Last visit was: 25 Apr 2024, 18:27 It is currently 25 Apr 2024, 18:27

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
Manager
Manager
Joined: 16 Mar 2016
Posts: 104
Own Kudos [?]: 224 [0]
Given Kudos: 0
Location: France
GMAT 1: 660 Q47 V33
GPA: 3.25
Send PM
User avatar
Manager
Manager
Joined: 12 Jan 2015
Posts: 154
Own Kudos [?]: 614 [0]
Given Kudos: 79
Send PM
Tutor
Joined: 16 Oct 2010
Posts: 14823
Own Kudos [?]: 64923 [1]
Given Kudos: 426
Location: Pune, India
Send PM
avatar
Intern
Intern
Joined: 15 Dec 2014
Posts: 2
Own Kudos [?]: [0]
Given Kudos: 1
Send PM
Re: A newer machine, working alone at its constant rate [#permalink]
What GMAT level question is this? I could not do it on the Veritas Prep test. :( Found it very very tough
Tutor
Joined: 16 Oct 2010
Posts: 14823
Own Kudos [?]: 64923 [0]
Given Kudos: 426
Location: Pune, India
Send PM
Re: A newer machine, working alone at its constant rate [#permalink]
Expert Reply
189anish wrote:
What GMAT level question is this? I could not do it on the Veritas Prep test. :( Found it very very tough


It is a 700 level question, so certainly on the higher side of the difficulty range. I hope that after reading the explanations, you understand it now.
User avatar
Manager
Manager
Joined: 18 Jan 2010
Posts: 210
Own Kudos [?]: 997 [6]
Given Kudos: 9
Send PM
Re: A newer machine, working alone at its constant rate [#permalink]
5
Kudos
1
Bookmarks
gmacforjyoab wrote:
A newer machine, working alone at its constant rate, can fill a production order in half the time required by two older machines working together at their constant rates. If the three machines are used together, will they require more than 1 hour to fill a production order?

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour



Suppose old machine completes work in x hours.

2 old machines will complete work in (x/2) hours

New machine completes work in (x/4) hours

In one hour Old machine does (1/x) work
In one hour New machine does (4/x) work

When all 3 work together then in one hour they do

\(\frac{1}{x}+\frac{1}{x}+\frac{4}{x} = \frac{6}{x}\)

Full work is done in \(\frac{x}{6}\) hours

Question asked is \(\frac{x}{6}\) > 1; or x > 6.


Statement 1

Old machine completes (1/2) order in less than 4 hours

so Old machine completes full order in less than 8 hours

x < 8; so x = 7 or x =1. I cant say x is necessarily more than 6.

Not sufficient.

Statement 2

New machine doubles its rate.

It completes order in (x/8) hours.

Given (x/8) < 1

or x < 8.

This is the same condition that we got from statement (1). So again not sufficient.

Even if we combine statements (1) and (2), we dont get anything new. we only get x<8

E is the answer.
Manager
Manager
Joined: 14 Oct 2012
Posts: 117
Own Kudos [?]: 258 [0]
Given Kudos: 1023
Send PM
A newer machine, working alone at its constant rate [#permalink]
Hello Friends, my 2 cents...

m/c --------------- work load ---------------------time
O1 --------------------- f/x --------------------- 1hr
O2 --------------------- f/y --------------------- 1hr
O1 + O2 ------------- f*[(x+y)/xy] ------------- 1hr
N1 ------------------- 2f*[(x+y)/xy] ------------- 1hr
O1+O2+N1 --------- 3f*[(x+y)/xy] ------------- 1hr
--------------------- f --------------------- (1/3)*[xy/(x+y)] hrs
--------------------- --------------------- (1/3)*[xy/(x+y)] < 1
--------------------- --------------------- xy/(x+y) < 3hr ?
1) Each older machine can fill (1/2) prod order in < 4 hrs
O1 --------------------- f/2x ---------------------- < 4hrs
O2 --------------------- f/2y ---------------------- < 4hrs
O1+O2 ---------------- f/2*[1/x+1/y] ---------- < 4hrs
--------------------- f/2*[x+y/xy] ------------ < 4hrs
N1 -------------------- f*[x+y/xy] --------------- < 4hrs
O1+O2+N1 ----------- f*[x+y/xy]*3/2 ---------- < 4hrs
--------------------- f --------------------- < (2/3)*[xy/(x+y)] hrs
--------------------- --------------------- (2/3)*[xy/(x+y)] < 4 hrs
--------------------- --------------------- xy/(x+y) < 6 hrs NOT SUFFICIENT
2) If new m/c doubles its rate, it can fill prod order in < 1 hr
N1 --------------------- 2f*[(x+y)/xy] --------------------- 1hr
N1 --------------------- 4f*[(x+y)/xy] --------------------- < 1hr
O1 + O2 -------------- 2f*[(x+y)/xy] --------------------- < 1hr
O1+O2+N1 ----------- 6f*[(x+y)/xy] --------------------- < 1hr
--------------------- f --------------------- (1/6)*xy/(x+y)
--------------------- --------------------- (1/6)*xy/(x+y) < 1
--------------------- --------------------- xy/(x+y) < 6hr NOT SUFFICIENT
1) + 2)
Both statments give us the same information. Thus answer E
Intern
Intern
Joined: 30 Apr 2017
Posts: 47
Own Kudos [?]: 12 [0]
Given Kudos: 74
Send PM
A newer machine, working alone at its constant rate [#permalink]
VeritasPrepKarishma wrote:
gmacforjyoab wrote:
A newer machine, working alone at its constant rate, can fill a production order in half the time required by two older machines working together at their constant rates. If the three machines are used together, will they require more than 1 hour to fill a production order?

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour


Here is another solution:

New machine takes half the time taken by 2 old machines i.e. rate of new machine is twice the rate of 2 old machines. Say rate of old machine is R. Then rate of 2 old machines is 2R. Then rate of a new machine is 2*2R = 4R.
If all 3 machines work together, their combined rate is R + R + 4R = 6R

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.
This means the old machine takes less than 8 hrs to fill a complete order i.e. its rate is at least 1/8.
R is at least 1/8 so 6R is atleast 6/8 = 3/4. So time taken by all 3 machines together to complete 1 lot is maximum 4/3 hrs. Is it actually less than 1 hr, we can't say. Not sufficient.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour
If rate is 2*4R =8R, time taken is less than 1 hour to complete 1 full production lot. So rate is at least 1/8. This is exactly the same information as obtained in statement 1. This alone will also be insufficient.

Both statements give the same information and are insufficient. So together they will be insufficient.

Answer (E)



Dear VeritasPrepKarishma
the question says: rate of a new machine is twice the rate of 2 old machines.

statement 2 says: If the newer machine were to double its rate, it could fill a production order working alone in less than one hour
we know from the question newer is twice two old, so two old can do half of part
for example newer:4R two old together:4R
if newer were 8R, work would be done in less than 1 hour
so, if we add 4R (two old) we can get that

it's logical, I cant see why it is wrong
Manager
Manager
Joined: 09 Jun 2014
Posts: 229
Own Kudos [?]: 280 [0]
Given Kudos: 205
Location: India
Concentration: General Management, Operations
Send PM
Re: A newer machine, working alone at its constant rate [#permalink]
VeritasKarishma wrote:
gmacforjyoab wrote:
A newer machine, working alone at its constant rate, can fill a production order in half the time required by two older machines working together at their constant rates. If the three machines are used together, will they require more than 1 hour to fill a production order?

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour


Here is another solution:

New machine takes half the time taken by 2 old machines i.e. rate of new machine is twice the rate of 2 old machines. Say rate of old machine is R. Then rate of 2 old machines is 2R. Then rate of a new machine is 2*2R = 4R.
If all 3 machines work together, their combined rate is R + R + 4R = 6R

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.
This means the old machine takes less than 8 hrs to fill a complete order i.e. its rate is at least 1/8.
R is at least 1/8 so 6R is atleast 6/8 = 3/4. So time taken by all 3 machines together to complete 1 lot is maximum 4/3 hrs. Is it actually less than 1 hr, we can't say. Not sufficient.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour
If rate is 2*4R =8R, time taken is less than 1 hour to complete 1 full production lot. So rate is at least 1/8. This is exactly the same information as obtained in statement 1. This alone will also be insufficient.

