (They needed MORE than 34 days to finish the job, so if it rained for 6 days they wouldn't be able to finish the job in 100(40) days.)

Answer: B.



Hi,

please tell me one thing:

Estimated time = 110 days
actual completed time = 100 days
no work days = 110-100 = 10 days
we are given only rain is a factor because of which no work will be done and it has already rained for 5 days before the 60th. thus 10-5 = 5 more days it will rain after the 60th

why do we have get into work and rates for this?
Tutor
Joined: 16 Oct 2010
Posts: 14830
Own Kudos [?]: 64934 [0]
Given Kudos: 427
Location: Pune, India
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
Expert Reply
geezer0305 wrote:
Hi,

please tell me one thing:

Estimated time = 110 days
actual completed time = 100 days
no work days = 110-100 = 10 days
we are given only rain is a factor because of which no work will be done and it has already rained for 5 days before the 60th. thus 10-5 = 5 more days it will rain after the 60th

why do we have get into work and rates for this?


It took 100 days to complete the work instead of the estimated 110 because he employed 6 extra people, not because they did not work on those days. The workers actually worked for only 90 days. Out of the 100 days, it rained for 10 days and they worked for the rest of the 90 days. It is just a co-incidence that the extra workforce reduced the working days by 10, the same number of days for which it rained.
avatar
Intern
Intern
Joined: 19 Jul 2012
Posts: 17
Own Kudos [?]: 33 [0]
Given Kudos: 8
Location: United States
Concentration: Operations, Entrepreneurship
Schools: INSEAD '14
WE:Consulting (Manufacturing)
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
Given 10 men took 110 days.
Total work = 1100 Man Days

Given on the 61-st day, after 5 days of rain, which means the 10 men worked for 55 days and completed:
55 X 10 = 550 Man Days of work.

Remaining work = 1100-550 = 550 Man Days of work.

Problem states that the work was completed early in 100 days by the 16 men.
Assume it rained on x days, so the work was completed in 40-x days
Hence , 16 (40-x)=550
or x ~ 5 days


Hi,
I wanted to understand if the above mentioned step in red is right.
Tutor
Joined: 16 Oct 2010
Posts: 14830
Own Kudos [?]: 64934 [0]
Given Kudos: 427
Location: Pune, India
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
Expert Reply
chechaxo wrote:
Given 10 men took 110 days.
Total work = 1100 Man Days

Given on the 61-st day, after 5 days of rain, which means the 10 men worked for 55 days and completed:
55 X 10 = 550 Man Days of work.

Remaining work = 1100-550 = 550 Man Days of work.

Problem states that the work was completed early in 100 days by the 16 men.
Assume it rained on x days, so the work was completed in 40-x days
Hence , 16 (40-x)=550
or x ~ 5 days


Hi,
I wanted to understand if the above mentioned step in red is right.


Yes, but ensure that you understand how to deal with fractions.

16 (40-x)=550
40 - x = 34.375
x = 5.625
Now will you say it rained for 5 days or 6 days? Note that you will say that it rained for 5 days because the workers needed the extra .375 day to complete the work. If it were to rain on the 6th day too, the workers would not have been able to work on that day and hence the work would not be complete.
The fraction means that on the 100th day, the workers worked i.e. there was no rain but they worked for only a fraction of the day because the work got over.
User avatar
Manager
Manager
Joined: 25 Feb 2014
Status:PLAY HARD OR GO HOME
Posts: 109
Own Kudos [?]: 624 [2]
Given Kudos: 622
Location: India
Concentration: General Management, Finance
Schools: Mannheim
GMAT 1: 560 Q46 V22
GPA: 3.1
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
2
Kudos
110 days * 10 workers= 1100 units of work in total..

55 days of work done with help of 10 workers..therefore, 55 days * 10 workers = 550 units of work done..it means 550 units of work remaining..

It means, 550 units /16 workers = 34.3 days required to finish the work..

Since the work done in 100 days,we have 40 days remaining, but the days required are 34.3 or we can say 35 since,until 0.3 units of work is not completed,we cannot claim that work is completed..

Hence 5 days of work remain...


Hope it helps.. :)
Manager
Manager
Joined: 03 Apr 2013
Posts: 222
Own Kudos [?]: 239 [0]
Given Kudos: 872
Location: India
Concentration: Marketing, Finance
GMAT 1: 740 Q50 V41
GPA: 3
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
VeritasPrepKarishma wrote:
rtaha2412 wrote:
A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?

4
5
6
7
8


You can visualize it in another way:
10 man crew needs 110 days means the total work = 10*110 = 1100 man-days
(man-days means the amount of work 1 man does in 1 day)

In 60 days, it rained for 5 days and the crew worked for 55 days and completed 10*55 = 550 man-days work and left over work is 1100 - 550 = 550 man-days

From 61st day on, there are 16 people working and will need 550/16 = 34.4 days to complete the remaining work. So out of 40 days (from 61st to 100th day), 35 days were used (though the 100th day wasn't completely utilized) and it must have rained on 5 days.


Following your approach, I did this, but the answer came out wrong.

after 60 days have passed, the 16 member crew is able to do 550 mandays of work in 40 days.

What would've happened if it worked for the 40 days? they would have done 640 mandys of work.
But they did only 550 mandays of work. so they did not work for the number of days it would have taken them to do 640-550 = 90 mandays of work

90/16 = 5.625 rounding off gives 6!
Tutor
Joined: 16 Oct 2010
Posts: 14830
Own Kudos [?]: 64934 [0]
Given Kudos: 427
Location: Pune, India
Send PM
Re: A contractor estimated that his 10-man crew could complete [#permalink]
Expert Reply
ShashankDave wrote:
VeritasPrepKarishma wrote:
rtaha2412 wrote:
A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?

4
5
6
7
8


You can visualize it in another way:
10 man crew needs 110 days means the total work = 10*110 = 1100 man-days
(man-days means the amount of work 1 man does in 1 day)

In 60 days, it rained for 5 days and the crew worked for 55 days and completed 10*55 = 550 man-days work and left over work is 1100 - 550 = 550 man-days

From 61st day on, there are 16 people working and will need 550/16 = 34.4 days to complete the remaining work. So out of 40 days (from 61st to 100th day), 35 days were used (though the 100th day wasn't completely utilized) and it must have rained on 5 days.


Following your approach, I did this, but the answer came out wrong.

after 60 days have passed, the 16 member crew is able to do 550 mandays of work in 40 days.

What would've happened if it worked for the 40 days? they would have done 640 mandys of work.
But they did only 550 mandays of work. so they did not work for the number of days it would have taken them to do 640-550 = 90 mandays of work

90/16 = 5.625 rounding off gives 6!


The answer is the same - you need to use logic here to figure out whether you will round off to 5 or 6. Note that in my explanation above, I rounded off 34.4 days to 35 days. Why? Because they worked for a part of the 35th day too. The work got completed in 0.4 day but the 35th day was used. Hence it rained for 5 days only.
You will use the same logic.
5.6 days were not used. It must have rained on 5 days and a part of the 6th day must have been used so it must not have rained on it.
GMAT Club Bot
Re: A contractor estimated that his 10-man crew could complete [#permalink]
 1   2   
Moderators:
Math Expert
92940 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne