The argument hinges on the conclusion that the environmental engineer's methodology for estimating reclamation costs must have been faulty, based on the significant discrepancy between the initial estimate and the actual cost. To support this conclusion, the argument depends on an assumption that rules out other possible reasons for the underestimation.
Let’s evaluate each option to see which one captures an essential assumption of the argument.
Option Analysis
A) Though more expensive than originally thought, the reclamation still would have resulted in a profitable development.
This option addresses profitability rather than the accuracy of the engineer’s estimate or methodology. The profitability of the project does not impact the argument about the methodology's accuracy, so this is irrelevant.
B) The environmental engineer did not study other reclamation sites and use the same methodology to estimate costs.
This option provides background on how the engineer might have approached the estimate, but it does not directly address whether the engineer's specific methodology was flawed or not. The fact that the engineer used or didn’t use data from other sites does not logically affect the conclusion about faultiness.
C) The REIT had successfully reclaimed land in other developments during the past few years.
While this may add context, it doesn’t provide evidence regarding the accuracy or faultiness of the engineer’s estimation methodology. Past success in other developments does not directly impact the argument here.
D) A third party determined that the REIT’s methodology for determining the cost to reclaim the brown-field site was more accurate than that used by the environmental engineer.
This option strengthens the argument by supporting the REIT’s assessment of higher costs, but it doesn’t directly address whether the engineer’s methodology was flawed; it simply offers another perspective on accuracy.
E) The engineer and land developer did not purposefully misrepresent the cost to reclaim the development site.
Correct Answer:
This option is essential to the argument. If the engineer or developer had intentionally misrepresented the cost, the discrepancy might not be due to a flawed methodology but rather due to a deliberate understatement. Therefore, the argument that the methodology was faulty relies on the assumption that the estimate was made in good faith and without intentional misrepresentation.Conclusion
The correct answer is E, as it provides the necessary assumption that the engineer's methodology (and not deliberate misrepresentation) is to blame for the inaccurate estimate.