pesfunk
Perfect Answer

Economist
Bunuel
Please find below new set of PS problems:
4. A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?
(A) 4
(B) 5
(C) 6
(D) 7
(E) 8
Nobody attempted 4, let me give a try.
total work = 110*10 = 1100 man days
now, from day 1 to day 55, 10 men worked = 550 man days of work was done.
from day 61 to day 100, 16 men worked = 640 man days of work was done.
so total work done should be 1190, the 90 days offset is due to rain on few days between 61 to 100th day...so the number
of rainy days should be 90/16=5.625 ~ 6.C.
I found one more solution to this problem by Bunnel but the answer is 5... that is B..
But here its mentioned C...
4. A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?
(A) 4
(B) 5
(C) 6
(D) 7
(E) 8
This one was solved incorrectly:
Days to finish the job for 10 people 110 days.
On the 61-st day, after 5 days of rain --> 5 days was rain, 55 days they worked, thus completed 1/2 of the job, 1/2 is left (55 days of work for 10 people).
Then 6 more people was hired --> speed of construction increased by 1.6, days needed to finish 55/1.6=34.375, BUT after they were hired job was done in
100-60=40 days --> so 5 days rained. They needed MORE than 34 days to finish the job, so if it rained for 6 days they wouldn't be able to finish the job in 100(40) days.
Answer: B.