Last visit was: 26 Apr 2024, 22:09 It is currently 26 Apr 2024, 22:09

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
Math Expert
Joined: 02 Sep 2009
Posts: 92948
Own Kudos [?]: 619274 [5]
Given Kudos: 81609
Send PM
GMAT Club Legend
GMAT Club Legend
Joined: 03 Oct 2013
Affiliations: CrackVerbal
Posts: 4946
Own Kudos [?]: 7629 [2]
Given Kudos: 215
Location: India
Send PM
Manager
Manager
Joined: 01 Jan 2019
Posts: 52
Own Kudos [?]: 27 [0]
Given Kudos: 14
Send PM
Manager
Manager
Joined: 01 Jan 2019
Posts: 52
Own Kudos [?]: 27 [0]
Given Kudos: 14
Send PM
Re: The digging work of the DMRC on the Adohini-Andheriamore stretch requi [#permalink]
CrackVerbalGMAT wrote:
\(\frac{1}{24*16}\) is the work done by 1 man per day

To do \(\frac{1}{8}\)th of the work, the number of men = \(\frac{1 * \frac{1}{8}}{\frac{1}{24*16}} = \frac{24 * 16}{8} = 48\) men

Arun Kumar


Hi Arun, you neglected to take into account the fact that we're looking for the additional men hired after the original 16 men and 16 women.
GMAT Club Legend
GMAT Club Legend
Joined: 03 Oct 2013
Affiliations: CrackVerbal
Posts: 4946
Own Kudos [?]: 7629 [0]
Given Kudos: 215
Location: India
Send PM
Re: The digging work of the DMRC on the Adohini-Andheriamore stretch requi [#permalink]
Top Contributor
WheatyPie wrote:
CrackVerbalGMAT wrote:
\(\frac{1}{24*16}\) is the work done by 1 man per day

To do \(\frac{1}{8}\)th of the work, the number of men = \(\frac{1 * \frac{1}{8}}{\frac{1}{24*16}} = \frac{24 * 16}{8} = 48\) men

Arun Kumar


Hi Arun, you neglected to take into account the fact that we're looking for the additional men hired after the original 16 men and 16 women.



Thank you. have edited the same.
Manager
Manager
Joined: 29 Jan 2017
Posts: 50
Own Kudos [?]: 6 [0]
Given Kudos: 27
Send PM
Re: The digging work of the DMRC on the Adohini-Andheriamore stretch requi [#permalink]
Hi wheaty pie,

i tried this way but not getting the answer :

24 M * 16 D = Total Work or W
32W * 24D = 24 M * 16 D this implies that 1M = 2W

Now work done by 16 m and 16 w is (16 M + 16 W ) * 12d or 24M * 12 d

so remaining work is 24 M * 16 D - 24 M * 12 D = 192 M D

After this i am not able to proceed ? is my approach correct
Senior Manager
Senior Manager
Joined: 02 Jul 2019
Posts: 258
Own Kudos [?]: 202 [1]
Given Kudos: 200
Location: United States
Concentration: Finance, Strategy
GMAT 1: 630 Q48 V28
GMAT 2: 640 Q48 V28
Send PM
Re: The digging work of the DMRC on the Adohini-Andheriamore stretch requi [#permalink]
1
Kudos
I did it this way... Is this approach correct? CrackVerbalGMAT


Rate of men: 1 / (24*16)
Rate of women: 1 / (32*24)


Find the additional # of men required to finish work in 12 days:
16 men + 16 women in 12 days =
x additional men / (24*16) + 1/24 + 1/48 = 1/12
3x / (24*16) + 72 / 1152 = 1/ 12
3x + 72 = 96
3x = 24

Hence C.
GMAT Club Legend
GMAT Club Legend
Joined: 03 Oct 2013
Affiliations: CrackVerbal
Posts: 4946
Own Kudos [?]: 7629 [1]
Given Kudos: 215
Location: India
Send PM
Re: The digging work of the DMRC on the Adohini-Andheriamore stretch requi [#permalink]
1
Kudos
Top Contributor
DinoPen wrote:
I did it this way... Is this approach correct? CrackVerbalGMAT


Rate of men: 1 / (24*16)
Rate of women: 1 / (32*24)


Find the additional # of men required to finish work in 12 days:
16 men + 16 women in 12 days =
x additional men / (24*16) + 1/24 + 1/48 = 1/12
3x / (24*16) + 72 / 1152 = 1/ 12
3x + 72 = 96
3x = 24

Hence C.