Both statements give the same information and are insufficient. So together they will be insufficient.

Answer (E)



Hi Karishma,

Why the combined rate as been assumed as equal R? and so 2R

Can we take it as simple R for both and for the new machine as 2R.

Now total rate sum =3R

Now from stat 1 : older machines can fill the prod order in 4 hours

So R can complete the task in less than 4 hours
hence 3R will complete the work in less than 4/3 hours .
So statement one insufficient.

Is my approach right ?
Intern
Intern
Joined: 25 Jun 2017
Posts: 28
Own Kudos [?]: 30 [0]
Given Kudos: 49
Location: Canada
GMAT 1: 660 Q45 V36
GPA: 3.5
WE:Human Resources (Consumer Products)
Send PM
Re: A newer machine, working alone at its constant rate [#permalink]
VeritasKarishma, how do we assume that the rates of the two older machines are the same?
Manager
Manager
Joined: 11 Aug 2017
Posts: 51
Own Kudos [?]: 19 [0]
Given Kudos: 92
Send PM
Re: A newer machine, working alone at its constant rate [#permalink]
tuanle wrote:
Let x, y be the time for 2 old machines to complete the job and z be the time for the newest machine to complete the same job.
When 2 old machine working together, they finish the job in \(\frac{1}{\frac{1}{x}+ \frac{1}{y}} = \frac{xy}{x+y}\). So \(z= \frac{xy}{2(x+y)}\).
(1) implies that x<8 and y<8. So z<2. If all three machines work together, the time \(\frac{1}{\frac{1}{x} + \frac{1}{y} + \frac{1}{z}}\) is less than 4/3.
(2) implies that z< 2. Similarly, If all three machines work together, the time is less than 4/3.
Answer is E



I got explanation of your first statement well.. perhaps easiest way to solve this question..
can please ellab. on 2-statement for my better understanding.
Intern
Intern
Joined: 18 Mar 2018
Posts: 20
Own Kudos [?]: 5 [0]
Given Kudos: 45
Location: Malaysia
GMAT 1: 650 Q48 V31
Send PM
Re: A newer machine, working alone at its constant rate [#permalink]
There is a very simple method to this question, the trick is to glance at what the statements are giving, and re-write the question stem in terms of time.

Draw a basic RTW table as the picture below, and assign t as the time taken for the newer machine to complete its order, associate the older machines too with the question stem:
Attachment:
Machines.PNG
Machines.PNG [ 2.78 KiB | Viewed 2096 times ]


The combined rates of newer and 2 older is as below:
\(\frac{1}{t}+\frac{1}{2t}=\frac{3}{2t}\)
Therefore it takes \(\frac{2t}{3}\) hours for the machines to complete the job.
The question stem is then asking if \(\frac{2t}{3}>1\)?
Rewriting, the question then becomes, is \(t>\frac{3}{2}\)?

Statement 1: 2 old machines finish a job in 2t hours, therefore 1 machine finishes half a job in the same 2t hours.
It takes less than 4 hours to complete the job so 2t < 4 and t < 2.
Since the question asks if t > 1.5, the answer could be yes (t = 1.75) or no (t = 1) NOT SUFFICIENT

Statement 2: Newer machine rate = \(\frac{2}{t}\), therefore time taken to complete a job =\(\frac{t}{2}\)
It takes less than an hour to complete the job so \(\frac{t}{2}<1\)
And t<2, so NOT SUFFICIENT as is it the same as Statement 1

Statements 1 & 2: Both statements give the same values, and both are inefficient, ANSWER E
Attachments

Machines.PNG
Machines.PNG [ 3.48 KiB | Viewed 2096 times ]

VP
VP
Joined: 18 Dec 2017
Posts: 1170
Own Kudos [?]: 991 [0]
Given Kudos: 421
Location: United States (KS)
GMAT 1: 600 Q46 V27
Send PM
Re: A newer machine, working alone at its constant rate [#permalink]
gmacforjyoab wrote:
A newer machine, working alone at its constant rate, can fill a production order in half the time required by two older machines working together at their constant rates. If the three machines are used together, will they require more than 1 hour to fill a production order?

