Last visit was: 18 Nov 2025, 13:37 It is currently 18 Nov 2025, 13:37
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
nick13
Joined: 07 Oct 2023
Last visit: 19 Dec 2023
Posts: 19
Own Kudos:
1,374
 [278]
Posts: 19
Kudos: 1,374
 [278]
9
Kudos
Add Kudos
268
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
chetan2u
User avatar
GMAT Expert
Joined: 02 Aug 2009
Last visit: 15 Nov 2025
Posts: 11,238
Own Kudos:
43,696
 [76]
Given Kudos: 335
Status:Math and DI Expert
Location: India
Concentration: Human Resources, General Management
GMAT Focus 1: 735 Q90 V89 DI81
Products:
Expert
Expert reply
GMAT Focus 1: 735 Q90 V89 DI81
Posts: 11,238
Kudos: 43,696
 [76]
46
Kudos
Add Kudos
30
Bookmarks
Bookmark this Post
User avatar
GradMentors
Joined: 09 Dec 2017
Last visit: 30 Apr 2024
Posts: 57
Own Kudos:
66
 [49]
Given Kudos: 3
Status:GradMentors.org
Location: United States
GMAT 1: 770 Q49 V47
GPA: 3.9
GMAT 1: 770 Q49 V47
Posts: 57
Kudos: 66
 [49]
39
Kudos
Add Kudos
9
Bookmarks
Bookmark this Post
General Discussion
User avatar
gmatophobia
User avatar
Quant Chat Moderator
Joined: 22 Dec 2016
Last visit: 17 Nov 2025
Posts: 3,170
Own Kudos:
10,413
 [3]
Given Kudos: 1,861
Location: India
Concentration: Strategy, Leadership
Posts: 3,170
Kudos: 10,413
 [3]
Kudos
Add Kudos
3
Bookmarks
Bookmark this Post
nick13
Two machines, X and Y, working together at their respective constant rates for 14 hours, and then machine Y, working alone at its constant rate for an additional 4 hours, can produce a total of m items. The time that it takes machine X, working alone at its constant rate, to produce m items is 8 hours less than the time that it takes machine Y, working alone at its constant rate, to produce m items. How many hours does it take machine Y, working alone at its constant rate, to produce m items?

a. 28
b. 30
c. 32
d. 34
e. 36

IMO this a tough one if one tries to solve using an algebraic approach.

  • Assume the rate of Machine X = \(x\)
  • Assume the rate of Machine Y = \(y\)

Two machines, X and Y, working together at their respective constant rates for 14 hours, and then machine Y, working alone at its constant rate for an additional 4 hours, can produce a total of m items.

Inference → To produce m items ⇒ Machine X works for 14 hours, and Machine Y works for 18 hours

14x + 18y = Efforts required to produce m items

The time that it takes machine X, working alone at its constant rate, to produce m items is 8 hours less than the time that it takes machine Y, working alone at its constant rate, to produce m items.

Inference → X is faster than Y

Time taken by machine X to produce m items =\( \frac{\text{Efforts required to produce m items} }{\text{Rate of machine X} }\)

Time taken by machine X to produce m items = \(\frac{14x + 18y}{x} = 14 + 18 \frac{y}{x}\)

Time taken by machine Y to produce m items =\( \frac{\text{Efforts required to produce m items} }{\text{Rate of machine Y} }\)

Time taken by machine Y to produce m items = \(\frac{14x + 18y}{y} = 14\frac{x}{y} + 18 \)

Given

\((14\frac{x}{y} + 18) - (14 + 18 \frac{y}{x}) = 8\)

\(14\frac{x}{y} + 4 - 18 \frac{y}{x} = 8\)

\(14\frac{x}{y} - 18 \frac{y}{x} = 4\)

Dividing by 2, we get

\(7\frac{x}{y} - 9\frac{y}{x} = 2\)

If, time taken by machine X = \( X \); Rate of machine X ⇒ \(x = \frac{1}{X}\)

If, time taken by machine Y = \( Y \); Rate of machine Y ⇒ \(y = \frac{1}{Y}\)

Transforming our equation in terms of \(X\) and \(Y\)

\(7\frac{\frac{1}{X} }{\frac{1}{Y} } - 9\frac{\frac{1}{Y} }{\frac{1}{X} } = 2\)

\(7\frac{Y}{X} - 9\frac{X}{Y} = 2\)

Now we can use the options to our advantage. The options provide us the value of \(Y\); we can calculate the value of \(X\) as shown below -

Attachment:
Screenshot 2023-10-23 081303.png
Screenshot 2023-10-23 081303.png [ 43.86 KiB | Viewed 41775 times ]

My initial hunch is to try Option E first because in that option \(X\) is a multiple of 7, and \(Y\) is a multiple of 9. Hence, the numerator and denominator cancel out when we substitute the values in our equation. No other option provides that advantage (if I were running on a time crunch, I would choose this as my final answer).

