Right Answer Explanation / Suggested Answer :
Let the work done by A in one day be A, that by B be B, and that by C be C.
Let the total work be W.
As A and B together can do the work in 40 days, we have
40(A + B) = W
Or A + B = ... (i)
Now, work done by A and B in 10 days = 10(A + B) ... (ii)
Plugging in the value of A + B from equation (i) in terms of W into equation (ii), we get
Work done by A and B in 10 days = 10(A + B) = =
Work left to be done =
This work is done by A, B and C in 20 days.
Work done by A, B and C in 20 days = 20(A + B + C) = ... (iii)
Now, work done by C in 2 days = work done by B in 3 days
So, 2C = 3B
Or C = B ... (iv)
Now, plugging in the value of A as - B from equation (i) and the value of C as B from equation (iv) into equation (iii), we get
120B = W
Or B = ... (v)
So, A =
Let the number of days taken by A to do the work alone be 'd'.
So, dA = W
Or = W
Or d = 60
Let the number of days taken by B to do the work be 'f'.
So, fB = W
Or = W
Or f = 120
As C takes 2 days to do the work that B does in 3 days, C takes = 80 days to do the same work.
Thus, A, B and C respectively take 60, 120 and 80 days to do the work alone.
Thus, answer option 4 is correct.
Amity007
A and B together can do a piece of work in 40 days. After working for 10 days, they get assistance from C and the work is finished in another 20 days. If C does as much work in 2 days as B does in 3 days, in how many days can A, B and C do the same work alone, respectively?
(Source=TCYOnline)
A. 50, 100, 70
B. 60, 110, 75
C. 70, 120, 90
D. 60, 120, 80
E. 50, 90, 70