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour


I did not get this question right in the test yesterday. I hate that fact.

However, this is my solution.

Let's say units of work 32 units.

Old machines does 4 units an hour. Two old combined will do 8 units, that means they will take 32/8=4 hours. That means new one is taking 2 hours and that's 16 units an hour.

Combined all 3, 32/(4+4+16)=32/24. More than an hour.

Old machines does 8 units an hour. Two old combined will do 16 units, that means they will take 32/16=2 hours. That means new one is taking 1 hours and that's 32 units an hour.

Well, clearly all 3 will take less than 1 hour.

Not Sufficient.

Statement B is just rephrasing of statement 1. I did realize that in the exam but it did not click me the answer can be E. Confidently I marked D.

Right Answer. (E)

P.S: Do you generally find VP tests to be on the higher side of difficulty ?
Intern
Intern
Joined: 08 Sep 2013
Posts: 17
Own Kudos [?]: 6 [0]
Given Kudos: 267
Send PM
A newer machine, working alone at its constant rate [#permalink]
gmacforjyoab wrote:
A newer machine, working alone at its constant rate, can fill a production order in half the time required by two older machines working together at their constant rates. If the three machines are used together, will they require more than 1 hour to fill a production order?

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour



Lets assume the total work to be 12 toys == 1 production order

New machine makes x toys per hour; Each of the older machines be y and z toys per hour

We are given x = 2 (y+z) toys in 1 hour
Questions asks, is x + y + z > 12

Statement 1: we get y=z >=(12/2)/4 toys per hour; so y+z >= 3 toys per hour
or x >=6 toys per hour
so x+y+z >= 9 toys per hour; so x+y+ z can 9, 10, 11, 12, 13....hence insufficient.

Statement 2: we get 2x > 12 or x >=6 toys per hour
=> y+z >= 3 toys per hour
so, again, x+y+z >= 9 toys per hour; Hence insufficient. since statement 1 and 2 essentially are the same both together are insufficient.
GMAT Club Legend
GMAT Club Legend
Joined: 08 Jul 2010
Status:GMAT/GRE Tutor l Admission Consultant l On-Demand Course creator
Posts: 5960
Own Kudos [?]: 13387 [0]
Given Kudos: 124
Location: India
GMAT: QUANT+DI EXPERT
Schools: IIM (A) ISB '24
GMAT 1: 750 Q51 V41
WE:Education (Education)
Send PM
Re: A newer machine, working alone at its constant rate [#permalink]
Expert Reply
gmacforjyoab wrote:
A newer machine, working alone at its constant rate, can fill a production order in half the time required by two older machines working together at their constant rates. If the three machines are used together, will they require more than 1 hour to fill a production order?

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour


Answer: Option E

Check the explanation in attachment

Attachment:
Screenshot 2020-08-05 at 8.07.34 AM.png
Screenshot 2020-08-05 at 8.07.34 AM.png [ 771.01 KiB | Viewed 1787 times ]


Subscribe to my YouTube Channel for FREE resource (1000+ Videos)



Subscribe Topic-wise UN-bundled Video course. CHECK FREE Sample Videos
GMAT Club Legend
GMAT Club Legend
Joined: 18 Aug 2017
Status:You learn more from failure than from success.
Posts: 8019
Own Kudos [?]: 4098 [0]
Given Kudos: 242
Location: India
Concentration: Sustainability, Marketing
GMAT Focus 1:
545 Q79 V79 DI73
GPA: 4
WE:Marketing (Energy and Utilities)
Send PM
Re: A newer machine, working alone at its constant rate [#permalink]
given
rate of A, B & C be ; a,b,c
we know that a= 1/2*(b+c)
or say 2a = b+c
target find whether If the three machines are used together, will they require more than 1 hour to fill a production order
i.e a+b+c>1 or not ; or say 3a>1 ; a>1/3