LHS = \(7\frac{36}{28} - 9\frac{28}{36}\)

LHS = \(\frac{36}{4} - \frac{28}{4}\)

LHS = \(9 - 7 = 2\)

RHS = \(2\)

Hence, option E matches.

Option E

avigutman - I would love to see your approach to this question. Can this be solved in a shorter way ?
User avatar
KarishmaB
Joined: 16 Oct 2010
Last visit: 18 Nov 2025
Posts: 16,265
Own Kudos:
76,980
 [19]
Given Kudos: 482
Location: Pune, India
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 16,265
Kudos: 76,980
 [19]
14
Kudos
Add Kudos
5
Bookmarks
Bookmark this Post
Two machines, X and Y, working together at their respective constant rates for 14 hours, and then machine Y, working alone at its constant rate for an additional 4 hours, can produce a total of m items. The time that it takes machine X, working alone at its constant rate, to produce m items is 8 hours less than the time that it takes machine Y, working alone at its constant rate, to produce m items. How many hours does it take machine Y, working alone at its constant rate, to produce m items?

A. 28
B. 30
C. 32
D. 34
E. 36

I decided to check on the options and thought of the following:

For the most part (14 hrs), both were working together. Then Y worked for another 4 hrs and hence the work got done in 18 hrs. Perhaps if X had continued working with Y for the whole time, the work may have gotten done in approximately 16 hrs. So if either one of them works alone (assuming equal rate of work for them) they would take 32 hrs alone each. But X is faster and takes 8 hrs less. So I could split the time taken by them into 28 hrs and 36 hrs for X and Y respectively.

Mind you, this is all an approximation but I see the figures in the question stem and the options so I would try 36.
If Y takes 36 hrs and X takes 28 alone, in 18 hrs of Y, he will do half the work and in 14 hrs of X, he will do half the work. Hence it works.

Answer (E)

Check this video for Work Rate concepts: https://youtu.be/88NFTttkJmA
User avatar
Kinshook
User avatar
Major Poster
Joined: 03 Jun 2019
Last visit: 18 Nov 2025
Posts: 5,793
Own Kudos:
5,508
 [18]
Given Kudos: 161
Location: India
GMAT 1: 690 Q50 V34
WE:Engineering (Transportation)
Products:
GMAT 1: 690 Q50 V34
Posts: 5,793
Kudos: 5,508
 [18]
16
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
GIven: Two machines, X and Y, working together at their respective constant rates for 14 hours, and then machine Y, working alone at its constant rate for an additional 4 hours, can produce a total of m items. The time that it takes machine X, working alone at its constant rate, to produce m items is 8 hours less than the time that it takes machine Y, working alone at its constant rate, to produce m items.

Asked: How many hours does it take machine Y, working alone at its constant rate, to produce m items?

Let the time taken by Machine X & Machine Y to produce m items be x & y hours respectively.

14/x + 18/y = 1

y - x = 8
x = y - 8

y = ?

14/(y-8) + 18/y = 1

A. 28
B. 30
C. 32
D. 34
E. 36: 14/28 + 18/36 = 1

IMO E
User avatar
Kinshook
User avatar
Major Poster
Joined: 03 Jun 2019
Last visit: 18 Nov 2025
Posts: 5,793
Own Kudos:
5,508
 [1]
Given Kudos: 161
Location: India
GMAT 1: 690 Q50 V34
WE:Engineering (Transportation)
Products:
GMAT 1: 690 Q50 V34
Posts: 5,793
Kudos: 5,508
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
nick13
Given: Two machines, X and Y, working together at their respective constant rates for 14 hours, and then machine Y, working alone at its constant rate for an additional 4 hours, can produce a total of m items. The time that it takes machine X, working alone at its constant rate, to produce m items is 8 hours less than the time that it takes machine Y, working alone at its constant rate, to produce m items.

Asked: How many hours does it take machine Y, working alone at its constant rate, to produce m items?
Let the time taken by machine X & machine Y to produce m items be x & y hours respectively

14/x + 14/y + 4/y = 1

x = y - 8 

y = ?

14/x + 18/y = 1
14/(y+8) + 18/y = 1
14y + 18(y+8) = y(y+8)
42y + 18*8 = yˆ2 + 8y
yˆ2 - 34y - 2ˆ4*3ˆ2 = 0
yˆ2 - 36y - 4y - 2ˆ4*3ˆ2 = 0
(y-36) - 4(y-36) = 0
(y-4)(y-36) = 0
y = 4 or 36
Since x = y-4 > 0 ; y = 4 is NOT POSSIBLE

y = 36

IMO E
­
User avatar
einstein801
Joined: 23 Jan 2024
Last visit: 18 Feb 2025
Posts: 169
Own Kudos:
178
 [1]
Given Kudos: 138
Posts: 169
Kudos: 178
 [1]
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Hi,

Don't think your first way is right. Half work will take (t+8)/2 less hours which = t/2 + 4. 
chetan2u

nick13
Two machines, X and Y, working together at their respective constant rates for 14 hours, and then machine Y, working alone at its constant rate for an additional 4 hours, can produce a total of m items. The time that it takes machine X, working alone at its constant rate, to produce m items is 8 hours less than the time that it takes machine Y, working alone at its constant rate, to produce m items. How many hours does it take machine Y, working alone at its constant rate, to produce m items?

A. 28
B. 30
C. 32
D. 34
E. 36

A straight forward logical way
Y takes 8 hours more for entire work. So he will take 8/2 or 4 hrs extra to complete half work.
Here too, he is working for 4 hours extra = X works for 14 hrs and Y works for 18 hours 🧐
So, this must be the time for doing half the work by each. Thus X would take 14*2 and Y would take 18*2 or 36 hours.

Another convenient way is to look at total time they work for.
X works for 14 hrs while Y works for 14+4 or 17 hours.
Total work done by X and Y is \(\frac{14}{X}+\frac{18}{Y}\).
As X=Y-8 => \(\frac{14}{Y-8}+\frac{18}{Y}=1\)
(I) Now use options => I would use the most friendly option, the one that would divide the numerator as finally we have to get 1.
36 would fit in perfectly as 36-8 or 28 would have common factors with 14 and 36 would have common factors with 18.
And 36 surely fits in properly. If it had not we would have gone for some other value.
OR
(II) you could solve the equation.
\(\frac{14}{Y-8}+\frac{18}{Y}=1\)
\(14Y+18Y-8*18=Y(Y-8)\)
\(Y^2-40Y+8*18=0\)
\((Y-4)(Y-36)=0\)
Y cannot be less than 8, thus Y is 36

E
­
User avatar
chetan2u
User avatar
GMAT Expert
Joined: 02 Aug 2009
Last visit: 15 Nov 2025
Posts: 11,238
Own Kudos:
Given Kudos: 335
Status:Math and DI Expert
Location: India
Concentration: Human Resources, General Management
GMAT Focus 1: 735 Q90 V89 DI81
Products:
Expert
Expert reply
GMAT Focus 1: 735 Q90 V89 DI81
Posts: 11,238
Kudos: 43,696
Kudos
Add Kudos
Bookmarks
Bookmark this Post
unicornilove
It is perfectly fine. 
Full work: X= t and Y=t+8
hakf work: X=t/2 and Y=(t+8)/2 or t/2 + 4. You are making a mistake by taking t/2 + 4 as the less time. 
X takes (t/2 + 4) - t/2 = 4 hours less and that is exactly what has been mentioned. 
User avatar
HarshavardhanR
Joined: 16 Mar 2023
Last visit: 18 Nov 2025
Posts: 425
Own Kudos:
460
 [14]
Given Kudos: 59
Status:Independent GMAT Tutor
Affiliations: Ex - Director, Subject Matter Expertise at e-GMAT
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 425
Kudos: 460
 [14]
12
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post


Harsha
Attachment:
GMAT-Club-Forum-6fk39cl2.png
GMAT-Club-Forum-6fk39cl2.png [ 287.88 KiB | Viewed 10395 times ]
User avatar
MartyMurray
Joined: 11 Aug 2023
Last visit: 18 Nov 2025
Posts: 1,630
Own Kudos:
6,116
 [8]
Given Kudos: 173
GMAT 1: 800 Q51 V51
Expert
Expert reply
GMAT 1: 800 Q51 V51
Posts: 1,630
Kudos: 6,116
 [8]
8
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Two machines, X and Y, working together at their respective constant rates for 14 hours, and then machine Y, working alone at its constant rate for an additional 4 hours, can produce a total of m items. The time that it takes machine X, working alone at its constant rate, to produce m items is 8 hours less than the time that it takes machine Y, working alone at its constant rate, to produce m items. How many hours does it take machine Y, working alone at its constant rate, to produce m items?

