Last visit was: 19 Nov 2025, 07:58 It is currently 19 Nov 2025, 07:58
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 19 Nov 2025
Posts: 105,389
Own Kudos:
Given Kudos: 99,977
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 105,389
Kudos: 778,259
 [28]
1
Kudos
Add Kudos
27
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
nick1816
User avatar
Retired Moderator
Joined: 19 Oct 2018
Last visit: 06 Nov 2025
Posts: 1,849
Own Kudos:
8,237
 [6]
Given Kudos: 707
Location: India
Posts: 1,849
Kudos: 8,237
 [6]
3
Kudos
Add Kudos
3
Bookmarks
Bookmark this Post
General Discussion
User avatar
Archit3110
User avatar
Major Poster
Joined: 18 Aug 2017
Last visit: 19 Nov 2025
Posts: 8,422
Own Kudos:
4,981
 [2]
Given Kudos: 243
Status:You learn more from failure than from success.
Location: India
Concentration: Sustainability, Marketing
GMAT Focus 1: 545 Q79 V79 DI73
GMAT Focus 2: 645 Q83 V82 DI81
GPA: 4
WE:Marketing (Energy)
GMAT Focus 2: 645 Q83 V82 DI81
Posts: 8,422
Kudos: 4,981
 [2]
1
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
User avatar
GyanOne
Joined: 24 Jul 2011
Last visit: 16 Nov 2025
Posts: 3,222
Own Kudos:
Given Kudos: 33
Status: World Rank #4 MBA Admissions Consultant
Expert
Expert reply
Posts: 3,222
Kudos: 1,691
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
Twelve engineers can complete a task in 7 Hours. Twelve engineers started the task at 10 am but starting from 1 pm, one engineer leaves every hour. At what time the task gets completed?

A. 5.30 pm
B. 6.00 pm
C. 6.30 pm
D. 7.00 pm
E. 7.30 pm


Are You Up For the Challenge: 700 Level Questions

Let us assume that every engineer does 1 unit of work in 1 hour.

If nobody had left, they would have completed the work at 5 sharp (i.e. in 7 hours from 10am).

Since one engineer leaves every hour, 1+2+3+4 units of work (or 10 units of work) is still left by 5pm. Number of engineers left at 5pm = 7.

In the next hour, they will complete 7 units of these 10 units. At 6pm, 3 units are left, and 6 engineers are left to complete them. They will do so in half an hour.

So the work will be complete at 6:30.

Option (C).
User avatar
ScottTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 14 Oct 2015
Last visit: 18 Nov 2025
Posts: 21,712
Own Kudos:
26,995
 [2]
Given Kudos: 300
Status:Founder & CEO
Affiliations: Target Test Prep
Location: United States (CA)
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 21,712
Kudos: 26,995
 [2]
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
Bunuel
Twelve engineers can complete a task in 7 Hours. Twelve engineers started the task at 10 am but starting from 1 pm, one engineer leaves every hour. At what time the task gets completed?

A. 5.30 pm
B. 6.00 pm
C. 6.30 pm
D. 7.00 pm
E. 7.30 pm


Are You Up For the Challenge: 700 Level Questions


Since the rate for 12 engineers is 1/7, after 3 hours of work (from 10 am to 1 am), 3 x 1/7 = 3/7 of the job had been completed and therefore 4/7 of the job is left to be completed.

Furthermore, the rate of 1 engineer is (1/7)/12 = 1/84, so the rate of 11 engineers is 11/84.

So, by 2 pm, 4/7 - 11/84 = 48/84 - 11/84 = 37/84 of the job is left to be completed.

The rate for 10 engineers is 10/84.

So, by 3 pm, 37/84 - 10/84 = 27/84 of the job is left to be completed.

The rate for 9 engineers is 9/84.

So, by 4 pm, 27/84 - 9/84 = 18/84 of the job is left to be completed

The rate for 8 engineers is 8/84.

So, by 5 pm, 18/84 - 8/84 = 10/84 of the job is left to be completed.

The rate for 7 engineers is 7/84.

So, by 6 pm, 10/84 - 7/84 = 3/84 of the job is left to be completed.

The rate of 6 engineers is 6/84.

So, by 6:30 pm, 3/84 - 1/2 x 6/84 = 0 of the job is left to be completed. That is, the job will be completed by 6:30 pm.

Alternate Solution:

Since it takes 12 engineers 7 hours to do the job, the total job can be accomplished in 84 hours.

From 10 - 1, we have 12 x 3 = 36 hours of work accomplished.

From 1 - 2, we have 11 additional hours, for a total of 36 + 11 = 47 hours.

From 2 - 3, we have 10 additional hours, for a total of 47 + 10 = 57 hours.

From 3 - 4, we have 9 additional hours, for a total of 57 + 9 = 66 hours.

From 4 - 5, we have 8 additional hours, for a total of 66 + 8 = 74 hours.

From 5 - 6, we have 7 additional hours, for a total of 74 + 7 = 81 hours.

Since the entire job requires 84 hours, we need only 3 more hours of work, which can be accomplished by the 6 remaining engineers in half an hour. Thus, the job will be completed at 6:30 pm.

Answer: C
User avatar
bumpbot
User avatar
Non-Human User
Joined: 09 Sep 2013
Last visit: 04 Jan 2021
Posts: 38,588
Own Kudos:
Posts: 38,588
Kudos: 1,079
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
Moderators:
Math Expert
105389 posts
Tuck School Moderator
805 posts