Last visit was: 24 Apr 2026, 05:13 It is currently 24 Apr 2026, 05:13
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
kishankolli
Joined: 30 Sep 2008
Last visit: 24 Sep 2009
Posts: 8
Own Kudos:
Posts: 8
Kudos: 72
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
spiridon
Joined: 04 Aug 2008
Last visit: 25 Jul 2011
Posts: 274
Own Kudos:
Given Kudos: 1
Posts: 274
Kudos: 127
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
smahamkl
Joined: 27 Sep 2008
Last visit: 14 Oct 2008
Posts: 6
Own Kudos:
Posts: 6
Kudos: 258
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
leonidas
Joined: 29 Mar 2008
Last visit: 03 Aug 2009
Posts: 215
Own Kudos:
Posts: 215
Kudos: 366
Kudos
Add Kudos
Bookmarks
Bookmark this Post
(1/3)*(5/6) + (1/3)*(2/6) = 7/18

1st hr = 1/6 of work done.
Remaining work = 5/6. Peter does (1/3)*(5/6) =5/18 of the work ----(1)

2nd hr = 1/6 + 1/3 = 3/6 of work is done => In two hrs (1/6+3/6)= 4/6 work is done
Remaining work = 1-(4/6) = 2/6

Peter does 1/3* 2/6 = 2/18 of total work. ...(2)

(1) + (2) = 7/18
User avatar
amitdgr
Joined: 30 Jun 2008
Last visit: 21 May 2013
Posts: 534
Own Kudos:
Given Kudos: 1
Posts: 534
Kudos: 3,212
Kudos
Add Kudos
Bookmarks
Bookmark this Post
leonidas
(1/3)*(5/6) + (1/3)*(2/6) = 7/18

1st hr = 1/6 of work done.
Remaining work = 5/6. Peter does (1/3)*(5/6) =5/18 of the work ----(1)

2nd hr = 1/6 + 1/3 = 3/6 of work is done => In two hrs (1/6+3/6)= 4/6 work is done
Remaining work = 1-(4/6) = 2/6

Peter does 1/3* 2/6 = 2/18 of total work. ...(2)

(1) + (2) = 7/18

leonidas... why are we calculating remaining work here ?
User avatar
leonidas
Joined: 29 Mar 2008
Last visit: 03 Aug 2009
Posts: 215
Own Kudos:
Posts: 215
Kudos: 366
Kudos
Add Kudos
Bookmarks
Bookmark this Post
amitdgr
leonidas
(1/3)*(5/6) + (1/3)*(2/6) = 7/18

1st hr = 1/6 of work done.
Remaining work = 5/6. Peter does (1/3)*(5/6) =5/18 of the work ----(1)

2nd hr = 1/6 + 1/3 = 3/6 of work is done => In two hrs (1/6+3/6)= 4/6 work is done
Remaining work = 1-(4/6) = 2/6

Peter does 1/3* 2/6 = 2/18 of total work. ...(2)

(1) + (2) = 7/18

leonidas... why are we calculating remaining work here ?

We have to know Peter's contribution in the last leg. By calculating the total work in the first 2 hours, remaining work can be calculated and hence peter's contribution in the last leg (i.e remaining work after 2 hours). Did I confuse you?
User avatar
kishankolli
Joined: 30 Sep 2008
Last visit: 24 Sep 2009
Posts: 8
Own Kudos:
Posts: 8
Kudos: 72
Kudos
Add Kudos
Bookmarks
Bookmark this Post
7/18 was the initial answer even I got.. But the OA is "E"
User avatar
scthakur
Joined: 17 Jun 2008
Last visit: 30 Jul 2009
Posts: 608
Own Kudos:
Posts: 608
Kudos: 453
Kudos
Add Kudos
Bookmarks
Bookmark this Post
smahamkl
Please let me knoe if I am doing anything wrong here:

In the first 1 hr, Tom covered = 1/6R
In the second hr, Tom and Peter coverd = 1/6R + 1/3R
So in two hrs, they combinedly covered = 2/3R
which leaves, only 1/3R to be covered.
Now all of them joined and completed the work in the next X hrs
=> X/6R + X/3R + X/2R = R/3
=> X = 1/3 Hrs

So in 1/3rd hour John should have painted the fraction of (1/3)(1/2R) = R/6


Question is asking for Peter....hence it will be (1/3)*(R/6) = R/18.