All the given information and the question are about m items. So, we can consider m items 1 completed job.

Since X takes 8 fewer hours than Y takes, X is faster than Y.

Working together, they take 14 + 18 = 32 hours to complete the job. So, Y must take more than 32 hours since, working alone, Y would be slower than X and Y working together.

A. 28
B. 30
C. 32
D. 34
E. 36


So, of the choices, only 34 and 36 are possible values for the number of hours Y takes.

Test 34:

If Y takes 34 hours, X takes 34 - 8 = 26 hours to complete 1 job alone.

So, X's rate is 1/26 per hour and Y's rate is 1/34 per hour.

Using the given information on X and Y working together for 14 and 18 hours to complete 1 job, we get the following:

14/26 + 18/34 = more than 1 completed job since 14/26 and 18/34 are both greater than 1/2.

So, Y must go slower than 1/34 per hour and take more than 34 hours.

We're now done with this question after testing just one answer choice because 36 is the only remaining possible value. So, 36 must be the correct answer.

Just to see how 36 works, though, let's test it.

Test 36:

If Y takes 36 hours, X takes 36 - 8 = 28 hours to complete one job alone.

So, X's rate is 1/28 per hour and Y's rate is 1/36 per hour.

14/28 + 18/36 = 1

28 hours for X and 36 hours for Y work.

Correct answer: E
User avatar
KarishmaB
Joined: 16 Oct 2010
Last visit: 18 Nov 2025
Posts: 16,265
Own Kudos:
76,980
 [1]
Given Kudos: 482
Location: Pune, India
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 16,265
Kudos: 76,980
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
nick13
Two machines, X and Y, working together at their respective constant rates for 14 hours, and then machine Y, working alone at its constant rate for an additional 4 hours, can produce a total of m items. The time that it takes machine X, working alone at its constant rate, to produce m items is 8 hours less than the time that it takes machine Y, working alone at its constant rate, to produce m items. How many hours does it take machine Y, working alone at its constant rate, to produce m items?

A. 28
B. 30
C. 32
D. 34
E. 36

Ratios help you see the answer here quickly.

X works for 14 hrs and Y works for 18 hrs. Difference between the hours is 4. They produce m units.
So if X works for 28 hrs and Y works for 36 hrs, they will produce 2m units. Difference between the hours is 8.

We are given that X working alone to produce m items takes 8 hours less than does Y, working alone to produce m items. Since the difference we obtained between the hrs is 8 for total 2m units, it fits. X working for 28 hrs will produce m units and Y working for 36 hrs will produce m units.

Hence answer would be 36.

Answer (A)

If the values were a bit different, you might have needed to use algebra and equations etc. But knowing that GMAT would not expect too many calculations from us, I would always look at the given numbers and whether they fit to give the answer quickly.

Some other interesting work rate discussion:
https://anaprep.com/arithmetic-avoiding ... work-rate/
https://youtu.be/6CT3AXW-QzA
https://anaprep.com/arithmetic-work-rat ... s-and-all/
User avatar
wtang123
Joined: 16 Apr 2021
Last visit: 25 Jan 2025
Posts: 6
Own Kudos:
3
 [1]
Given Kudos: 32
Posts: 6
Kudos: 3
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
This is probably a slower approach but this was the method that initially came to my mind.

