Last visit was: 29 Apr 2024, 10:28 It is currently 29 Apr 2024, 10:28

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
GMAT Club Legend
GMAT Club Legend
Joined: 19 Dec 2014
Status:GMAT Assassin/Co-Founder
Affiliations: EMPOWERgmat
Posts: 21846
Own Kudos [?]: 11669 [3]
Given Kudos: 450
Location: United States (CA)
GMAT 1: 800 Q51 V49
GRE 1: Q170 V170
Send PM
SVP
SVP
Joined: 20 Mar 2014
Posts: 2362
Own Kudos [?]: 3626 [3]
Given Kudos: 816
Concentration: Finance, Strategy
GMAT 1: 750 Q49 V44
GPA: 3.7
WE:Engineering (Aerospace and Defense)
Send PM
GMAT Club Legend
GMAT Club Legend
Joined: 19 Dec 2014
Status:GMAT Assassin/Co-Founder
Affiliations: EMPOWERgmat
Posts: 21846
Own Kudos [?]: 11669 [2]
Given Kudos: 450
Location: United States (CA)
GMAT 1: 800 Q51 V49
GRE 1: Q170 V170
Send PM
avatar
Intern
Intern
Joined: 18 Mar 2015
Posts: 3
Own Kudos [?]: 3 [1]
Given Kudos: 18
Send PM
Re: Random Pack 1, Question 2 An assembly line produces 40 cogs per hour [#permalink]
1
Kudos
First rate = 40cogs/hr till 60 cogs are produced
So n1=60, t1=60/40=1.5 hrs

Second rate = 60 cogs/hr till another 60 cogs are produced.
So n2=60, t2=60/60=1 hr.

In total the average no. of cogs produced per hour =\(\frac{total no. of cogs}{Total no. of hours}\)
=\(\frac{120}{2.5}\)
=48 cogs/hr
Manager
Manager
Joined: 04 May 2014
Status:One Last Shot !!!
Posts: 196
Own Kudos [?]: 608 [1]
Given Kudos: 141
Location: India
Concentration: Marketing, Social Entrepreneurship
GMAT 1: 630 Q44 V32
GMAT 2: 680 Q47 V35
Send PM
Re: Random Pack 1, Question 2 An assembly line produces 40 cogs per hour [#permalink]
1
Kudos
EMPOWERgmatRichC wrote:
QUANT 4-PACK SERIES Problem Solving Pack 1 Question 2 At a company meeting...

An assembly line produces 40 cogs per hour until an initial order of 60 cogs is completed. The speed of the assembly line is then immediately increased so that it can produce 60 cogs per hour until another 60 cogs are produced. What is the average output, in cogs per hour, for the assembly line during this time?

A) 42
B) 45
C) 48
D) 50
E) 55

48 Hour Window Answer & Explanation Window
Earn KUDOS! Post your answer and explanation.
OA, and explanation will be posted after the 48 hour window closes.

This question is part of the Quant 4-Pack series

Scroll Down For Official Explanation


As soon as you realize its testing the Rates/Distance basics, it becomes quite trivial.
Just translate in terms of Speed and Distance:
Speed1 : 40 cogs/hr
Distance1: 60 Cogs

Spped2: 60 cogs/hr
Distance2: 60 cogs


Avg speed (when distances are same) : \(\frac{2*S1*S2}{S1+S2}\)
\(=> \frac{2*40*60}{40+60}\)
\(=> 48 cogs/hr\)

Option C

Please let me know if im wrong.
Board of Directors
Joined: 11 Jun 2011
Status:QA & VA Forum Moderator
Posts: 6071
Own Kudos [?]: 4691 [0]
Given Kudos: 463
Location: India
GPA: 3.5
WE:Business Development (Commercial Banking)
Send PM
Re: Random Pack 1, Question 2 An assembly line produces 40 cogs per hour [#permalink]
EMPOWERgmatRichC wrote:
An assembly line produces 40 cogs per hour until an initial order of 60 cogs is completed.


Hour 1 = 40 cogs
Hour 1\(\frac{1}{2}\) = 60 cogs

EMPOWERgmatRichC wrote:
The speed of the assembly line is then immediately increased so that it can produce 60 cogs per hour until another 60 cogs are produced


Hour 2\(\frac{1}{2}\) = 60 cogs

Hence after 2\(\frac{1}{2}\) from starting 120 cogs are produced.

EMPOWERgmatRichC wrote:
What is the average output, in cogs per hour, for the assembly line during this time?


Average cogs produced per Hour = Total No of cogs produced/Time from starting production

Average cogs produced per Hour = 120/2\(\frac{1}{2}\) => 48 cogs per hour.

A) 42
B) 45
C) 48
D) 50
E) 55

Hence answer is (C)
Senior Manager
Senior Manager
Joined: 05 Jan 2017
Posts: 416
Own Kudos [?]: 284 [0]
Given Kudos: 15
Location: India
Send PM
Re: Random Pack 1, Question 2 An assembly line produces 40 cogs per hour [#permalink]
EMPOWERgmatRichC wrote:
QUANT 4-PACK SERIES Problem Solving Pack 1 Question 2 At a company meeting...

An assembly line produces 40 cogs per hour until an initial order of 60 cogs is completed. The speed of the assembly line is then immediately increased so that it can produce 60 cogs per hour until another 60 cogs are produced. What is the average output, in cogs per hour, for the assembly line during this time?

A) 42
B) 45
C) 48
D) 50
E) 55

48 Hour Window Answer & Explanation Window
Earn KUDOS! Post your answer and explanation.
OA, and explanation will be posted after the 48 hour window closes.

This question is part of the Quant 4-Pack series

Scroll Down For Official Explanation


with 40 cogs/hr, to produce 60 cogs, time taken is 60/40 = 1.5 hrs
with 60 cogs/hr, to produce 60 cogs, time taken is 60/60 = 1 hrs

Total time taken is 1.5 +1 = 2.5
total cogs produced = 120

average rate = 120/2.5 =48 cogs/hr
User avatar
Non-Human User
Joined: 09 Sep 2013
Posts: 32738
Own Kudos [?]: 822 [0]
Given Kudos: 0
Send PM
Re: Random Pack 1, Question 2 An assembly line produces 40 cogs per hour [#permalink]
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
GMAT Club Bot
Re: Random Pack 1, Question 2 An assembly line produces 40 cogs per hour [#permalink]
Moderators:
Math Expert
93014 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne