Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.
Customized for You
we will pick new questions that match your level based on your Timer History
Track Your Progress
every week, we’ll send you an estimated GMAT score based on your performance
Practice Pays
we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Thank you for using the timer!
We noticed you are actually not timing your practice. Click the START button first next time you use the timer.
There are many benefits to timing your practice, including:
Struggling with GMAT Verbal as a non-native speaker? Harsh improved his score from 595 to 695 in just 45 days—and scored a 99 %ile in Verbal (V88)! Learn how smart strategy, clarity, and guided prep helped him gain 100 points.
At one point, she believed GMAT wasn’t for her. After scoring 595, self-doubt crept in and she questioned her potential. But instead of quitting, she made the right strategic changes. The result? A remarkable comeback to 695. Check out how Saakshi did it.
The Target Test Prep course represents a quantum leap forward in GMAT preparation, a radical reinterpretation of the way that students should study. Try before you buy with a 5-day, full-access trial of the course for FREE!
Prefer video-based learning? The Target Test Prep OnDemand course is a one-of-a-kind video masterclass featuring 400 hours of lecture-style teaching by Scott Woodbury-Stewart, founder of Target Test Prep and one of the most accomplished GMAT instructors
Tom, working alone, can paint a room in 6 hours. Peter and John, working independently, can paint the same room in 3 hours and 2 hours, respectively. Tom starts painting the room and works on his own for one hour. He is then joined by Peter and they work together for an hour. Finally, John joins them and the three of them work together to finish the room, each one working at his respective rate. What fraction of the whole job was done by Peter?
1/9
1/6
1/3
7/18
4/9
Archived Topic
Hi there,
This topic has been closed and archived due to inactivity or violation of community quality standards. No more replies are possible here.
Still interested in this question? Check out the "Best Topics" block below for a better discussion on this exact question, as well as several more related questions.
Ok, Tom's rate is 1/6, Peter's rate is 1/3, and John's rate is 1/2
Tom first worked for one hour, therefore 1/6 of the job is done, hence 5/6 left.
Then Peter joins in and they both worked one hour (1/6+1/3)*1=3/6, another 3/6 of the job is done. There are 1-1/6-3/6=2/6 of job left. Then John joins in. (1/6+1/3+1/2)*X=2/6 from this equation you know that it took them 1/3 hour to finish the rest of the job. Therefore, Peter worked a total of 1 and 1/3 hour. It usually took him 3 hours for the whole job, so the fraction he did is (4/3)/3 or 4/9.
Tom -> 1 room in 6 hours -> 1/6 room in 1 hour
Peter -> 1 room in 3 hours -> 1/3 room in 1 hour
John -> 1 room in 2 hour -> 1/2 room in 1 hour
Tom and Peter together = 1/2 room in 1 hour
Tom and Peter and John = 1 room in 1 hour
So Tom starts first and paints 1/6 of the room
Then Peter joins in for an hour and they finish up 1/2 of the room. (total 2/3 painted)
Finally John comes along and they finish up the remaining 1/3 of the room. This takes 1/3 of an hour to complete.
SO Peter works 4/3 hours and in this amount of time, he would have painted 4/3*1/3 = 4/9 of a room.
Tom, working alone, can paint a room in 6 hours. Peter and John, working independently, can paint the same room in 3 hours and 2 hours, respectively. Tom starts painting the room and works on his own for one hour. He is then joined by Peter and they work together for an hour. Finally, John joins them and the three of them work together to finish the room, each one working at his respective rate. What fraction of the whole job was done by Peter?
1/9 1/6 1/3 7/18 4/9
Show more
ughhhh super combined rate problems...
First hour Tom completes 1/6 of the job. so there is 5/6 of the job remaining.
Second hour Tom+Peter 1/6+1/3=3/6 so 3/6 of the job was completed.
2/6 of the job is remaining.
now remaining time Tom+Peter+John =6/6 or 1. using d=rt ->2/6=t1
or t=1/3 of an hour. So Tom Peter and John worked the following hours:
T:2 1/3 hours. P: 1 1/3 hours J: 1/3 hour.
We are looking for the total work done by Peter so again us d=rt. d=1/3*1 1/3 hrs. or d=1/3*4/3 d= 4/9
Ans E.
You can also find out the d for the other two workers. T: d=1/6*7/3 -->7/18
J: d=1/2*1/3= 1/6
Archived Topic
Hi there,
This topic has been closed and archived due to inactivity or violation of community quality standards. No more replies are possible here.
Still interested in this question? Check out the "Best Topics" block above for a better discussion on this exact question, as well as several more related questions.