14(x + y) + 4y = m → 14x + 18y = m

The time it takes to produce m units is 8 hours less for Machine X
m/x = m/y - 8 → 8 = m/y - mx → 8 = m(x - y)/xy → m = 8xy/(x-y)

Substituting for m
14x + 18y = 8xy/(x-y) → 14x2 - 4xy - 18y2 = 0 → 7x2 - 2xy - 9y2 = 0 → (7x - 9y)(x + y) = 0

Rate cannot be negative so the only solution is 7x = 9y or (7/9)x = y

Since we know X takes 8 hours less to produce m units, an equation can be formed
x(t - 8) = yt → x(t - 8) = (7/9)xt → t - 8 = (7/9)t → (2/9)t = 8 → t = 36
User avatar
hemanthPA
Joined: 09 Mar 2023
Last visit: 18 Mar 2025
Posts: 50
Own Kudos:
35
 [1]
Given Kudos: 11
Posts: 50
Kudos: 35
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
nick13
Two machines, X and Y, working together at their respective constant rates for 14 hours, and then machine Y, working alone at its constant rate for an additional 4 hours, can produce a total of m items. The time that it takes machine X, working alone at its constant rate, to produce m items is 8 hours less than the time that it takes machine Y, working alone at its constant rate, to produce m items. How many hours does it take machine Y, working alone at its constant rate, to produce m items?

A. 28
B. 30
C. 32
D. 34
E. 36


Hey guys, we all know this is a time consuming, mad problem but here is the simplest solution for you. it cannot get any simpler than this.

First visualise and know the basics of work, rate and time. i.e., w = r.t or r = w/t, and consider the below terms
Work done by X – Wx
Work done by Y – Wy
Time taken by X – Tx
Time taken by Y – Ty

VISUALIZE - VISUALIZATION IS THE KEY


it is given that in the beginning X and Y work together work for 14 hrs, then x is no more there and y work for the remaining 4 hrs
From this, we can derive our main equation
To do 1 unit of work, i.e., M as they said x works for 14hrs, Y works for 14hrs and Y works an additional of 4 hrs

So work done by X and Y individually to complete 1 unit (or M amount) of work would be
Wx + Wy = 1
14/Tx + 14/Ty + 4/Ty = 1
14/Tx + 18/Ty = 1
Next they have given the relationship, Tx = Ty – 8

Now coming until here must take you about a min, at max. now lets just plug in the options and see for what values of Tx and Ty we get 1, this must be relatively simple and error free. We need to follow the AEBDC method.

Plug options and check in the order AEBDC in the equation 14/tx + 16/ty = 1 work units, with the relation tx = ty – 8
Given options are for ty

Option A. Ty = 28, tx = 20, this will be 14/20 + 18/28 = 7/10 + 9/14 = (98 + 90) / 140 which is not equal to 1
Option D. Ty = 36, tx = 28, this will be 14/28 + 18/36 = 1⁄2 + 1⁄2 = 1 units of work, hence ty = 36hrs

Viola! as simple as that, under 2 mins.

THANKS TO MY NEW TUTOR SAM, i learnt these tricks!!
Attachment:
GMAT-Club-Forum-ymf07q97.png
GMAT-Club-Forum-ymf07q97.png [ 13.3 KiB | Viewed 1778 times ]
User avatar
KPBAN
Joined: 23 Oct 2024
Last visit: 01 Jan 2025
Posts: 8
Own Kudos:
Posts: 8
Kudos: 6
Kudos
Add Kudos
Bookmarks
Bookmark this Post
nick13
Two machines, X and Y, working together at their respective constant rates for 14 hours, and then machine Y, working alone at its constant rate for an additional 4 hours, can produce a total of m items. The time that it takes machine X, working alone at its constant rate, to produce m items is 8 hours less than the time that it takes machine Y, working alone at its constant rate, to produce m items. How many hours does it take machine Y, working alone at its constant rate, to produce m items?

A. 28
B. 30
C. 32
D. 34
E. 36
For simplicity lets say the rate for machine X and machine Y is x and y and the units of work required to produce m items be M

Then 14(x+y) + 4y = M implies 14x + 18y = M (Eqn 1)

Let the time taken by X alone to produce m items be T1 and time taken by Y alone to produce m items be T2

Then (T1-8) * x = T2 * y = M

Which can be re written as (T1-8) * x + T2 * y = 2*M implies that (T1-8) * x + T2 * y = 28x + 36 y (From eqn 1). We can directly conclude that T2 is 36
User avatar
sarthak1701
Joined: 11 Sep 2024
Last visit: 16 Nov 2025
Posts: 110
Own Kudos:
Given Kudos: 18
GMAT Focus 1: 575 Q77 V81 DI78
GMAT Focus 1: 575 Q77 V81 DI78
Posts: 110
Kudos: 50
Kudos
Add Kudos
Bookmarks
Bookmark this Post
LCM of 14 and 18 is 126, so M is a multiple of 126. But the LCM allows us to get the rates of X and Y

9*14 = 126 (X's rate) and 7*18 = 126 (Y's rate)

Now, 9*T-8 = M and 7*T = M

Equating we get, 9T-72 = 7T = 2T = 72, T = 36.

Ans. E

EDIT: The solution is wrong but somehow I still got the answer right, keeping this up so others don't make the same mistake.
User avatar
Dream009
Joined: 05 Nov 2024
Last visit: 31 Oct 2025
Posts: 200
Own Kudos:
Given Kudos: 54
Location: India
Concentration: Strategy, Leadership
GPA: 84
WE:General Management (Consulting)
Products:
Posts: 200
Kudos: 50
Kudos
Add Kudos
Bookmarks
Bookmark this Post
time of x is y-8 not effort - how can you write x= y-8
chetan2u



A straight forward logical way
Y takes 8 hours more for entire work. So he will take 8/2 or 4 hrs extra to complete half work.
Here too, he is working for 4 hours extra = X works for 14 hrs and Y works for 18 hours 🧐
So, this must be the time for doing half the work by each. Thus X would take 14*2 and Y would take 18*2 or 36 hours.

Another convenient way is to look at total time they work for.
X works for 14 hrs while Y works for 14+4 or 17 hours.
Total work done by X and Y is \(\frac{14}{X}+\frac{18}{Y}\).
As X=Y-8 => \(\frac{14}{Y-8}+\frac{18}{Y}=1\)
(I) Now use options => I would use the most friendly option, the one that would divide the numerator as finally we have to get 1.
36 would fit in perfectly as 36-8 or 28 would have common factors with 14 and 36 would have common factors with 18.
And 36 surely fits in properly. If it had not we would have gone for some other value.
OR
(II) you could solve the equation.
\(\frac{14}{Y-8}+\frac{18}{Y}=1\)
\(14Y+18Y-8*18=Y(Y-8)\)
\(Y^2-40Y+8*18=0\)
\((Y-4)(Y-36)=0\)
Y cannot be less than 8, thus Y is 36

E
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 18 Nov 2025
Posts: 105,355
Own Kudos:
Given Kudos: 99,964
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 105,355
Kudos: 778,060
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Dream009
time of x is y-8 not effort - how can you write x= y-8


In that setup, Y represents the number of hours machine Y takes alone to produce m items, and X represents the number of hours machine X takes alone to produce the same m items.

So:
• X’s rate = 1/X
• Y’s rate = 1/Y

X worked for 14 hours, and Y worked for 18 hours, producing a total of m items (one complete job). Hence, the total work equation is:
14/X + 18/Y = 1

Since X = Y - 8, we get:
14/(Y - 8) + 18/Y = 1
User avatar
nihilre
Joined: 03 Nov 2025
Last visit: 17 Nov 2025
Posts: 15
Given Kudos: 34
Posts: 15
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
god bless you chetan2u
chetan2u



A straight forward logical way
Y takes 8 hours more for entire work. So he will take 8/2 or 4 hrs extra to complete half work.
Here too, he is working for 4 hours extra = X works for 14 hrs and Y works for 18 hours 🧐
So, this must be the time for doing half the work by each. Thus X would take 14*2 and Y would take 18*2 or 36 hours.

Another convenient way is to look at total time they work for.
X works for 14 hrs while Y works for 14+4 or 17 hours.
Total work done by X and Y is \(\frac{14}{X}+\frac{18}{Y}\).
As X=Y-8 => \(\frac{14}{Y-8}+\frac{18}{Y}=1\)
(I) Now use options => I would use the most friendly option, the one that would divide the numerator as finally we have to get 1.
36 would fit in perfectly as 36-8 or 28 would have common factors with 14 and 36 would have common factors with 18.
And 36 surely fits in properly. If it had not we would have gone for some other value.
OR
(II) you could solve the equation.
\(\frac{14}{Y-8}+\frac{18}{Y}=1\)
\(14Y+18Y-8*18=Y(Y-8)\)
\(Y^2-40Y+8*18=0\)
\((Y-4)(Y-36)=0\)
Y cannot be less than 8, thus Y is 36

E
Moderators:
Math Expert
105355 posts
Tuck School Moderator
805 posts