#1
Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.
i.e b+c<4
so value of b+c can be 3.9 , 3,2, 1
therefore value of a can be (3.9/2) ; 1.95 ; (3/2) ; 1,5 ; (2/2) ; 1 ; (1/2) ; .5
so 3a = 5.85,4.5,3,1.5 yes & no insufficient
#2
If the newer machine were to double its rate, it could fill a production order working alone in less than one hour
we know
a= 1/2*(b+c)
and now given double rate ; so a = b+c
target becomes is 2a>1
with double rate a<1
so a = .95,.9,0.5,0.1
so
2a ; 1.9,1.8,1,.2 ; again yes & no
insufficient
from 1 &2
we get we get both yes & no for values a as given under #2
insufficient
OPTION E



gmacforjyoab wrote:
A newer machine, working alone at its constant rate, can fill a production order in half the time required by two older machines working together at their constant rates. If the three machines are used together, will they require more than 1 hour to fill a production order?

(1) Each of the older machines, working alone at its constant rate, can fill half a production order in less than 4 hours.

(2) If the newer machine were to double its rate, it could fill a production order working alone in less than one hour
Senior Manager
Senior Manager
Joined: 19 Oct 2014
Posts: 394
Own Kudos [?]: 328 [0]
Given Kudos: 188
Location: United Arab Emirates
Send PM
Re: A newer machine, working alone at its constant rate [#permalink]
Let the time needed for each old machines be O

Time needed together = O/2

New machine needs time = O/4

Time for 2 old and one new = O/6

Question asks if O/6 > 1 or O > 6

Statement 1:
O < 8

Not sufficient

Statement 2:

O/8 < 1

O <8
Not Sufficient

1&2: Not sufficient

E
Senior Manager
Senior Manager
Joined: 19 Oct 2014
Posts: 394
Own Kudos [?]: 328 [0]
Given Kudos: 188
Location: United Arab Emirates
Send PM
Re: A newer machine, working alone at its constant rate [#permalink]
OE:

This is a challenging question that requires quite a bit of scratch work. In general, yes/no data sufficiency questions involving inequalities and rates can be time-consuming.

We could start with some algebra, even before going to the statements. If the two older machines combined can do 1 production order in t hours, the newer machine can do the same 1 production order in half the time, or t/2 hours. Thus, the two older machines work at a combined rate of 1/t orders per hour, and the newer machine works at the rate of 2/t orders per hour. When the three machines work together, their rates add to a combined rate of 1/t + 2/t = 3/t orders per hour. The time required by all three machines working together to fill 1 production order at the rate of 3/t orders per hour would be 1/(3/t) = t/3 hours. The yes/no question asks whether this t/3 hours is greater than 1 hour, i.e. whether t is greater than 3.

Statement 1 provides enough information to find that t<4 hours. This is not sufficient to answer whether or not t is greater than 3. If each of the older machines can fill ½ production order in less than 4 hours, then both older machines working together could fill 1 entire order in less than 4 hours. Using our algebra from the question stem, t represents this time, so t is less than 4 hours.

Statement 2 provides enough information to find that t<4 hours. This is not sufficient to answer whether or not t is greater than 3. If the newer machine doubles its rate from 2/t to 4/t, it can fill 1 order in 1/(4/t) = t/4 hours. If this t/4 hours is less than 1 hour, then t is less than 4 hours.

Statements 1 and 2 are redundant, so combining them provides no new information. If each statement alone is insufficient, and they are redundant, then both statements combined are still insufficient. Answer E is correct.
User avatar
Non-Human User
Joined: 09 Sep 2013
Posts: 32680
Own Kudos [?]: 822 [0]
Given Kudos: 0
Send PM
Re: A newer machine, working alone at its constant rate [#permalink]
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
GMAT Club Bot
Re: A newer machine, working alone at its constant rate [#permalink]
   1   2 
Moderator:
Math Expert
92915 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne