Last visit was: 22 Apr 2026, 02:18 It is currently 22 Apr 2026, 02:18
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Caas
Joined: 04 Mar 2007
Last visit: 13 Aug 2007
Posts: 180
Own Kudos:
Posts: 180
Kudos: 864
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Hayabusa
Joined: 22 May 2007
Last visit: 15 Sep 2008
Posts: 46
Own Kudos:
Posts: 46
Kudos: 15
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
ggarr
Joined: 12 Jun 2006
Last visit: 20 Mar 2010
Posts: 263
Own Kudos:
Given Kudos: 1
Posts: 263
Kudos: 842
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Hayabusa
Joined: 22 May 2007
Last visit: 15 Sep 2008
Posts: 46
Own Kudos:
Posts: 46
Kudos: 15
Kudos
Add Kudos
Bookmarks
Bookmark this Post
If 3 machines have to work 8 hrs per day in order to complete the job and one machine broke, wouldn't they have to work more than 8 hours per day in order to make up ???
User avatar
KillerSquirrel
Joined: 08 Jun 2005
Last visit: 28 Mar 2009
Posts: 520
Own Kudos:
Posts: 520
Kudos: 647
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Hayabusa is right.

total task will take 240 hours to finish = 3*8*10 (three machines *eight hours a day*ten days)

since the three machines already worked 2 days they worked for 2*8*3 = 48 hours.

240 - 48 = 192 hours left

since we are left with 2 working machines:

192/2 = 96 hours

and we still have 8 working days:

96/8 = 12

the answer is 12 hours a day !

:-D
User avatar
Mishari
Joined: 30 Nov 2006
Last visit: 23 Feb 2015
Posts: 352
Own Kudos:
Location: Kuwait
Concentration: Strategy - Finance
Posts: 352
Kudos: 922
Kudos
Add Kudos
Bookmarks
Bookmark this Post
3 identical machines each working 8 hours a day, together can complete a task in 10 days. After working together for 2 days, one machine broke. How many hours a day should each of the remaining machines work to complete the task on time?

3 Machines: X,X, andX
10 days = 80 hours/job for all three machines
OR 1/80 job/hour

1/T = 3/X = 1/80 --> X = 240 hours/ job
For two days [ 16 hours ], the three machines completed 16*1/80 = 1/5 of the job. [4/5 left yet to complete]

2 machines together work at the rate:
1/T = 1/X + 1/X = 2/X = 2/240 = 1/120
T = 120 hours/job OR 1/120 job/hour

Remaining hours to complete the job for two machines working together:

4/5 job x 120 hours/job = 96 hours

Since only 8 days are left to finish the job [assuming a 10 days period contract to end the job, as described in the problem], each of the remaining machine needs to work for 96/8 = 12 hours a day


ANSWER: 12 hours/day
User avatar
ggarr
Joined: 12 Jun 2006
Last visit: 20 Mar 2010
Posts: 263
Own Kudos:
Given Kudos: 1
Posts: 263
Kudos: 842
Kudos
Add Kudos
Bookmarks
Bookmark this Post
the end of this prob is confusing me. Hayabusa is right that it makes no sense that the machines are working less time, so 6 is wrong. but isn't 96 hrs being split b/w 2 machines? if so, why isn't it 96/2 = 48 total hrs over 8 days. what the %&*# am I missing?
User avatar
Mishari
Joined: 30 Nov 2006
Last visit: 23 Feb 2015
Posts: 352
Own Kudos:
Location: Kuwait
Concentration: Strategy - Finance
Posts: 352
Kudos: 922
Kudos
Add Kudos
Bookmarks
Bookmark this Post
For my solution, the calculated number of hours left is for each one of the two machines, not for both machines. So no need to split the hours between the two, as long as I've used a combined rate of work. Get it ?
User avatar
ggarr
Joined: 12 Jun 2006
Last visit: 20 Mar 2010
Posts: 263
Own Kudos:
Given Kudos: 1
Posts: 263
Kudos: 842
Kudos
Add Kudos
Bookmarks
Bookmark this Post
yes, just when I was gonna post the answer to my own question I saw your response. thanks. yes, 96 hrs are split across 2 machines. I failed to divide 48 hrs (the # of hrs it'd take 1 machine to complete the job) by 4 (the # of days that 1 machine would work). I divided 48 by 8, the # of hrs it'd take 1 machine to complete the job by the # of days it'd take both machines to complete the job.
User avatar
vidyasagar
Joined: 04 Feb 2007
Last visit: 02 Jun 2008
Posts: 19
Own Kudos:
Posts: 19
Kudos: 5
Kudos
Add Kudos
Bookmarks
Bookmark this Post
M/C----HRS/DAY----TOTAL-DAYS-----WORK-PROPORTION

3--------8---------------10---------------------100% (1 WORK)

3--------8----------------2---------------------20% (1/5 WORK).OBIVOUS

2--------x----------------8---------------------80% (4/5 WORK)

=> 8/x=(2/3)*(8/2)* (20/80)

=> X=12 DAYS
User avatar
grad_mba
Joined: 13 Mar 2007
Last visit: 24 May 2011
Posts: 349
Own Kudos:
Schools:MIT Sloan
Posts: 349
Kudos: 580
Kudos
Add Kudos
Bookmarks
Bookmark this Post
do we need Math at all for this problem ??

3 - identical machines - work at same rate

so if one machine breaks - the load will equally be shared by other two

8/2 = 4hrs

hence 8 + 4 = 12hrs !
User avatar
ywilfred
Joined: 07 Jul 2004
Last visit: 06 Mar 2012
Posts: 1,987
Own Kudos:
Location: Singapore
Posts: 1,987
Kudos: 2,051
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Each day, the three machine clears 3*8 = 24 hours worth of work.
So over 10 days, there are 240 hours worth of work.

After two days, 48 hours of work is cleared. This leaves 192 hours to be shared among two machines and we want this to be completed within 8 days.

2*x*8 = 192
x = 12 hours.
User avatar
Caas
Joined: 04 Mar 2007
Last visit: 13 Aug 2007
Posts: 180
Own Kudos:
Posts: 180
Kudos: 864
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Thank you all for your various solutions.

I think grad_mba's way is the easiest :)



Archived Topic
Hi there,
This topic has been closed and archived due to inactivity or violation of community quality standards. No more replies are possible here.
Where to now? Join ongoing discussions on thousands of quality questions in our Problem Solving (PS) Forum
Still interested in this question? Check out the "Best Topics" block above for a better discussion on this exact question, as well as several more related questions.
Thank you for understanding, and happy exploring!
Moderator:
Math Expert
109740 posts