Hence, total work done by peter = R(1/6 + 1/6 + 1/18) = 7R/18.
User avatar
amitdgr
Joined: 30 Jun 2008
Last visit: 21 May 2013
Posts: 534
Own Kudos:
Given Kudos: 1
Posts: 534
Kudos: 3,212
Kudos
Add Kudos
Bookmarks
Bookmark this Post
kishankolli
7/18 was the initial answer even I got.. But the OA is "E"

OA is E ?? Does the source have any explanation ?
User avatar
leonidas
Joined: 29 Mar 2008
Last visit: 03 Aug 2009
Posts: 215
Own Kudos:
Posts: 215
Kudos: 366
Kudos
Add Kudos
Bookmarks
Bookmark this Post
I made a mistake on (1)
Remaining work = 5/6. Peter does (1/3)*(5/6) =5/18 of the work ----(1)

Here I am double counting P's work

1/6 + (1/6 + 1/3) = 4/6 is done...i.e 1/3 is remaining aftre hr 2
now 3 of them who work in the ratio of 1/6:1/3:1/2 will work on the remaining work which is 1/3 of total work
so P worked: 1/3 + .33/(.167+.334+0.5)*1/3
: 1/3 + 1/9 = 4/9

I make so many mistakes :(
User avatar
kishankolli
Joined: 30 Sep 2008
Last visit: 24 Sep 2009
Posts: 8
Own Kudos:
Posts: 8
Kudos: 72
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Tom's individual rate is 1 job / 6 hours or 1/6 job/hr ("job per hour").
During the hour that Tom works alone, he completes 1/6 of the job, using rt = w: (1/6 job/hr) x 1 hr = 1/6 job.

Peter's individual rate is 1 job / 3 hours or 1/3 job/hr.
Peter joins Tom and they work together for another hour; Peter and Tom's respective individual rates can be added together to calculate their combined rate: 1/6 + 1/3 = 1/2 job/hr.
Working together then they will complete 1/2 of the job in the 1 hour they work together.

At this point, 2/3 of the job has been completed (1/6 by Peter alone + 1/2 by Peter and Tom), and 1/3 remains.

When John joins Tom and Peter, the new combined rate for all three is: 1/6 + 1/3 + 1/2 = 1 job/hr.
The time that it will take them to finish the remaining 1/3 of the job can be solved:
rt = w -> (1 job/hr)(t) = 1/3 job -> t = 1/3 hr.

The question asks us for the fraction of the job that Peter completed. In the hour that Peter worked with Tom he alone completed: rt = w -> w = (1/3 job/hr) x (1 hr) = 1/3 of the job.

In the last 1/3 of an hour that all three worked together, Peter alone completed:
(1/3 job/hr) x (1/3 hr) = 1/9 of the job.
Adding these two values together, we get 1/3 job + 1/9 job = 4/9 of the job.

So E....
User avatar
spiridon
Joined: 04 Aug 2008
Last visit: 25 Jul 2011
Posts: 274
Own Kudos:
Given Kudos: 1
Posts: 274
Kudos: 127
Kudos
Add Kudos
Bookmarks
Bookmark this Post
yeah it is E...

doubt i will got this right on gmat

would select D in a hurry



Archived Topic
Hi there,
This topic has been closed and archived due to inactivity or violation of community quality standards. No more replies are possible here.
Where to now? Join ongoing discussions on thousands of quality questions in our Quantitative Questions Forum
Still interested in this question? Check out the "Best Topics" block above for a better discussion on this exact question, as well as several more related questions.
Thank you for understanding, and happy exploring!