Hi. The approach is correct
VP
VP
Joined: 11 Aug 2020
Posts: 1262
Own Kudos [?]: 201 [0]
Given Kudos: 332
Send PM
Re: The digging work of the DMRC on the Adohini-Andheriamore stretch requi [#permalink]
CrackVerbalGMAT wrote:
Bunuel wrote:
The digging work of the DMRC on the Adohini-Andheriamore stretch requires Twenty-four men to complete the work in sixteen days. As a part of the task if DMRC were to hire Thirty-two women, they can complete the same work in twenty-four days. Sixteen men and sixteen women started working and worked for twelve days. Due to time bound schedule the work had to be completed in remaining 2 days, for which how many more men are to be employed?

A. 48
B. 36
C. 24
D. 16
E. 15




Completion of work = 1

Work done by 24 men in 16 days = 1 (Since work is completed)

Work done by 1 man in 1 day = \(\frac{1}{24*16}\)


Work done by 32 women in 24 days = 1

Work done by 1 woman in 1 day = \(\frac{1}{24*32}\)


So the Ratio of work = 2 : 1 or 2 women does the work of 1 man



Work done by 16 men in 12 days = \(\frac{16 * 12}{24*16} = \frac{1}{2}\)

Work done by 16 women in 12 days = \(\frac{16 * 12}{24*32} = \frac{1}{4}\)



Work Remaining = \(1 - \frac{1}{2} - \frac{1}{4} = \frac{1}{4}\)

This work needs to be completed in 2 days. So work done per day = \(\frac{1}{8}\)



\(\frac{1}{24*16}\) is the work done by 1 man per day

To do \(\frac{1}{8}\)th of the work, the number of men = \(\frac{1 * \frac{1}{8}}{\frac{1}{24*16}} = \frac{24 * 16}{8} = 48\) men

We already have 16 men + 16 women. 16 women = 8 men (as 2 women does the work of 1 man)

Therefore Extra men required = 48 - 16 - 8 = 24


Option C

Arun Kumar


This is a difficult problem.

Arun, can you explain this last step here: To do 1818th of the work, the number of men = 1∗18/1/(24∗16) = (24∗16)/8=48 men?

Why does dividing the remaining work by the amount of work done by a man per day get you the total number of men 48?

Also, how did you conclude that the ratio of work b/w men and women is 1:2 up above?
GMAT Club Legend
GMAT Club Legend
Joined: 03 Oct 2013
Affiliations: CrackVerbal
Posts: 4946
Own Kudos [?]: 7629 [1]
Given Kudos: 215
Location: India
Send PM
Re: The digging work of the DMRC on the Adohini-Andheriamore stretch requi [#permalink]
1
Kudos
Top Contributor
CEdward wrote:

Arun, can you explain this last step here: To do 1818th of the work, the number of men = 1∗18/1/(24∗16) = (24∗16)/8=48 men?

Why does dividing the remaining work by the amount of work done by a man per day get you the total number of men 48?

Also, how did you conclude that the ratio of work b/w men and women is 1:2 up above?



Hi CEdward.

First the ratio.

Work done by Men in 1 day : Work done by women in 1 day = \(\frac{1}{24*16}\) : \(\frac{1}{24*32}\) = \(\frac{1}{16} : \frac{1}{32} = 2 : 1\)

Now the remaining work. It is simple unitary method

\(\frac{1}{24*16}\) work done by 1 man in 1 day

Therefore to do \(\frac{1}{8}\) of the work ... ? men

= \(\frac{\frac{1}{8}*1}{\frac{1}{24*16}}\) = 48


Hope this helps.


Arun Kumar
GMAT Club Bot
Re: The digging work of the DMRC on the Adohini-Andheriamore stretch requi [#permalink]
Moderators:
Math Expert
92948 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne