Last visit was: 06 Oct 2024, 02:11 It is currently 06 Oct 2024, 02:11
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
User avatar
Joined: 25 Jun 2011
Status:Finally Done. Admitted in Kellogg for 2015 intake
Posts: 395
Own Kudos [?]: 17437 [206]
Given Kudos: 217
Location: United Kingdom
Concentration: International Business, Strategy
GMAT 1: 730 Q49 V45
GPA: 2.9
WE:Information Technology (Consulting)
Send PM
Most Helpful Reply
Math Expert
Joined: 02 Sep 2009
Posts: 95944
Own Kudos [?]: 665567 [91]
Given Kudos: 87509
Send PM
avatar
Joined: 25 Feb 2010
Status:I will not stop until i realise my goal which is my dream too
Posts: 104
Own Kudos [?]: 263 [16]
Given Kudos: 16
Schools: Johnson '15
Send PM
General Discussion
User avatar
Joined: 23 Mar 2012
Posts: 2
Own Kudos [?]: 38 [17]
Given Kudos: 3
Send PM
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
11
Kudos
5
Bookmarks
above720
Here is a work problem from GMATPrep, Practice Test 1:

A company has two types of machines, type R and type S. Operating at a constant rate, a machine of type R does a certain job in 36 hours and a machine of type S does the same in job in 18 hours. If the company used the same number of each type of machine to do the job in 2 hours, how many machines of type R were used?

a) 3
b) 4
c) 6
d) 9
e) 12

Machine R does a job in 36 Hours. Machine S in 18 Hours.
Together, the machines R & S can finish the job in \(\frac{(36*18)}{(36+18)}= 12 Hours\)
In other words,
1 machine of R + 1 machine of S can finish the job together in = 12 Hours

So, to finish the job in 2 Hours, company needs 6 machines of each type - Option C
User avatar
Joined: 13 Aug 2012
Posts: 327
Own Kudos [?]: 1865 [7]
Given Kudos: 11
Concentration: Marketing, Finance
GPA: 3.23
Send PM
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
6
Kudos
1
Bookmarks
\(Let N be the number of machines...\)
\(\frac{N}{36}+\frac{N}{18}(2hours)=1\)
\(\frac{3N}{18}=1==>N=6\)

ANswer: 6 machines
avatar
Joined: 18 Jan 2010
Posts: 6
Own Kudos [?]: 3 [1]
Given Kudos: 1
Send PM
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
1
Kudos
Could someone please clarify why the answer is not 3 each? I understand how to get to 6 machines and do it quickly but why isn't this 6 machines total since it is a combined rate?
Math Expert
Joined: 02 Sep 2009
Posts: 95944
Own Kudos [?]: 665567 [3]
Given Kudos: 87509
Send PM
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
2
Kudos
1
Bookmarks
Expert Reply
mns18051985
Could someone please clarify why the answer is not 3 each? I understand how to get to 6 machines and do it quickly but why isn't this 6 machines total since it is a combined rate?

x in the solution HERE is the number of type R machines as well as the number of type S machines (we are told that the company used the same number of each type of machine to do the job ). So, when we solve for x, we get what we want.
User avatar
Joined: 15 Dec 2013
Posts: 2
Own Kudos [?]: 10 [10]
Given Kudos: 1
GPA: 3.7
Send PM
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
7
Kudos
2
Bookmarks
R finishes job in 36h and S does the same in 18h. So if both work together, the job will be done in 12h:
1/36 + 1/18 will give you 1/12.
Now if one pair of R & S finishes job in 12h, how many such pairs are needed to finish the same job in 2h?
12/2 = 6 pairs of R & S. Hence 6 of R machines are required.
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
Doubt....

1 machine A and 1 machine B together do 1/12 of the job in 1 hour.

We need to do 6/12 of the job in 1 hour...
So 6 A machines and 6 B machines will be needed for 6/12 job in 1 hour...
and 12 A and B machines will do 12/12 of the job in 2 hours...

Shouldn't the answer be E)12
Math Expert
Joined: 02 Sep 2009
Posts: 95944
Own Kudos [?]: 665567 [0]
Given Kudos: 87509
Send PM
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
Expert Reply
gmathopeful90
Doubt....

