Last visit was: 25 Apr 2024, 21:17 It is currently 25 Apr 2024, 21:17

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Kudos
Tags:
Show Tags
Hide Tags
User avatar
Intern
Intern
Joined: 12 May 2005
Posts: 23
Own Kudos [?]: 46 [1]
Given Kudos: 0
Send PM
Math Expert
Joined: 02 Sep 2009
Posts: 92915
Own Kudos [?]: 619048 [1]
Given Kudos: 81595
Send PM
GMAT Club Legend
GMAT Club Legend
Joined: 18 Aug 2017
Status:You learn more from failure than from success.
Posts: 8019
Own Kudos [?]: 4098 [0]
Given Kudos: 242
Location: India
Concentration: Sustainability, Marketing
GMAT Focus 1:
545 Q79 V79 DI73
GPA: 4
WE:Marketing (Energy and Utilities)
Send PM
GMAT Club Legend
GMAT Club Legend
Joined: 12 Sep 2015
Posts: 6820
Own Kudos [?]: 29934 [0]
Given Kudos: 799
Location: Canada
Send PM
Re: It takes 6 people 6 days to do a job. How many days would it take 2 pe [#permalink]
Expert Reply
Top Contributor
Bunuel wrote:
It takes 6 people 6 days to do a job. How many days would it take 2 people working at the same rate to do the job?

A. 3
B. 6
C. 12
D. 16
E. 18


Let's assign a "nice" value to the job (i.e., a value that works well with the given numbers: 6, 6, 2)
Let's say the job consists of making 36 widgets

It takes 6 people 6 days to do a job.
In other words, it takes 6 people 6 days to make 36 widgets.
This means 6 people can make 6 widgets in 1 day [If we divide the number of workdays by 6, the OUTPUT is divided by 6]
It also means 1 person can make 1 widget in 1 day [If we divide the number of workers by 6, the OUTPUT is divided by 6]

How many days would it take 2 people working at the same rate to do the job?
If 1 person can make 1 widget in 1 day, then...
... 2 people can make 2 widgets in 1 day [If we double the number of workers, the OUTPUT is also doubled]
The entire job is to make 36 widgets
At a rate of 2 widgets per day, it will take the workers 18 days to make 36 widgets

Answer: E

Cheers,
Brent
Intern
Intern
Joined: 17 Dec 2018
Posts: 6
Own Kudos [?]: 5 [0]
Given Kudos: 84
Send PM
Re: It takes 6 people 6 days to do a job. How many days would it take 2 pe [#permalink]
Bunuel wrote:
It takes 6 people 6 days to do a job. How many days would it take 2 people working at the same rate to do the job?

A. 3
B. 6
C. 12
D. 16
E. 18


r * t = w

lets find rate:

6 Person * rate * time = work
6 * r * 6 = 1
36 * r = 1 --> r = 1/36

lets find time:

2 Person * rate * time = work
2 * 1/36 * t = 1
1/18 * t = 1 --> t = 18
User avatar
Non-Human User
Joined: 09 Sep 2013
Posts: 32681
Own Kudos [?]: 822 [0]
Given Kudos: 0
Send PM
Re: It takes 6 people 6 days to do a job. How many days would it take 2 pe [#permalink]
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
User avatar
Non-Human User
Joined: 09 Sep 2013
Posts: 32681
Own Kudos [?]: 822 [0]
Given Kudos: 0
Send PM
Re: If it takes 6 people 6 days to do a job? How many days would [#permalink]
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
GMAT Club Bot
Re: If it takes 6 people 6 days to do a job? How many days would [#permalink]
Moderators:
Math Expert
92915 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne