A can complete a piece of work in 4 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. They are paired in groups of two each. One pair takes two-thirds the time needed by the second pair to complete the work.
Which is the first pair?
A can complete a piece of work in = 4 days
B can complete a piece of work in = 8 days
C can complete a piece of work in = 16 days
D can complete a piece of work in = 32 days
Part of work done by A in a day = 1/4
Part of work done by B in a day = 1/8
Part of work done by C in a day = 1/16
Part of work done by D in a day = 1/32
Total number of pairs = 4C2 = 6 = {(A,B), (A,C), (A,D), (B,C), (B,D), (C,D)}
Part of work done by (A, B) = 1/4 + 1/8 = 3/8
Part of work done by (A, C) = 1/4 + 1/16 = 5/16
Part of work done by (A, D) = 1/4 + 1/32 = 9/32
Part of work done by (B, C) = 1/8 + 1/16 = 3/16
Part of work done by (B, D) = 1/8 + 1/32 = 5/32
Part of work done by (C, D) = 1/16 + 1/32 = 3/32
Time taken by (A, B) to complete the work = 8/3 days
Time taken by (A, C) to complete the work = 16/5 days
Time taken by (A, D) to complete the work = 32/9 days
Time taken by (B, C) to complete the work = 16/3 days
Time taken by (B, D) to complete the work = 32/5 days
Time taken by (C, D) to complete the work = 32/3 days
32/9 = 2/3 * 16/3
First pair = (A, D); Second pair = (B, C)
IMO D