1 machine A and 1 machine B together do 1/12 of the job in 1 hour.

We need to do 6/12 of the job in 1 hour...
So 6 A machines and 6 B machines will be needed for 6/12 job in 1 hour...
and 12 A and B machines will do 12/12 of the job in 2 hours...

Shouldn't the answer be E)12

6 A's and 6 B's do half of the job in 1 hour, so 6 A's and 6 B's will do the whole job in 2 hour and this is what we are asked to find.
Target Test Prep Representative
Joined: 04 Mar 2011
Status:Head GMAT Instructor
Affiliations: Target Test Prep
Posts: 3033
Own Kudos [?]: 6956 [4]
Given Kudos: 1646
Send PM
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
2
Kudos
1
Bookmarks
Expert Reply
enigma123
A company has two types of machines, type R and type S. Operating at a constant rate, a machine of type R does a certain job in 36 hrs and a machine of type S does the same job in 18 hours. If the company used the same number of each type of machine to do the job in 2 hours, how many machines of type R were used?

A. 3
B. 4
C. 6
D. 9
E. 12

We have a combined worker problem for which we can use the following formula:

work (1 machine) + work (2 machine) = total work completed

Since we are completing one job, we can say:

work (1 machine) + work (2 machine) = 1

We are given that a machine of type R does a certain job in 36 hours and a machine of type S does the same job in 18 hours.

Thus, the rates for the two machines are as follows:

rate of machine R = 1/36

rate of machine S = 1/18

We are also given that the company used the same number of each type of machine to do the job in 2 hours. If we let x = the number of each machine used, we can multiply each rate by x and we have:

rate of x number of R machines = x/36

rate of x number of S machines = x/18

Finally, since we know some number of R and S machines worked for two hours, and since work = rate x time, we can calculate the work done by each type of machine.

work done by x number of R machines = 2x/36 = x/18

work done by x number of S machines = 2x/18 = x/9

Now we can determine x using the combined worker formula:

work (machine R) + work (machine S) = 1

x/18 + x/9 = 1

x/18 + 2x/18 = 1

3x/18 = 1

x/6 = 1

x = 6

Answer: C
Joined: 20 Jan 2015
Posts: 8
Own Kudos [?]: 1 [0]
Given Kudos: 4
Send PM
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
A company has two types of machines, Type R and Type S. Operating at a certain rate, a machine of type R does a certain job in 36 hours and a machine of type S does the same job in 18 hours. If the company uses the same number of each type of machine to do the job in 2 hours, how many machines of Type R were used?

Options:
A. 3
B. 4
C. 6
D. 9
E. 12

Can anybody give me a quickest and simpler way to solve this? I took almost 3.5 min on this question to solve during a mock test. Still ended up guessing as I wasn't sure of the approach.
Thanks.
Joined: 13 Oct 2016
Posts: 299
Own Kudos [?]: 795 [7]
Given Kudos: 40
GPA: 3.98
Send PM
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
5
Kudos
2
Bookmarks
baalok88
A company has two types of machines, Type R and Type S. Operating at a certain rate, a machine of type R does a certain job in 36 hours and a machine of type S does the same job in 18 hours. If the company uses the same number of each type of machine to do the job in 2 hours, how many machines of Type R were used?

Options:
A. 3
B. 4
C. 6
D. 9
E. 12

Can anybody give me a quickest and simpler way to solve this? I took almost 3.5 min on this question to solve during a mock test. Still ended up guessing as I wasn't sure of the approach.
Thanks.

We are given rates of each machine and that the number of machines of each type being used is the same = x.

\(\frac{x}{36} + \frac{x}{18} = \frac{1}{2}\)

\(\frac{3x}{36} = \frac{1}{2}\)

\(6x = 36\)

\(x = 6\)
Joined: 22 Jul 2016
Posts: 15
Own Kudos [?]: 47 [4]
Given Kudos: 31
Send PM
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
4
Kudos
Rate(R) = \(\frac{1}{36}\)
Rate(S) = \(\frac{1}{18}\)
Combined rate of both machines ,
Rate(RS)=Rate(R) + Rate(S) = \(\frac{1}{12}\)

we have given time , T = 2hrs , Workdone = 1 (for single job)
Plug in the values :

[Rate] * [Time] * [No. of machines] = Workdone

\(\frac{1}{12}\) * 2 * [No. of machines] = 1
[No. of machines] = 6

Ans : C
Joined: 30 Jun 2019
Posts: 3
Own Kudos [?]: 1 [1]
Given Kudos: 7
Send PM
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
1
Kudos
Why is the total of Machine R used 6 and not 3?

I understand how to solve using the question Work = Rate x Time x Number.

I solved for each rate and then combined the rates to get Number = 6.

The questions states that the same number of Machine S and R is used. Why is 6 the number of one machine and not the total for both since we solved using combined rates of both machines?

1 = 1/36 + 1/18 x (2) x (N)

Please help!!
Tutor
Joined: 16 Oct 2010
Posts: 15343
Own Kudos [?]: 68571 [3]
Given Kudos: 443
Location: Pune, India
Send PM
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
3
Kudos
Expert Reply
enigma123
A company has two types of machines, type R and type S. Operating at a constant rate, a machine of type R does a certain job in 36 hrs and a machine of type S does the same job in 18 hours. If the company used the same number of each type of machine to do the job in 2 hours, how many machines of type R were used?

A. 3
B. 4
C. 6
D. 9
E. 12

Work done by machine R in 1 hr = 1/36
Work done by machine S in 1 hr = 1/18

If both work together, work done in 1 hr = 1/36 + 1/18 = 1/12 (this is the work done by a pair, R and S in 1 hr)

But we need them to do 1/2 work in 1 hr. So we must have 6 pairs (R and S) of them.

So 6 R machines were used and 6 S machines were used.

Answer (C)

myhigheredmba
Joined: 30 Jun 2019
Posts: 3
Own Kudos [?]: 1 [0]
Given Kudos: 7
Send PM
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
VeritasKarishma - Oh, I see! It's because the 6 represents pairs!! Thank you so much!
Joined: 28 Sep 2018
Posts: 705
Own Kudos [?]: 610 [0]
Given Kudos: 248
GMAT 1: 660 Q48 V33 (Online)
GMAT 2: 700 Q49 V37
Send PM
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
EducationAisle GMATBusters Since machine R does some work in 36hrs while machine S does the same work in 18hrs (i.e. half the time) we can infer that the rate of machine S is twice the rate of machine R.

In other words, we can say that 1R is equivalent to 2S (1R = 2S) Can we leverage this and solve the question without doing much calculation?
GMAT Tutor
Joined: 27 Oct 2017
Posts: 1928
Own Kudos [?]: 5914 [0]
Given Kudos: 240
WE:General Management (Education)
Send PM
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
Expert Reply
You can do as follows :
let the work done by R per hour = x
that work done by S per hour = 2x

Now As R was able to do the work in 36 hrs: total work to be done = 36x

Now, one R and one S can do 2*(x+2x) in 2 hrs = 6x work in 2 hrs
we need to do 36x work done, hence we need 6 Nos of each machine R and S

Hoozan
EducationAisle GMATBusters Since machine R does some work in 36hrs while machine S does the same work in 18hrs (i.e. half the time) we can infer that the rate of machine S is twice the rate of machine R.

In other words, we can say that 1R is equivalent to 2S (1R = 2S) Can we leverage this and solve the question without doing much calculation?
Board of Directors
Joined: 11 Jun 2011
Status:QA & VA Forum Moderator
Posts: 6037
Own Kudos [?]: 4858 [0]
Given Kudos: 463
Location: India
GPA: 3.5
WE:Business Development (Commercial Banking)
Send PM
Re: A company has two types of machines, type R and type S. Operating at [#permalink]
enigma123
A company has two types of machines, type R and type S. Operating at a constant rate, a machine of type R does a certain job in 36 hrs and a machine of type S does the same job in 18 hours. If the company used the same number of each type of machine to do the job in 2 hours, how many machines of type R were used?

A. 3
B. 4
C. 6
D. 9
E. 12
Let the total work be 36 Units

Efficiency of machine R is 2 Units/Hr ; Efficiency of machine S is 1 Units/Hr

\(2 *n*(2 + 1) = 36\) ; n = no of machines of R and S type....

Thus, \(n = 6\), hence Answer must be (C) 6